IDOT contract 87866 bid tabulation
Project Number: 4Wak-615 / /, section 20-00272-00-SP. Let by Illinois DOT on March 7, 2025, Dekalb, District 03. 6 bids received; low bid $442,950 by Martin & Company Excavating.
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 33
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martin & Company Excavating | $442,950 | Low |
| 2 | Curran Contracting Company | $460,171 | +4.0% |
| 3 | Elliott and Wood, Inc. | $523,254 | +18% |
| 4 | Performance Construction and Engineering, LLC | $598,013 | +35% |
| 5 | Fischer Excavating, Inc. | $613,914 | +39% |
| 6 | Alliance Contractors, Inc. | $670,479 | +51% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martin & Company Excavating | 2. Curran Contracting Company | 3. Elliott and Wood, Inc. | 4. Performance Construction and Engineering, LLC | 5. Fischer Excavating, Inc. | 6. Alliance Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Box culvert removal (X1200050) | LF | 78 | $48.00 | $20.00 | $20.00 | $155.00 | $100.00 | $100.00 |
| 2 | Traf cont & prot SPL (X7010216) | LS | 1 | $10,000 | $20,000 | $4,875.00 | $30,000 | $8,900.00 | $36,664 |
| 3 | Construction layout (Z0013798) | LS | 1 | $4,500.00 | $7,000.00 | $4,200.00 | $12,500 | $4,850.00 | $4,850.00 |
| 4 | Temp info signing (Z0030850) | SF | 42 | $16.00 | $25.00 | $25.00 | $25.00 | $14.00 | $25.00 |
| 5 | Earth excavation (20200100) | CY | 3,418 | $24.30 | $28.00 | $38.00 | $40.00 | $38.00 | $15.00 |
| 6 | Trench backfill (20800150) | CY | 16 | $38.00 | $40.00 | $40.00 | $20.00 | $25.00 | $35.00 |
| 7 | Seeding CL 2A (25000210) | ACRE | 0.75 | $3,000.00 | $2,500.00 | $2,500.00 | $2,500.00 | $5,780.00 | $2,500.00 |
| 8 | Nitrogen fert nutr (25000400) | LB | 69 | $3.00 | $2.00 | $2.00 | $2.00 | $4.00 | $2.00 |
| 9 | Phosphorus fert nutr (25000500) | LB | 69 | $3.00 | $2.00 | $2.00 | $2.00 | $4.00 | $2.00 |
| 10 | Potassium fert nutr (25000600) | LB | 69 | $3.00 | $2.00 | $2.00 | $2.00 | $4.00 | $2.00 |
| 11 | Erosion contr blanket (25100630) | SY | 3,657 | $1.40 | $1.00 | $1.00 | $1.00 | $1.45 | $1.00 |
| 12 | Temp eros contr seed (28000250) | LB | 75 | $1.90 | $1.00 | $1.00 | $5.00 | $7.00 | $1.00 |
| 13 | Temp ditch checks (28000305) | LF | 180 | $18.00 | $15.00 | $15.00 | $15.00 | $14.00 | $15.00 |
| 14 | Perimeter eros bar (28000400) | LF | 648 | $5.00 | $4.00 | $4.00 | $5.00 | $3.65 | $4.00 |
| 15 | Inlet & pipe protect (28000500) | EACH | 2 | $150.00 | $150.00 | $330.00 | $500.00 | $330.00 | $50.00 |
| 16 | Agg subgrade impr 18 (30300118) | SY | 1,975 | $24.38 | $18.00 | $32.00 | $22.00 | $40.00 | $39.50 |
| 17 | Agg base cse B 6 (35101800) | SY | 1,290 | $8.79 | $8.00 | $17.50 | $13.00 | $13.00 | $20.35 |
| 18 | Bit matls tack CT (40600290) | LB | 638 | $0.10 | $2.50 | $2.50 | $0.01 | $1.00 | $2.50 |
| 19 | Long joint sealant (40600370) | LF | 656 | $22.00 | $14.00 | $14.00 | $16.75 | $15.75 | $14.00 |
| 20 | HMA BC IL-19.0 N50 (40603080) | TON | 1,089 | $84.00 | $75.00 | $75.00 | $82.00 | $80.00 | $75.00 |
| 21 | HMA SC IL-9.5 C N50 (40604050) | TON | 198 | $86.00 | $92.00 | $92.00 | $122.00 | $120.00 | $92.00 |
| 22 | Pavement rem (44000100) | SY | 1,780 | $7.70 | $10.12 | $15.00 | $18.00 | $8.00 | $25.00 |
| 23 | HMA surf rem 1 1/2 (44000155) | SY | 495 | $7.35 | $10.00 | $10.00 | $30.00 | $30.00 | $10.00 |
| 24 | CL D patch T4 10 (44201771) | SY | 68 | $114.00 | $110.00 | $110.00 | $100.00 | $350.00 | $110.00 |
| 25 | Aggregate SHLDS B 8 (48101600) | SY | 564 | $11.00 | $17.50 | $17.50 | $19.00 | $24.00 | $17.50 |
| 26 | HMA shoulders 8 (48203029) | SY | 580 | $40.35 | $40.00 | $40.00 | $41.00 | $41.00 | $40.00 |
| 27 | Conc headwall removal (50104400) | EACH | 3 | $175.00 | $175.00 | $175.00 | $3,000.00 | $1,200.00 | $500.00 |
| 28 | Pipe culvert remov (50105220) | LF | 49 | $6.00 | $20.00 | $20.00 | $65.00 | $95.00 | $25.00 |
| 29 | Box cul end sec C1 (54001001) | EACH | 2 | $9,200.00 | $7,500.00 | $7,500.00 | $7,000.00 | $10,500 | $9,450.00 |
| 30 | PCBC 4X2 (54010402) | LF | 78 | $465.00 | $550.00 | $550.00 | $625.00 | $675.00 | $1,358.00 |
| 31 | P cul CL D 1 24 (542D0229) | LF | 51 | $105.00 | $170.00 | $170.00 | $125.00 | $250.00 | $105.50 |
| 32 | Mobilization (67100100) | LS | 1 | $24,000 | $28,000 | $29,244 | $34,800 | $36,000 | $115,900 |
| 33 | Paint PVT MK line 4 (78001110) | LF | 5,180 | $0.66 | $1.25 | $0.60 | $0.60 | $1.25 | $0.60 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.