IDOT contract 62V08 bid tabulation
Section 2023. Let by Illinois DOT on June 12, 2026, Cook, District 01. 3 bids received; low bid $1,863,322 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 12 JUN 2026
- Pay items
- 113
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $1,863,322 | Low |
| 2 | Martam Construction Incorporated | $2,921,524 | +57% |
| 3 | V3 Construction Group, LTD. | $2,989,833 | +60% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Martam Construction Incorporated | 3. V3 Construction Group, LTD. |
|---|---|---|---|---|---|---|
| 1 | Mulch placement 4 (K0036120) | SY | 20 | $19.80 | $22.00 | $28.77 |
| 2 | TV inspect of sewer (X0325207) | LF | 672 | $25.50 | $4.68 | $9.21 |
| 3 | Stump removal only (X2010400) | UNIT | 2,081 | $10.25 | $9.35 | $10.36 |
| 4 | Earth excavation SPL (X2020410) | CY | 161 | $60.00 | $178.26 | $90.56 |
| 5 | Seeding CL 4 mod (X2501800) | ACRE | 2 | $3,154.80 | $4,400.00 | $9,333.22 |
| 6 | Seeding CL 5 mod (X2501820) | ACRE | 2 | $5,823.40 | $5,500.00 | $7,900.44 |
| 7 | Box culvert removal (X5400005) | LF | 42 | $0.01 | $480.59 | $116.44 |
| 8 | Rem & reloc end sect (X5427600) | EACH | 2 | $1,500.00 | $6,041.17 | $1,610.12 |
| 9 | Storm sewer repair (X5510008) | LF | 50 | $225.00 | $627.50 | $94.68 |
| 10 | SS cleaned 15 (X5537900) | LF | 89 | $16.50 | $4.68 | $34.52 |
| 11 | SS cleaned 36 (X5538600) | LF | 583 | $49.50 | $7.81 | $46.03 |
| 12 | Memb WTRPRF sys B STR (X5810103) | SY | 27 | $150.00 | $95.44 | $196.80 |
| 13 | Fence removal (X6640104) | LF | 92 | $11.44 | $26.25 | $10.30 |
| 14 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $5,000.00 | $6,389.04 | $5,754.14 |
| 15 | Temp info signing (X7200061) | SF | 151.70 | $35.00 | $17.60 | $3.45 |
| 16 | Detour signing (X7200203) | LS | 1 | $27,500 | $27,500 | $14,385 |
| 17 | Remov sign complete (X7240205) | EACH | 1 | $302.50 | $168.49 | $1,726.24 |
| 18 | Rem RE-erect EX sign (X7240600) | EACH | 6 | $467.50 | $935.00 | $978.20 |
| 19 | Temp TR signal timing (X8900104) | EACH | 3 | $990.00 | $990.00 | $1,035.75 |
| 20 | Construction layout (Z0013798) | LS | 1 | $41,000 | $69,129 | $41,430 |
| 21 | Drainage STR repair (Z0018300) | EACH | 1 | $2,000.00 | $2,772.17 | $2,854.47 |
| 22 | Drainage STR cleaned (Z0018500) | EACH | 1 | $4,400.00 | $467.50 | $1,726.24 |
| 23 | Drainage STR reconst (Z0018600) | EACH | 2 | $2,000.00 | $1,868.74 | $3,327.88 |
| 24 | Rock fill (Z0054400) | CY | 104 | $75.00 | $62.94 | $86.34 |
| 25 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 26 | Tree trunk protection (20101100) | EACH | 66 | $250.00 | $148.50 | $287.71 |
| 27 | Earth excavation (20200100) | CY | 2,930 | $35.00 | $104.87 | $98.00 |
| 28 | Rem & disp uns matl (20201200) | CY | 790 | $40.00 | $101.55 | $73.66 |
| 29 | Channel excavation (20300100) | CY | 625 | $30.00 | $116.43 | $101.59 |
| 30 | Porous gran embank (20700220) | CY | 38 | $65.00 | $144.58 | $72.70 |
| 31 | Trench backfill (20800150) | CY | 10 | $100.00 | $152.22 | $143.53 |
| 32 | Gran embank spec (21000310) | CY | 90 | $65.00 | $171.09 | $64.86 |
| 33 | Geotech fab F/GR stab (21001000) | SY | 743 | $5.00 | $3.84 | $3.05 |
| 34 | Topsoil F & P 4 (21101615) | SY | 9,836 | $6.60 | $8.69 | $30.98 |
| 35 | Topsoil F & P 6 (21101625) | SY | 1,147 | $9.90 | $12.27 | $41.98 |
| 36 | Grading & shap ditch (21400100) | LF | 5,481 | $25.00 | $24.05 | $26.32 |
| 37 | Seeding CL 1B (25000115) | ACRE | 2 | $5,343.80 | $1,760.00 | $3,763.21 |
| 38 | Seeding CL 2A (25000210) | ACRE | 1 | $5,462.60 | $3,300.00 | $3,958.85 |
| 39 | Seeding CL 3 (25000300) | ACRE | 0.75 | $4,291.10 | $5,665.00 | $6,076.37 |
| 40 | Nitrogen fert nutr (25000400) | LB | 236 | $4.40 | $3.96 | $6.90 |
| 41 | Potassium fert nutr (25000600) | LB | 236 | $4.40 | $3.96 | $3.45 |
| 42 | Wildlife friendly ecb (25100645) | SY | 8,729 | $2.97 | $2.33 | $2.24 |
| 43 | Temp eros contr seed (28000250) | LB | 307 | $5.50 | $8.80 | $9.21 |
| 44 | Temp ditch checks (28000305) | LF | 930 | $6.71 | $12.65 | $11.51 |
| 45 | Agg ditch checks (28000315) | TON | 66 | $60.00 | $86.42 | $143.00 |
| 46 | Perimeter eros bar (28000400) | LF | 11,038 | $3.30 | $3.63 | $6.78 |
| 47 | Inlet & pipe protect (28000500) | EACH | 15 | $121.00 | $165.00 | $345.25 |
| 48 | Inlet filters (28000510) | EACH | 2 | $250.00 | $308.00 | $345.25 |
| 49 | Temp WLDLF frndly ecb (28001105) | SY | 14,691 | $2.86 | $1.27 | $1.96 |
| 50 | Stone riprap CL A3 (28100105) | SY | 1,018 | $75.00 | $98.44 | $63.94 |
| 51 | Stone riprap CL A4 (28100107) | SY | 535 | $80.00 | $138.19 | $118.80 |
| 52 | Stone riprap CL A5 (28100109) | SY | 564 | $90.00 | $151.28 | $149.99 |
| 53 | Filter fabric (28200200) | SY | 1,553 | $5.00 | $3.84 | $3.14 |
| 54 | Gabions (28400100) | CY | 105 | $400.00 | $667.99 | $1,221.77 |
| 55 | Slope mattress 12 (28401000) | SY | 133 | $167.00 | $312.80 | $334.55 |
| 56 | Agg subgrade improve (30300001) | CY | 20 | $80.00 | $111.03 | $144.14 |
| 57 | Agg subgrade impr 12 (30300112) | SY | 433 | $22.00 | $37.26 | $42.41 |
| 58 | Bit matls PR CT (40600275) | LB | 706 | $0.01 | $0.01 | $1.15 |
| 59 | Bit matls tack CT (40600290) | LB | 706 | $0.01 | $0.01 | $1.15 |
| 60 | Long joint sealant (40600370) | LF | 100 | $115.00 | $55.00 | $57.54 |
| 61 | HMA pavt FD 10 (40701881) | SY | 140 | $90.00 | $275.00 | $201.39 |
| 62 | Pavement rem (44000100) | SY | 50 | $50.00 | $49.97 | $88.83 |
| 63 | Paved SHLD removal (44004250) | SY | 226 | $25.00 | $48.77 | $26.73 |
| 64 | Aggregate SHLDS B (48101202) | CY | 10 | $100.00 | $165.50 | $154.39 |
| 65 | Agg wedge SHLD type B (48102100) | TON | 5 | $200.00 | $102.30 | $129.77 |
| 66 | HMA shoulders 8 (48203029) | SY | 226 | $52.00 | $151.80 | $138.10 |
| 67 | HMA shoulders 10 (48203037) | SY | 45 | $100.00 | $330.00 | $258.94 |
| 68 | Rem exist struct (50100100) | EACH | 1 | $0.01 | $40,019 | $14,116 |
| 69 | Rem/disp uns matl-STR (50200450) | CY | 84 | $40.00 | $107.35 | $39.93 |
| 70 | Cofferdam typ 1 loc 1 (50201101) | EACH | 3 | $0.01 | $30,220 | $18,936 |
| 71 | Temp soil reten systm (52200020) | SF | 1,170 | $37.50 | $50.30 | $5.90 |
| 72 | Box cul end sec C1 (54001001) | EACH | 2 | $7,800.00 | $23,621 | $40,596 |
| 73 | PCBC 3X2 (54010302) | LF | 39 | $680.00 | $2,554.93 | $2,346.87 |
| 74 | PRC flar end sec 15 (54213660) | EACH | 1 | $2,000.00 | $2,380.72 | $2,192.94 |
| 75 | Storm sew CL A 1 15 (550A0070) | LF | 15 | $200.00 | $273.56 | $267.95 |
| 76 | Storm sewer rem 6 (55100200) | LF | 4 | $20.00 | $28.96 | $253.96 |
| 77 | Storm sewer rem 12 (55100500) | LF | 19 | $20.00 | $40.31 | $108.75 |
| 78 | Storm sewer rem 15 (55100700) | LF | 15 | $20.00 | $40.37 | $137.75 |
| 79 | Geocomposite wall DR (59100100) | SY | 27 | $50.00 | $76.35 | $196.80 |
| 80 | Man adjust (60255500) | EACH | 1 | $1,000.00 | $1,780.56 | $2,854.47 |
| 81 | Grates T8 (60402210) | EACH | 1 | $1,000.00 | $531.05 | $600.55 |
| 82 | Box cul to BE cleaned (60905305) | LF | 194 | $100.00 | $110.00 | $115.08 |
| 83 | Pipe culv cleaned 15 (60920015) | LF | 19 | $110.00 | $7.15 | $40.28 |
| 84 | Pipe culv cleaned 18 (60920018) | LF | 64 | $110.00 | $9.35 | $40.28 |
| 85 | Pipe culv cleaned 30 (60920030) | LF | 18 | $200.00 | $22.00 | $69.05 |
| 86 | SPBGR TY A 6FT posts (63000001) | LF | 37.50 | $40.04 | $96.17 | $143.85 |
| 87 | Traf bar term T6B (63100089) | EACH | 1 | $6,479.00 | $4,883.73 | $10,357 |
| 88 | TR bar TRM T1 SPL tan (63100167) | EACH | 1 | $3,769.70 | $4,264.38 | $9,782.04 |
| 89 | Guardrail remov (63200310) | LF | 112.50 | $9.85 | $21.46 | $11.51 |
| 90 | Shoulder rum strip 8 (64200108) | LF | 100 | $47.75 | $27.46 | $57.54 |
| 91 | CH LK fence 5 (66400205) | LF | 1,723 | $45.18 | $35.83 | $47.26 |
| 92 | Non SPL waste disposl (66900200) | CY | 2,075 | $100.00 | $98.74 | $97.47 |
| 93 | Soil disposal analy (66900530) | EACH | 8 | $1,750.00 | $990.00 | $1,380.99 |
| 94 | Reg sub P-const plan (66901001) | LS | 1 | $2,500.00 | $6,380.00 | $9,782.04 |
| 95 | Reg sub F con report (66901003) | LS | 1 | $2,500.00 | $550.00 | $9,782.04 |
| 96 | Reg sub mon (66901006) | CAL DAY | 13 | $2,000.00 | $825.00 | $1,611.16 |
| 97 | Mobilization (67100100) | LS | 1 | $109,877 | $175,291 | $346,140 |
| 98 | Traf cont-prot 701421 (70100310) | LS | 1 | $0.01 | $132,422 | $11,508 |
| 99 | Traf cont-prot 701201 (70100450) | LS | 1 | $141,500 | $199,202 | $4,603.31 |
| 100 | Traf cont-prot 701306 (70100460) | LS | 1 | $0.01 | $1.10 | $4,603.31 |
| 101 | Traf cont-prot 701336 (70100600) | LS | 1 | $0.01 | $1.10 | $4,603.31 |
| 102 | TR cont & prot 701501 (70102620) | LS | 1 | $0.01 | $2,750.00 | $5,754.14 |
| 103 | TR cont & prot 701606 (70102625) | LS | 1 | $0.01 | $3,850.00 | $11,508 |
| 104 | TR cont & prot 701601 (70102630) | LS | 1 | $0.01 | $2,200.00 | $8,631.21 |
| 105 | TR cont & prot 701701 (70102635) | LS | 1 | $0.01 | $1.10 | $5,754.14 |
| 106 | TR cont & prot 701801 (70102640) | LS | 1 | $0.01 | $3,300.00 | $1,726.24 |
| 107 | Short term pavt mking (70300100) | LF | 200 | $5.00 | $12.10 | $12.66 |
| 108 | SHRT TRM pavt MK rem (70300150) | SF | 67 | $1.00 | $22.00 | $23.02 |
| 109 | Terminal marker - DA (72501000) | EACH | 1 | $55.00 | $56.84 | $1,726.24 |
| 110 | THPL PVT MK line 4 (78000200) | LF | 200 | $28.60 | $28.60 | $17.26 |
| 111 | Raised refl pavt MKR (78100100) | EACH | 2 | $2,640.00 | $2,475.00 | $1,726.24 |
| 112 | Grdrail ref type A (78200005) | EACH | 1 | $27.50 | $15.46 | $28.77 |
| 113 | Raised ref PVT MK rem (78300200) | EACH | 2 | $100.00 | $141.66 | $1,150.83 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.