IDOT contract 62Y12 bid tabulation

Section (21B-NRM-4)BR. Let by Illinois DOT on September 19, 2025, Cook, District 01. 5 bids received; low bid $955,094 by Martam Construction Incorporated.

Owner
Illinois DOT
Letting
19 SEP 2025
Pay items
60
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Martam Construction Incorporated$955,094Low
2Lorig Construction Company$995,321+4.0%
3Rausch Infrastructure, LLC$1,092,103+14%
4Areatha Construction Co., Inc.$1,269,133+33%
5MYS, Incorporated$1,391,730+46%
IDOT contract 62Y12: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Martam Construction Incorporated2. Lorig Construction Company3. Rausch Infrastructure, LLC4. Areatha Construction Co., Inc.5. MYS, Incorporated
1Graffiti removal (X0300062)SY169$97.00$95.00$99.00$88.05$97.69
2Rem & rein bric paver (X0327611)SF144$18.00$13.00$73.00$60.50$37.72
3CC&G RMVL repl > 10FT (X4400503)LF256$65.00$125.00$90.00$138.75$90.22
4BR deck grooving long (X5030250)SY657$13.00$13.00$12.00$11.25$16.64
5SS cleaned 12 (X5537800)LF120$5.00$1.00$1.00$10.00$33.28
6Engrs FLD ofc TY A D1 (X6700407)CAL MO6$3,600.00$4,000.00$6,000.00$2,500.00$4,455.57
7Traf cont & prot SPL (X7010216)LS1$112,900$120,000$41,000$19,500$36,856
8Temp info signing (X7200061)SF57$14.00$18.00$13.00$20.00$27.73
9Appr slab repair (FD) (Z0001700)SY5$1,600.00$950.00$3,000.00$1,947.55$3,974.26
10Appr slab repair (PD) (Z0001800)SY30$800.00$925.00$1,400.00$975.70$1,849.25
11BR DK LTX C oly 2 3/4 (Z0006016)SY654$142.00$170.00$169.00$338.65$235.40
12BR deck scar 3/4 (Z0012130)SY656$61.00$90.00$129.00$217.00$133.92
13STR rep con DP = < 5 (Z0012754)SF187$220.00$273.00$237.00$185.00$255.12
14STR rep con DP over 5 (Z0012755)SF6$235.00$800.00$254.00$276.85$277.30
15Debris removal (Z0015550)CY20$158.00$100.00$866.00$483.50$915.71
16Deck slab rep (FD-T2) (Z0016002)SY1.50$4,500.00$2,500.00$11,000$2,510.25$4,037.47
17Drainage STR cleaned (Z0018500)EACH4$1,100.00$1,000.00$1,050.00$2,000.00$887.36
18Diamond grind BR sec (Z0029090)SY657$17.00$16.00$17.00$22.35$33.28
19Polymer concrete (Z0041895)CF3.90$1,150.00$2,200.00$2,700.00$3,990.70$2,271.78
20Temp shoring & crib (Z0073200)EACH1$12,600$3,000.00$19,000$16,382$42,379
21Earth excavation (20200100)CY19$178.00$90.00$200.00$64.20$189.60
22Bit matls tack CT (40600290)LB262$9.00$8.00$9.00$8.00$0.01
23Long joint sealant (40600370)LF363$27.00$25.00$28.00$25.00$9.98
24HMA surf rem butt JT (40600982)SY581$1.00$20.00$22.00$20.00$44.37
25HMA SC IL-9.5 D N70 (40604062)TON57$550.00$510.00$565.00$500.00$811.56
26PCC driveway pavt 6 (42300200)SY23$135.00$140.00$163.00$244.05$131.79
27PC conc sidewalk 5 (42400200)SF1,670$15.00$17.00$16.00$14.65$15.00
28Sidewalk rem (44000600)SF1,876$2.00$4.00$7.00$5.25$4.31
29Conc rem (50102400)CY53.40$2,100.00$2,000.00$1,300.00$2,329.55$2,218.40
30Protective shield (50157300)SY598$0.10$1.00$95.00$25.00$132.99
31Conc sup-STR (50300255)CY57.50$2,400.00$1,900.00$2,200.00$2,963.85$3,383.06
32Protective coat (50300300)SY726$1.00$1.80$13.00$3.90$5.90
33Reinf bars, epoxy CTD (50800205)LB2,830$5.00$3.25$2.90$5.90$6.74
34Bar splicers (50800515)EACH28$65.00$67.00$133.00$66.80$75.01
35Pref JT strip seal (52000110)LF135$325.00$325.00$365.00$550.75$311.78
36FR & lids adjust (60300305)EACH7$600.00$2,000.00$1,186.00$135.70$644.72
37Rem RE-E T B term T1 (63301990)EACH4$2,300.00$1,950.00$2,195.00$1,943.00$4,575.45
38Non SPL waste disposl (66900200)CY20$95.00$120.00$120.00$184.50$175.02
39Soil disposal analy (66900530)EACH1$1,600.00$2,000.00$2,260.00$1,600.00$2,218.40
40Reg sub P-const plan (66901001)LS1$3,500.00$2,300.00$2,599.00$3,400.00$3,882.20
41Reg sub F con report (66901003)LS1$600.00$2,100.00$2,373.00$500.00$3,882.20
42Reg sub mon (66901006)CAL DAY2$800.00$1,300.00$1,412.00$800.00$1,386.50
43Mobilization (67100100)LS1$56,000$55,000$65,000$76,500$93,880
44Changeable message SN (70107025)CAL DAY60$35.00$30.00$33.00$50.00$33.28
45SHRT TRM pavt MK rem (70300150)SF2,069$0.40$0.40$0.30$0.60$1.22
46Temp PVT MK line 6 - paint (70300241)LF553$0.60$0.60$0.50$1.20$6.10
47Temp PVT MK LTR & sym T4 tape (70307100)SF52$4.00$4.00$4.10$5.00$5.55
48Temp PVT MK L4 T4 tape (70307120)LF4,851$1.20$1.25$1.30$1.30$1.24
49Temp PVT MK L6 T4 tape (70307130)LF77$2.00$2.00$1.90$2.50$2.02
50Temp PVT MK L8 T4 tape (70307140)LF16$6.00$3.00$5.60$4.00$5.55
51Temp PVT MK L12 T4 tape (70307160)LF75$4.00$5.00$3.90$8.00$5.55
52Temp conc barrier (70400100)LF312$55.00$33.00$60.00$53.00$75.98
53Rel temp conc barrier (70400200)LF312$10.00$7.00$10.00$16.00$13.31
54Imp attn temp NRN TL2 (70600241)EACH2$2,700.00$3,500.00$2,825.00$4,600.00$8,319.00
55Imp attn rel NRN TL2 (70600341)EACH2$600.00$1,300.00$565.00$1,500.00$4,159.50
56Pref PL PM TD STD L4 (78004620)LF148$28.00$12.00$33.90$26.00$26.62
57Mod ureth PM line 4 (78009004)LF1,266$6.00$5.00$3.30$5.00$3.05
58Mod ureth PM line 24 (78009024)LF100$22.00$10.00$20.30$20.00$19.97
59GRV RCSD PVT MRKG 5 (78011025)LF148$20.00$8.00$28.20$18.00$26.34
60PVT MKG rem WTR blast (78300202)SF666$4.00$8.00$3.90$5.65$13.86
IDOT contract 62Y12: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy