IDOT contract 85772 bid tabulation
Moline, section 21-00287-00-RS. Let by Illinois DOT on January 17, 2025, Rock Island, District 02. 4 bids received; low bid $1,565,824 by Valley Construction Co..
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 65
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Valley Construction Co. | $1,565,824 | Low |
| 2 | Centennial Contractors of the Quad Cities, Inc. | $1,578,832 | +1.0% |
| 3 | Brandt Construction Co. | $1,621,653 | +4.0% |
| 4 | Langman Construction, Inc. | $1,635,329 | +4.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Valley Construction Co. | 2. Centennial Contractors of the Quad Cities, Inc. | 3. Brandt Construction Co. | 4. Langman Construction, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Seeding SPL (K1005421) | ACRE | 1 | $10,000 | $15,000 | $12,000 | $10,000 |
| 2 | PCC PVMT SPL W IC (LR420100) | SY | 85 | $115.00 | $120.00 | $147.00 | $140.00 |
| 3 | Adj san sew cleanout (XX007759) | EACH | 1 | $1,000.00 | $750.00 | $1,230.00 | $400.00 |
| 4 | Rem ped push-button (X1400031) | EACH | 8 | $80.00 | $92.00 | $90.00 | $80.00 |
| 5 | Temporary ramp SPL (X4060995) | SY | 893 | $19.50 | $11.50 | $45.00 | $10.00 |
| 6 | Inlet adj new F&G SPL (X6024503) | EACH | 1 | $2,000.00 | $2,500.00 | $2,625.00 | $2,500.00 |
| 7 | Inlets adjust SPL (X6026200) | EACH | 1 | $2,300.00 | $2,500.00 | $2,625.00 | $1,500.00 |
| 8 | FR & grates adjust SP (X6030205) | EACH | 17 | $2,200.00 | $2,500.00 | $2,625.00 | $1,850.00 |
| 9 | CH LK fence reloc (X6640306) | LF | 6 | $150.00 | $250.00 | $285.00 | $95.00 |
| 10 | Traf cont & prot SPL (X7010216) | LS | 1 | $35,000 | $40,250 | $41,000 | $130,000 |
| 11 | Fac T4 cab SPL (X8570226) | EACH | 1 | $18,543 | $21,324 | $21,000 | $18,453 |
| 12 | Accessible ped signal (X8760200) | EACH | 8 | $888.00 | $1,020.00 | $995.00 | $887.63 |
| 13 | Ped pushbutton post (X8760201) | EACH | 8 | $2,101.00 | $2,415.00 | $2,350.00 | $2,101.00 |
| 14 | Rem EX TR cont & cab (X8950105) | EACH | 1 | $747.00 | $860.00 | $840.00 | $747.00 |
| 15 | Rem EX ped sig head (X8950307) | EACH | 8 | $126.00 | $144.00 | $140.00 | $125.25 |
| 16 | Conc block removal (Z0001202) | CY | 0.50 | $200.00 | $1,000.00 | $1,265.00 | $1,000.00 |
| 17 | Trainees (Z0076600) | HR | 1,000 | $0.80 | $0.80 | $0.80 | $0.80 |
| 18 | Trainees TPG (Z0076604) | HR | 1,000 | $15.00 | $15.00 | $15.00 | $15.00 |
| 19 | Tree root pruning (20101200) | EACH | 2 | $250.00 | $1,000.00 | $230.00 | $0.01 |
| 20 | Agg surf course TY B (40200800) | TON | 1 | $150.00 | $30.00 | $485.00 | $295.00 |
| 21 | P bit matls tack CT (40600295) | LB | 10,848 | $0.01 | $0.02 | $0.75 | $0.01 |
| 22 | HMA BC HM N50 (40600900) | TON | 75 | $200.00 | $115.00 | $200.00 | $100.00 |
| 23 | P HMA BC IL-9.5FG N50 (40603215) | TON | 1,582 | $117.50 | $143.00 | $126.00 | $125.00 |
| 24 | P HMA SC 9.5FG D N50 (40604110) | TON | 1,356 | $117.50 | $143.00 | $126.00 | $125.00 |
| 25 | PCC PVT 8 (42000300) | SY | 604 | $100.00 | $110.00 | $150.00 | $135.00 |
| 26 | PCC driveway pavt 7 (42300300) | SY | 9 | $180.00 | $100.00 | $130.00 | $135.00 |
| 27 | PC conc sidewalk 4 (42400100) | SF | 4,581 | $14.00 | $12.00 | $16.00 | $13.00 |
| 28 | PC conc sidewalk 6 (42400300) | SF | 5,380 | $17.00 | $18.00 | $18.00 | $15.00 |
| 29 | Detectable warnings (42400800) | SF | 368 | $60.00 | $50.00 | $65.00 | $80.00 |
| 30 | Pavement rem (44000100) | SY | 689 | $25.00 | $25.00 | $35.00 | $28.00 |
| 31 | HMA surf rem 3 1/4 (44000162) | SY | 16,072 | $10.00 | $11.50 | $5.00 | $10.00 |
| 32 | Drive pavement rem (44000200) | SY | 9 | $24.00 | $25.00 | $30.00 | $22.00 |
| 33 | Comb curb gutter rem (44000500) | LF | 224 | $18.00 | $15.00 | $55.00 | $19.00 |
| 34 | Sidewalk rem (44000600) | SF | 8,797 | $3.50 | $2.50 | $4.00 | $2.25 |
| 35 | CL B patch T1 10 (44200966) | SY | 8 | $350.00 | $200.00 | $200.00 | $350.00 |
| 36 | CL B patch T2 10 (44200970) | SY | 163 | $280.00 | $175.00 | $200.00 | $240.00 |
| 37 | CL B patch T3 10 (44200974) | SY | 321 | $270.00 | $175.00 | $200.00 | $208.00 |
| 38 | CL B patch T4 10 (44200976) | SY | 741 | $225.00 | $175.00 | $200.00 | $205.00 |
| 39 | Fire hydnts relocated (56400400) | EACH | 2 | $4,400.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 40 | Dom wat ser box adj (56500600) | EACH | 2 | $1,050.00 | $750.00 | $700.00 | $750.00 |
| 41 | Inlets adj new T3F&G (60260500) | EACH | 2 | $2,250.00 | $2,500.00 | $4,285.00 | $2,500.00 |
| 42 | Valve box adj (60266600) | EACH | 6 | $925.00 | $750.00 | $1,100.00 | $1,000.00 |
| 43 | FR & grates adjust (60300105) | EACH | 5 | $1,900.00 | $1,500.00 | $1,665.00 | $1,500.00 |
| 44 | FR & lids adjust (60300305) | EACH | 37 | $1,900.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 45 | Comb CC&G TB6.12 aep (60603900) | LF | 224 | $75.00 | $60.00 | $90.00 | $75.00 |
| 46 | Mobilization (67100100) | LS | 1 | $90,000 | $75,000 | $95,000 | $92,500 |
| 47 | Short term pavt mking (70300100) | LF | 11,612 | $0.01 | $0.75 | $1.65 | $1.00 |
| 48 | SHRT TRM pavt MK rem (70300150) | SF | 3,781 | $0.01 | $0.75 | $4.40 | $3.00 |
| 49 | THPL PVT MK LTR & sym (78000100) | SF | 1,022 | $4.80 | $8.00 | $5.50 | $4.80 |
| 50 | THPL PVT MK line 4 (78000200) | LF | 7,059 | $0.80 | $1.75 | $0.90 | $0.80 |
| 51 | THPL PVT MK line 6 (78000400) | LF | 5,742 | $1.20 | $2.15 | $1.35 | $1.20 |
| 52 | THPL PVT MK line 12 (78000600) | LF | 240 | $2.40 | $3.80 | $2.70 | $2.40 |
| 53 | THPL PVT MK line 24 (78000650) | LF | 603 | $4.80 | $6.60 | $5.50 | $4.80 |
| 54 | PVT MKG rem WTR blast (78300202) | SF | 185 | $6.00 | $5.00 | $15.50 | $10.00 |
| 55 | Serv install GRND MT (80500010) | EACH | 1 | $5,181.00 | $5,958.00 | $5,800.00 | $5,181.00 |
| 56 | Undrgrd C PVC 1 (81028320) | LF | 47 | $12.80 | $14.75 | $14.00 | $12.77 |
| 57 | HD handhole (81400200) | EACH | 4 | $2,468.00 | $2,838.00 | $2,800.00 | $2,468.00 |
| 58 | Remov elect serv inst (84500120) | EACH | 1 | $620.00 | $715.00 | $700.00 | $620.00 |
| 59 | Elcbl C signal 14 3C (87301225) | LF | 1,873 | $2.20 | $2.53 | $2.45 | $2.20 |
| 60 | Elcbl C signal 14 5C (87301245) | LF | 540 | $2.65 | $3.04 | $2.95 | $2.64 |
| 61 | Elcbl C signal 14 7C (87301255) | LF | 977 | $2.80 | $3.22 | $3.00 | $2.80 |
| 62 | Elcbl C egrdc 6 1C (87301900) | LF | 329 | $1.95 | $2.22 | $2.00 | $1.93 |
| 63 | Ped SH LED 1F BM CDT (88102717) | EACH | 8 | $715.00 | $822.00 | $800.00 | $714.50 |
| 64 | Reloc EX maa & pole (89501300) | EACH | 1 | $10,338 | $11,888 | $11,700 | $10,338 |
| 65 | Remov EX handhole (89502380) | EACH | 4 | $703.00 | $808.00 | $800.00 | $703.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.