IDOT contract 76A46 bid tabulation

Section 51-1R. Let by Illinois DOT on January 16, 2026, Madison, District 08. 2 bids received; low bid $17,570,642 by Keller Construction, Inc..

Owner
Illinois DOT
Letting
16 JAN 2026
Pay items
222
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Keller Construction, Inc.$17,570,642Low
2Millstone Weber LLC$21,372,296+22%
IDOT contract 76A46: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Keller Construction, Inc.2. Millstone Weber LLC
1Ped truss superstr (X0322508)SF1,920.70$158.34$170.00
2Fold down bollards (X0350805)EACH1$1,496.25$2,000.00
3Concrete pad removal (X1700114)SF2,660$1.75$0.64
4Retaining wall remov (X5220102)LF277$98.00$15.25
5Fence removal (X6640104)LF159$16.85$18.50
6Wood rail (X6640632)LF32$138.00$190.00
7Row/property corners (X6660445)EACH40$463.00$500.00
8Traf cont & prot SPL (X7010216)LS1$12,338$190,000
9Detour signing (X7200203)LS1$25,977$40,000
10Paint PVT mark curb (X7800200)LF293$5.25$16.50
11Ethernet switch (X8710103)EACH1$6,037.50$5,800.00
12Accessible ped signal (X8760200)EACH4$1,128.75$1,100.00
13Video veh det sys (X8891001)EACH1$43,181$41,000
14BR approach SHLD rem (Z0001495)SY45$92.30$39.00
15Bollards (Z0004002)EACH2$1,029.00$5,000.00
16HMA drivwy pavt rem (Z0004544)SY924$15.50$27.50
17Approach slab rem (Z0004552)SY129$125.00$88.00
18BLDG remov no 1 (Z0007601)LS1$3,000.00$920.00
19BLDG remov no 2 (Z0007602)LS1$3,000.00$920.00
20BLDG remov no 3 (Z0007603)LS1$3,000.00$920.00
21Construction layout (Z0013798)LS1$78,000$508,000
22SS 1 wat MN 15 (Z0056650)LF218$100.00$180.00
23SS 1 wat MN 24 (Z0056654)LF107$162.00$240.00
24SS 1 wat MN 36 (Z0056657)LF42$437.00$450.00
25SS 2 wat MN 24 (Z0056672)LF30$212.00$280.00
26SS 2 wat MN 42 (Z0056682)LF50$510.00$590.00
27Temp TR signal timing (Z0073510)EACH1$5,880.00$5,600.00
28Trainees (Z0076600)HR3,000$0.80$0.80
29Trainees TPG (Z0076604)HR3,000$15.00$15.00
30Tree remov 6-15 (20100110)UNIT21$133.00$150.00
31Tree remov over 15 (20100210)UNIT191$102.00$100.00
32Tree remov acres (20100500)ACRE0.43$37,000$60,000
33Earth excavation (20200100)CY23,025$17.00$30.00
34Channel excavation (20300100)CY11,270$15.00$45.00
35Furnished excavation (20400800)CY2,000$32.00$41.00
36Seeding CL 2A (25000210)ACRE5.75$2,400.00$3,000.00
37Nitrogen fert nutr (25000400)LB523$2.40$1.30
38Phosphorus fert nutr (25000500)LB523$2.40$1.30
39Potassium fert nutr (25000600)LB523$2.40$1.30
40Mulch method 2 (25100115)ACRE5.75$4,970.00$2,300.00
41Temp ditch checks (28000305)LF1,050$7.25$14.00
42Perimeter eros bar (28000400)LF1,942$3.50$6.30
43Inlet & pipe protect (28000500)EACH9$100.00$620.00
44Inlet filters (28000510)EACH24$280.00$610.00
45Stone riprap CL A6 (28100111)SY5,635$87.00$180.00
46Filter fabric (28200200)SY5,719$6.70$6.20
47Agg subgrade impr 24 (30300124)SY22,545$44.45$45.00
48Sub gran mat C 4 (31102100)SY3,240$11.10$16.75
49Agg base cse A 6 (35100500)SY726$12.60$45.00
50Aggregate-temp access (40201000)TON270.80$36.25$130.00
51Bit matls PR CT (40600275)LB70,547$0.88$0.84
52Bit matls tack CT (40600290)LB21,456$1.94$1.90
53Long joint sealant (40600370)LF32,844$3.00$2.90
54Matl transfer device (40600405)TON10,576$8.47$8.10
55HMA pavt FD 11 (40701901)SY17,168$97.25$93.00
56Incidental HMA surf (40800050)TON226$307.50$290.00
57PVT con HMA BR app SL (42000070)SY406$197.00$190.00
58PCC driveway pavt 8 (42300400)SY278$150.00$270.00
59PC conc sidewalk 6 (42400300)SF5,934$8.45$29.50
60Detectable warnings (42400800)SF190$58.00$110.00
61Pavement rem (44000100)SY13,496$11.80$23.75
62Drive pavement rem (44000200)SY291$21.25$33.00
63Gutter rem (44000400)LF530$13.70$19.00
64Comb curb gutter rem (44000500)LF117$16.60$33.00
65Median removal (44003100)SF1,253$9.20$3.30
66Paved SHLD removal (44004250)SY1,035$9.95$15.50
67Aggregate SHLDS B 7 (48101550)SY1,462$30.00$18.75
68HMA shoulders 8 (48203029)SY3,240$103.50$99.00
69Rem exist struct (50100100)EACH1$287,000$135,000
70Structure excavation (50200100)CY888$31.00$49.00
71Cofferdam excavation (50200300)CY1,764$63.75$99.00
72Cofferdam typ 2 loc 1 (50201121)EACH1$220,917$412,000
73Cofferdam typ 2 loc 2 (50201122)EACH1$203,750$470,000
74Cofferdam typ 2 loc 3 (50201123)EACH1$191,750$299,000
75Cofferdam typ 2 loc 4 (50201124)EACH1$191,750$281,000
76Conc struct (50300225)CY1,004.70$1,088.00$1,400.00
77Conc sup-STR (50300255)CY744$1,633.00$1,900.00
78BR deck grooving (50300260)SY2,914$8.90$9.20
79Seal coat conc (50300265)CY186.20$415.00$230.00
80Concrete encasement (50300280)CY8.60$1,460.00$3,400.00
81Protective coat (50300300)SY3,594$2.00$3.20
82Conc supstr app slab (50301350)CY439$443.25$440.00
83F & E struct steel (50500105)LS1$2,094,000$1,833,000
84Stud shear connectors (50500505)EACH16,554$3.87$9.20
85Reinf bars, epoxy CTD (50800205)LB485,380$1.75$1.70
86Bar splicers (50800515)EACH11$42.36$42.00
87Parapet railing (50901750)LF13.30$304.50$310.00
88Fur STL pile HP14X117 (51202100)LF11,750$168.25$150.00
89Driving piles (51202305)LF11,750$0.01$0.10
90Test pile ST HP14X117 (51204100)EACH3$37,080$12,600
91Name plates (51500100)EACH3$1,052.00$1,900.00
92Anchor bolts 3/4 (52100510)EACH32$113.00$93.00
93Anchor bolts 1 (52100520)EACH116$113.00$99.00
94P cul CL A 1 15 (542A0220)LF278$97.00$170.00
95P cul CL A 1 18 (542A0223)LF111$91.00$150.00
96P cul CL A 1 24 (542A0229)LF34$107.50$200.00
97PRC flar end sec 15 (54213660)EACH9$1,558.00$2,000.00
98PRC flar end sec 18 (54213663)EACH2$1,885.00$1,800.00
99PRC flar end sec 24 (54213669)EACH4$2,725.00$2,600.00
100PRC flar end sec 42 (54213687)EACH2$5,485.00$3,900.00
101Storm sew CL A 1 15 (550A0070)LF496$84.00$160.00
102Storm sew CL A 2 15 (550A0360)LF337$84.00$140.00
103Storm sew CL A 2 24 (550A0410)LF134$111.00$170.00
104Storm sew CL A 2 42 (550A0470)LF126$247.50$330.00
105Granular backfill STR (58600101)CY619$75.50$81.00
106Concrete sealer (58700300)SF127$4.00$30.00
107Geocomposite wall DR (59100100)SY301$39.00$57.00
108P undr for struct 4 (60146304)LF488$37.50$47.00
109Man TA 4 dia T1F CL (60218400)EACH2$4,325.00$4,700.00
110Man TA 4 dia T8G (60219000)EACH1$4,325.00$5,900.00
111Man TA 4 dia T3V F&G (60219570)EACH6$4,325.00$5,800.00
112Man TA 8 dia T1F CL (60224459)EACH1$16,265$16,200
113Inlets TA T3F&G (60235700)EACH2$2,590.00$4,300.00
114Inlets TA T3V F&G (60235705)EACH4$2,590.00$4,300.00
115Inlets TB T3F&G (60240220)EACH2$3,700.00$5,500.00
116Inlets TB T3V F&G (60240222)EACH10$3,877.00$5,500.00
117Class SI conc outlet (60600095)CY3$470.00$5,600.00
118Concrete gutter TY B (60602800)LF662$39.00$64.00
119Comb CC&G TB6.12 (60603800)LF144$75.00$80.00
120Comb CC&G TB6.18 (60604400)LF210$59.00$64.00
121Comb CC&G TY B-6.24 (60605000)LF1,645$40.00$65.00
122Comb CC&G TM6.06 (60608600)LF92$66.00$100.00
123Comb CC&G TM6.24 (60610400)LF166$59.00$80.00
124Conc median surf 4 (60618300)SF939$9.40$11.75
125SPBGR TY A 6FT posts (63000001)LF800$33.60$32.00
126LSG OV cul 18'9" span (63000360)LF87.50$38.85$37.00
127Traf bar term T2 (63100045)EACH2$1,890.00$1,800.00
128Traf bar term T5 (63100070)EACH1$1,575.00$1,500.00
129Traf bar term T6 (63100085)EACH7$5,040.00$4,800.00
130TR bar TRM T1 SPL tan (63100167)EACH10$3,675.00$3,500.00
131Guardrail remov (63200310)LF1,880$6.06$5.00
132Shoulder rum strip 8 (64200108)LF2,221$2.45$1.50
133Fur erect row markers (66600105)EACH8$373.00$570.00
134Non SPL waste disposl (66900200)CY1,461$72.00$75.00
135Soil disposal analy (66900530)EACH1$1,312.50$1,300.00
136Reg sub P-const plan (66901001)LS1$3,150.00$2,200.00
137Reg sub F con report (66901003)LS1$1,050.00$2,500.00
138Engineered barrier (66901005)SY889$3.40$130.00
139Reg sub mon (66901006)CAL DAY76$0.01$1,000.00
140Engr field office A (67000400)CAL MO24$2,220.00$5,200.00
141Mobilization (67100100)LS1$1,182,400$1,600,000
142Traf cont-prot 701201 (70100450)LS1$0.01$56,000
143Traf cont-prot 701306 (70100460)LS1$0.01$17,900
144Traf cont-prot 701326 (70100500)LS1$4,935.00$58,000
145Changeable message SN (70107025)CAL DAY420$62.50$50.00
146Sign panel T1 (72000100)SF325.51$30.00$38.00
147Sign panel T2 (72000200)SF108$22.50$50.00
148Remov sin pan assy TA (72400100)EACH21$26.25$390.00
149Remov sin pan assy TB (72400200)EACH13$26.25$400.00
150Remov sign panel T1 (72400310)SF30$2.10$32.00
151Reloc sin pan assy TA (72400500)EACH2$194.25$480.00
152Reloc sin pan assy TB (72400600)EACH3$325.50$500.00
153Terminal marker - DA (72501000)EACH13$52.50$50.00
154Teles STL sin support (72800100)LF543.01$16.50$16.00
155Wood sin support (73000100)LF276$26.25$50.00
156Base tel STL sin supp (73100100)EACH1$383.25$750.00
157THPL PVT MK LTR & sym (78000100)SF483.60$12.60$8.00
158THPL PVT MK line 6 (78000400)LF21,272$1.25$1.80
159THPL PVT MK line 8 (78000500)LF584$8.40$2.70
160THPL PVT MK line 12 (78000600)LF1,685$11.55$4.00
161THPL PVT MK line 24 (78000650)LF192$15.75$8.00
162Paint PVT MK line 4 (78001110)LF184$5.25$16.50
163Pref PL PM TD STD LTR/sym (78004600)SF62.40$10.16$50.00
164Pref PL PM TD STD L 6 (78004630)LF2,949$13.01$10.00
165Pref PL PM TD STD L 8 (78004640)LF96$14.94$15.00
166Pref PL PM TD STD L12 (78004660)LF345$18.63$25.00
167Pref PL PM TD STD L24 (78004720)LF30$29.98$50.00
168GRV RCSD PM LTR & sym (78011000)SF62.40$13.91$40.00
169GRV RCSD PVT MRKG 7 (78011035)LF2,949$3.68$7.50
170GRV RCSD PVT MRKG 9 (78011045)LF96$9.45$15.00
171GRV RCSD PVT MRKG 13 (78011065)LF345$13.90$20.00
172GRV RCSD PVT MRKG 25 (78011125)LF30$21.00$40.00
173Raised refl pavt MKR (78100100)EACH205$49.35$60.00
174Grdrail ref type A (78200005)EACH40$10.50$10.00
175Barr wall ref type B (78200010)EACH16$12.60$45.00
176Barr wall ref type C (78200011)EACH16$13.65$45.00
177Curb reflectors (78200020)EACH50$49.35$30.00
178Serv install TY A (80500100)EACH1$6,562.50$6,300.00
179Undrgrd C galvs 4 (81028240)LF194$120.25$110.00
180Undrgrd C PVC 1 (81028320)LF97$23.94$22.75
181Undrgrd C PVC 2 (81028350)LF988$27.00$25.75
182Undrgrd C PVC 3 (81028370)LF640$33.60$32.00
183Undrgrd C PVC 4 (81028390)LF116$35.70$34.00
184Undrgrd C PVC 5 (81028400)LF48$58.40$56.00
185Con at ST 2 galvs (81100600)LF135$44.45$42.00
186Handhole (81400100)EACH15$1,995.00$1,900.00
187DBL handhole (81400300)EACH1$3,533.00$3,400.00
188Main EX TR sig instal (85000200)EACH1$9,765.00$9,300.00
189Fac T4 cab (85700200)EACH1$31,500$30,000
190FO cab C 62.5/125 24F (87100160)LF1,130$9.45$9.00
191Elcbl C signal 14 2C (87301215)LF1,375$2.52$2.40
192Elcbl C signal 14 4C (87301235)LF1,410$3.25$3.10
193Elcbl C signal 14 5C (87301245)LF5,207$3.25$3.10
194Elcbl C signal 14 7C (87301255)LF2,028$3.80$3.70
195Elcbl C lead 14 1PR (87301305)LF1,867$2.94$2.80
196Elcbl C serv 6 3C (87301815)LF34$6.93$6.60
197Elcbl C egrdc 6 1C (87301900)LF1,400$4.20$4.00
198TS post 12 (87500800)EACH3$2,170.00$2,100.00
199S maa & P 55 (87700320)EACH1$23,940$23,000
200STL comb maa&P 48 (87702970)EACH1$24,780$24,000
201STL comb maa&P 50 (87702980)EACH1$25,200$24,000
202STL comb maa&P 60 (87703030)EACH1$32,025$31,000
203STL comb maa&P 68 (87703080)EACH1$36,330$35,000
204Conc FDN TY A (87800100)LF9$700.00$670.00
205Conc FDN TY D (87800200)LF3$1,627.50$1,600.00
206Conc FDN TY E 36D (87800415)LF43$667.00$640.00
207Conc FDN TY E 42D (87800420)LF46$1,018.50$970.00
208Drill EX handhole (87900200)EACH1$247.00$240.00
209SH P LED 1F 3S BM (88040070)EACH7$1,129.00$1,100.00
210SH P LED 1F 3S mam (88040090)EACH12$1,155.00$1,100.00
211SH P LED 1F 4S BM (88040110)EACH6$1,260.00$1,200.00
212SH P LED 1F 4S mam (88040120)EACH6$1,328.00$1,300.00
213Ped SH P LED 2F BM CT (88102845)EACH4$1,654.00$1,600.00
214TS backplate ret-refl (88200510)EACH18$362.25$350.00
215Inductive loop detect (88500100)EACH1$483.00$460.00
216Det loop T1 (88600100)LF688$21.15$20.25
217Reloc EX sig head (89500100)EACH2$1,816.50$1,700.00
218Mod EX contr cab (89502210)EACH1$8,116.50$7,700.00
219Rem elcbl FR con (89502300)LF3,338$0.53$0.50
220Remov EX TS equip (89502375)EACH1$7,014.00$6,700.00
221Remov EX handhole (89502380)EACH3$1,107.75$1,100.00
222Remov EX conc FDN (89502385)EACH1$1,218.00$1,200.00
IDOT contract 76A46: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy