IDOT contract 61M18 bid tabulation
Hazel Crest, section 25-00097-00-RS. Let by Illinois DOT on February 27, 2026, Cook, District 01. 5 bids received; low bid $399,778 by Gallagher Asphalt Corporation.
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 54
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Gallagher Asphalt Corporation | $399,778 | Low |
| 2 | Davis Concrete Construction Co. | $426,537 | +7.0% |
| 3 | D. Construction, Inc. | $438,582 | +10% |
| 4 | K-Five Construction Corporation | $446,470 | +12% |
| 5 | M & J Underground Inc. | $609,219 | +52% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Gallagher Asphalt Corporation | 2. Davis Concrete Construction Co. | 3. D. Construction, Inc. | 4. K-Five Construction Corporation | 5. M & J Underground Inc. |
|---|---|---|---|---|---|---|---|---|
| 1 | Prun safety/equip CLR (K1004595) | LS | 1 | $6,500.00 | $300.00 | $4,000.00 | $8,000.00 | $5,000.00 |
| 2 | Temp access- priv ent (X4021000) | EACH | 6 | $145.00 | $10.00 | $700.00 | $10.00 | $762.44 |
| 3 | Temp access- com ent (X4022000) | EACH | 1 | $175.00 | $25.00 | $1,000.00 | $10.00 | $885.41 |
| 4 | HMA driveway pavt 4 (X4060282) | SY | 174 | $69.00 | $75.00 | $30.00 | $73.00 | $95.84 |
| 5 | Sanitary manhole adj (X6026050) | EACH | 2 | $990.00 | $1,390.00 | $1,500.00 | $1,200.00 | $956.49 |
| 6 | FR & lids adjust SPL (X6030310) | EACH | 11 | $500.00 | $1,200.00 | $1,000.00 | $1,100.00 | $1,628.43 |
| 7 | Temp info signing (X7200061) | SF | 54 | $35.00 | $35.00 | $30.00 | $35.00 | $36.04 |
| 8 | Drain util STR adj (Z0017400) | EACH | 26 | $300.00 | $520.00 | $600.00 | $390.00 | $458.73 |
| 9 | Drain util STR recon (Z0017700) | EACH | 2 | $1,350.00 | $1,500.00 | $2,000.00 | $900.00 | $2,469.88 |
| 10 | Tree trunk protection (20101100) | EACH | 10 | $12.00 | $10.00 | $165.00 | $250.00 | $87.34 |
| 11 | Tree root pruning (20101200) | EACH | 10 | $12.00 | $10.00 | $136.40 | $200.00 | $178.81 |
| 12 | Nitrogen fert nutr (20101400) | LB | 35 | $6.00 | $3.00 | $3.30 | $3.00 | $3.09 |
| 13 | Phosphorus fert nutr (20101500) | LB | 35 | $6.00 | $3.00 | $3.30 | $3.00 | $3.09 |
| 14 | Potassium fert nutr (20101600) | LB | 35 | $6.00 | $3.00 | $3.30 | $3.00 | $3.09 |
| 15 | Earth excavation (20200100) | CY | 5 | $90.00 | $20.00 | $100.00 | $75.00 | $14.35 |
| 16 | Rem & disp uns matl (20201200) | CY | 20 | $80.00 | $20.00 | $100.00 | $50.00 | $114.29 |
| 17 | Topsoil F & P 4 (21101615) | SY | 765 | $10.00 | $6.00 | $6.60 | $6.00 | $5.15 |
| 18 | Sodding salt tolerant (25200110) | SY | 765 | $14.00 | $10.00 | $27.50 | $25.00 | $128.70 |
| 19 | Supple watering (25200200) | UNIT | 42 | $99.00 | $0.01 | $0.01 | $0.01 | $128.70 |
| 20 | Inlet filters (28000510) | EACH | 30 | $120.00 | $10.00 | $250.80 | $275.00 | $210.26 |
| 21 | Agg subgrade improve (30300001) | CY | 20 | $100.00 | $20.00 | $50.00 | $50.00 | $120.72 |
| 22 | Agg base cse B 4 (35101600) | SY | 555 | $13.00 | $8.50 | $8.50 | $3.60 | $13.26 |
| 23 | Bit matls tack CT (40600290) | LB | 4,790 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 24 | Long joint sealant (40600370) | LF | 2,510 | $5.00 | $5.80 | $5.23 | $5.00 | $4.98 |
| 25 | Mix CR JTS flangewys (40600400) | TON | 10 | $50.00 | $410.00 | $0.01 | $50.00 | $0.01 |
| 26 | HMA surf rem butt JT (40600982) | SY | 100 | $0.01 | $10.00 | $15.00 | $3.80 | $0.01 |
| 27 | P HMA BC IL-4.75 N50 (40603200) | TON | 285 | $113.00 | $125.00 | $101.00 | $157.20 | $126.25 |
| 28 | HMA SC IL-9.5 D N50 (40604060) | TON | 580 | $95.00 | $99.00 | $84.00 | $100.92 | $92.15 |
| 29 | PCC driveway pavt 7 (42300300) | SY | 75 | $105.00 | $95.00 | $90.00 | $90.00 | $147.75 |
| 30 | PC conc sidewalk 5 (42400200) | SF | 4,735 | $7.90 | $8.90 | $10.00 | $10.00 | $9.77 |
| 31 | Detectable warnings (42400800) | SF | 140 | $22.00 | $22.00 | $35.00 | $25.00 | $23.38 |
| 32 | HMA surf rem 2 (44000157) | SY | 6,890 | $3.50 | $3.70 | $2.25 | $3.92 | $10.97 |
| 33 | Drive pavement rem (44000200) | SY | 245 | $27.50 | $25.00 | $12.00 | $29.05 | $32.17 |
| 34 | Comb curb gutter rem (44000500) | LF | 1,770 | $14.00 | $16.00 | $10.00 | $10.00 | $16.09 |
| 35 | Sidewalk rem (44000600) | SF | 4,220 | $3.00 | $2.80 | $3.00 | $1.00 | $3.72 |
| 36 | CL D patch T3 8 (44201745) | SY | 25 | $133.00 | $139.00 | $100.00 | $217.00 | $36.86 |
| 37 | CL D patch T4 8 (44201747) | SY | 75 | $75.00 | $80.00 | $100.00 | $212.00 | $36.86 |
| 38 | FR & grates T11 (60404800) | EACH | 5 | $450.00 | $625.00 | $600.00 | $650.00 | $590.62 |
| 39 | FR & grates T12 (60404900) | EACH | 7 | $450.00 | $1,140.00 | $600.00 | $750.00 | $720.52 |
| 40 | FR & lids T1 OL (60406000) | EACH | 1 | $430.00 | $435.00 | $600.00 | $400.00 | $364.96 |
| 41 | Comb CC&G TB6.12 (60603800) | LF | 305 | $29.00 | $29.90 | $40.00 | $30.00 | $50.48 |
| 42 | Comb CC&G TM4.12 (60608562) | LF | 1,465 | $29.00 | $29.90 | $40.00 | $29.00 | $41.93 |
| 43 | Mobilization (67100100) | LS | 1 | $22,011 | $32,020 | $24,042 | $26,000 | $18,000 |
| 44 | TR cont & prot 701501 (70102620) | LS | 1 | $4,000.00 | $4,000.00 | $19,025 | $4,500.00 | $4,118.39 |
| 45 | TR cont & prot 701801 (70102640) | LS | 1 | $350.00 | $350.00 | $0.01 | $400.00 | $360.36 |
| 46 | Short term pavt mking (70300100) | LF | 230 | $0.01 | $1.00 | $0.01 | $1.50 | $2.01 |
| 47 | SHRT TRM pavt MK rem (70300150) | SF | 80 | $0.03 | $1.00 | $0.01 | $1.00 | $5.02 |
| 48 | Sign panel T1 (72000100) | SF | 105 | $35.00 | $35.00 | $27.50 | $35.00 | $36.04 |
| 49 | Reloc sin pan assy TA (72400500) | EACH | 4 | $300.00 | $300.00 | $302.50 | $300.00 | $15.44 |
| 50 | Metal post TY A (72900100) | LF | 210 | $15.00 | $15.00 | $14.30 | $15.00 | $15.44 |
| 51 | THPL PVT MK line 4 (78000200) | LF | 2,845 | $1.00 | $1.00 | $1.10 | $1.00 | $1.03 |
| 52 | THPL PVT MK line 6 (78000400) | LF | 330 | $2.00 | $2.00 | $2.20 | $2.00 | $2.06 |
| 53 | THPL PVT MK line 12 (78000600) | LF | 180 | $4.00 | $4.00 | $4.40 | $4.00 | $4.12 |
| 54 | THPL PVT MK line 24 (78000650) | LF | 40 | $8.00 | $8.00 | $8.80 | $8.00 | $8.24 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.