IDOT contract 72973 bid tabulation
Section K(B-1)BJR,BDR. Let by Illinois DOT on June 13, 2025, Menard, District 06. 3 bids received; low bid $1,947,800 by Otto Baum Company, Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 42
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Otto Baum Company, Inc. | $1,947,800 | Low |
| 2 | Freesen, a div of UCM, Inc. | $1,981,958 | +2.0% |
| 3 | Sangamo Construction Company | $2,016,220 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Otto Baum Company, Inc. | 2. Freesen, a div of UCM, Inc. | 3. Sangamo Construction Company |
|---|---|---|---|---|---|---|
| 1 | BR deck grooving long (X5030250) | SY | 3,580 | $18.38 | $14.86 | $10.58 |
| 2 | Drainage scuppers adj (X5230172) | EACH | 30 | $540.69 | $799.66 | $1,505.72 |
| 3 | Width restrict sign (X7200201) | LS | 1 | $2,392.81 | $2,362.50 | $4,756.85 |
| 4 | Appr slab repair (PD) (Z0001800) | SY | 10 | $976.52 | $1,253.71 | $1,059.19 |
| 5 | BR deck scar 3/4 (Z0012130) | SY | 4,694 | $76.27 | $47.25 | $44.82 |
| 6 | BR DK mic C ovl 2 3/4 (Z0012166) | SY | 4,694 | $88.68 | $128.94 | $108.46 |
| 7 | STR rep con DP = < 5 (Z0012754) | SF | 70 | $388.85 | $255.99 | $290.82 |
| 8 | Deck slab rep (FD-T1) (Z0016001) | SY | 10 | $1,681.92 | $1,723.18 | $1,780.35 |
| 9 | Diamond grind BR sec (Z0029090) | SY | 4,800 | $12.37 | $12.58 | $10.96 |
| 10 | Modular expan JT 9 (Z0034393) | LF | 42 | $3,609.80 | $4,609.85 | $4,480.99 |
| 11 | Temp shoring & crib (Z0073200) | EACH | 2 | $15,525 | $10,019 | $14,581 |
| 12 | Trainees TPG (Z0076604) | HR | 1,500 | $15.00 | $15.00 | $15.00 |
| 13 | Base cse widening 8 (35650300) | SY | 303 | $144.68 | $140.37 | $110.66 |
| 14 | Bit matls tack CT (40600290) | LB | 960 | $1.33 | $2.33 | $1.32 |
| 15 | HMA surf rem butt JT (40600982) | SY | 356 | $34.62 | $37.16 | $34.45 |
| 16 | Temporary ramp (40600990) | SY | 86 | $15.95 | $12.90 | $72.97 |
| 17 | HMA BC IL-9.5 N50 (40602978) | TON | 25 | $223.49 | $333.59 | $222.39 |
| 18 | HMA SC IL-9.5 C N50 (40604050) | TON | 140 | $22.49 | $316.58 | $222.39 |
| 19 | Paved SHLD removal (44004250) | SY | 303 | $63.68 | $58.65 | $53.70 |
| 20 | Agg wedge SHLD type B (48102100) | TON | 40 | $138.64 | $103.50 | $119.21 |
| 21 | Conc rem (50102400) | CY | 29.10 | $2,525.71 | $2,997.35 | $3,086.67 |
| 22 | Conc sup-STR (50300255) | CY | 36.40 | $4,219.18 | $3,543.04 | $4,007.03 |
| 23 | Protective coat (50300300) | SY | 4,772 | $4.72 | $3.47 | $3.43 |
| 24 | Stud shear connectors (50500505) | EACH | 8 | $63.81 | $63.00 | $63.50 |
| 25 | Reinf bars, epoxy CTD (50800205) | LB | 5,580 | $3.26 | $2.55 | $2.61 |
| 26 | Bar splicers (50800515) | EACH | 72 | $44.49 | $70.25 | $60.71 |
| 27 | Mechanical splicers (50800530) | EACH | 143 | $66.76 | $71.59 | $74.91 |
| 28 | Pref JT strip seal (52000110) | LF | 126 | $369.02 | $332.77 | $362.36 |
| 29 | Engr field office A (67000400) | CAL MO | 12 | $1,379.14 | $4,196.54 | $2,791.67 |
| 30 | Mobilization (67100100) | LS | 1 | $124,714 | $58,005 | $118,957 |
| 31 | Traf cont-prot 701321 (70100405) | EACH | 1 | $23,875 | $31,159 | $53,603 |
| 32 | Traf cont-prot 701201 (70100450) | LS | 1 | $850.78 | $3,528.72 | $9,789.83 |
| 33 | Traf cont-prot 701326 (70100500) | LS | 1 | $1,648.39 | $2,835.00 | $4,745.15 |
| 34 | Temp BR traf signals (70106500) | EACH | 1 | $24,041 | $23,625 | $33,335 |
| 35 | Temp rumble strips (70106700) | EACH | 6 | $1,515.45 | $525.00 | $1,406.05 |
| 36 | Changeable message SN (70107025) | CAL DAY | 300 | $106.35 | $46.46 | $72.11 |
| 37 | Temp conc barrier (70400100) | LF | 1,700 | $40.94 | $38.06 | $52.89 |
| 38 | Rel temp conc barrier (70400200) | LF | 1,700 | $6.38 | $3.81 | $9.54 |
| 39 | Imp attn temp NRD TL3 (70600250) | EACH | 2 | $5,175.83 | $4,042.50 | $5,592.08 |
| 40 | Imp attn rel NRN TL3 (70600352) | EACH | 2 | $1,080.89 | $1,360.25 | $1,562.98 |
| 41 | Mod ureth PM line 5 (78009005) | LF | 9,000 | $1.89 | $1.87 | $1.88 |
| 42 | PVT MKG rem grinding (78300201) | SF | 1,400 | $5.85 | $5.25 | $5.29 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.