IDOT contract 97852 bid tabulation

Jerseyville, section 22-00040-01-PV. Let by Illinois DOT on April 25, 2025, Jersey, District 08. 3 bids received; low bid $2,063,878 by Baxmeyer Construction, Inc..

Owner
Illinois DOT
Letting
25 APR 2025
Pay items
58
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Baxmeyer Construction, Inc.$2,063,878Low
2Keller Construction, Inc.$2,081,088+1.0%
3Stutz Excavating, Inc.$2,272,532+10%
IDOT contract 97852: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Baxmeyer Construction, Inc.2. Keller Construction, Inc.3. Stutz Excavating, Inc.
1Seeding SPL (K1005421)ACRE1.10$22,300$25,000$17,250
2Prec inlet SPL 4 open (XX009584)EACH22$3,625.00$5,900.00$3,226.00
3Prec inlet SPL 8 open (XX009585)EACH1$7,150.00$14,000$6,080.00
4Prec inlet SPL 5 open (XX009708)EACH9$4,700.00$7,100.00$4,345.00
5Pro SS conn to EX SS (X0322916)EACH3$1,585.00$2,240.00$1,400.00
6Relocate EX mailbox (X0327301)EACH10$675.00$425.00$420.00
7Remove exist riprap (X2810844)SY465$10.25$22.00$20.00
8Storm sew connection (X5510010)EACH20$1,600.00$615.00$870.00
9Engr FLD off A SPL (X6700410)CAL MO8$4,550.00$2,100.00$2,700.00
10Traf cont & prot SPL (X7010216)LS1$23,500$57,000$21,500
11Construction layout (Z0013798)LS1$16,500$23,970$28,885
12SS 2 wat MN 24 (Z0056672)LF143$175.00$132.00$174.00
13Trainees (Z0076600)HR1,000$0.80$0.80$0.80
14Trainees TPG (Z0076604)HR1,000$15.00$15.00$15.00
15Earth excavation (20200100)CY4,002$39.00$30.00$44.85
16Trench backfill (20800150)CY555$39.50$54.00$69.00
17Mulch method 2 (25100115)ACRE2.20$3,700.00$1,500.00$3,380.00
18Temp eros contr seed (28000250)LB220$5.50$3.00$5.00
19Perimeter eros bar (28000400)LF2,795$8.00$3.90$5.25
20Inlet & pipe protect (28000500)EACH29$220.00$90.00$250.00
21Stone riprap CL A3 (28100105)SY200$62.00$37.00$38.50
22Stone riprap CL A4 (28100107)SY96$97.00$65.00$61.00
23Filter fabric (28200200)SY296$5.50$8.00$4.25
24Process mod soil 12 (30200650)SY7,168$3.25$3.50$6.50
25Portland cement (30201700)TON213$252.00$250.00$256.00
26Agg base cse A 4 (35100300)SY11,463$11.15$9.50$7.95
27Agg base cse B 6 (35101800)SY66$27.25$17.00$17.00
28Aggregate-temp access (40201000)TON120$61.75$75.00$45.00
29HMA BC IL-19.0 N50 (40603080)TON47$250.00$224.21$233.00
30HMA SC IL-9.5 D N50 (40604060)TON16$375.00$338.87$345.00
31Bit matls PR CT (40800025)LB35$0.01$0.01$10.00
32Bit matls tack CT (40800029)LB7$3.75$3.17$35.00
33PCC PVT 8 (42000300)SY7,218$65.25$72.50$74.75
34PCC driveway pavt 6 (42300200)SY1,274$109.00$96.00$93.25
35PC conc sidewalk 4 (42400100)SF11,112$6.25$8.25$7.40
36Detectable warnings (42400800)SF77$40.00$53.50$54.00
37Pavement rem (44000100)SY918$8.15$14.50$21.25
38Drive pavement rem (44000200)SY520$16.50$28.00$22.50
39Sidewalk rem (44000600)SF78$3.00$8.00$5.25
40Pipe culvert remov (50105220)LF1,019$20.50$16.00$27.00
41Box cul end sec C1 (54001001)EACH1$16,135$16,500$14,880
42PCBC 4X3 (54010403)LF4$1,680.00$1,450.00$1,925.00
43Conc ES 542001 36 1:2 (54261236)EACH1$7,885.00$9,100.00$7,150.00
44Conc ES 542011 36 1:2 (54263236)EACH1$8,050.00$8,700.00$6,775.00
45Storm sew CL A 2 15 (550A0360)LF1,222$73.00$60.00$94.75
46Storm sew CL A 2 18 (550A0380)LF333$80.00$61.00$115.00
47Storm sew CL A 2 24 (550A0410)LF391$107.25$85.00$148.00
48Storm sew CL A 2 30 (550A0430)LF543$144.00$120.00$173.50
49Storm sew CL A 2 36 (550A0450)LF79$179.00$145.00$214.00
50SS CL A 2 eqrs 36 (550A5300)LF12$455.00$450.00$656.00
51Inlets TA T8G (60236200)EACH2$1,875.00$3,150.00$1,542.00
52Remov inlets (60500060)EACH2$525.00$375.00$450.00
53Comb CC&G TY B-6.24 (60605000)LF4,797$40.00$17.50$39.00
54Mobilization (67100100)LS1$45,920$142,031$143,300
55Reloc sin pan assy TA (72400500)EACH3$255.00$250.00$630.00
56Mod ureth PM line 4 (78009004)LF590$11.50$10.00$1.90
57Mod ureth PM line 12 (78009012)LF246$34.75$30.50$6.90
58Mod ureth PM line 24 (78009024)LF12$69.50$60.50$29.70
IDOT contract 97852: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy