IDOT contract 97880 bid tabulation
Columbia, section 23-00057-01-BT. Let by Illinois DOT on January 16, 2026, Monroe, District 08. 3 bids received; low bid $928,457 by DMS Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 65
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | DMS Contracting, Inc. | $928,457 | Low |
| 2 | Baxmeyer Construction, Inc. | $1,010,738 | +9.0% |
| 3 | Keller Construction, Inc. | $1,160,914 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. DMS Contracting, Inc. | 2. Baxmeyer Construction, Inc. | 3. Keller Construction, Inc. |
|---|---|---|---|---|---|---|
| 1 | Ped truss superstr (X0322508) | SF | 1,223 | $202.10 | $180.50 | $288.00 |
| 2 | Connect exist culvert (X0327423) | EACH | 1 | $1,470.00 | $3,925.00 | $1,750.00 |
| 3 | Fold down bollards (X0350805) | EACH | 1 | $2,300.00 | $2,375.00 | $2,285.00 |
| 4 | R R FL beacon A comp (X1400326) | EACH | 2 | $7,700.00 | $7,900.00 | $7,613.00 |
| 5 | Remove exist riprap (X2810844) | SY | 278 | $22.50 | $20.00 | $15.20 |
| 6 | Coarse agr backfil SPL (X3110102) | CY | 34 | $125.00 | $128.00 | $161.85 |
| 7 | Rem C box cul end sec (X5010520) | EACH | 1 | $6,000.00 | $2,675.00 | $2,700.00 |
| 8 | Pedestrian rail SPL (X5090810) | LF | 142 | $76.55 | $78.50 | $75.60 |
| 9 | Pro SS conn to EX SS (X5510012) | EACH | 1 | $779.50 | $1,850.00 | $1,900.00 |
| 10 | Wood rail SPL (X6640634) | LF | 48 | $114.00 | $117.00 | $112.90 |
| 11 | Traf cont & prot SPL (X7010216) | LS | 1 | $44,000 | $9,800.00 | $6,300.00 |
| 12 | Construction layout (Z0013798) | LS | 1 | $16,400 | $23,000 | $9,950.00 |
| 13 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 |
| 14 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 |
| 15 | Tree remov acres (20100500) | ACRE | 0.25 | $35,000 | $64,825 | $55,500 |
| 16 | Tree trunk protection (20101100) | EACH | 3 | $250.00 | $475.00 | $760.00 |
| 17 | Earth excavation (20200100) | CY | 1,870 | $14.25 | $38.25 | $25.75 |
| 18 | Porous gran embank (20700220) | CY | 10 | $330.00 | $111.50 | $240.00 |
| 19 | Trench backfill (20800150) | CY | 49 | $59.50 | $32.00 | $45.00 |
| 20 | Seeding CL 2 (25000200) | ACRE | 1.50 | $3,800.00 | $4,725.00 | $3,150.00 |
| 21 | Nitrogen fert nutr (25000400) | LB | 135 | $4.50 | $10.25 | $9.00 |
| 22 | Phosphorus fert nutr (25000500) | LB | 135 | $4.50 | $10.25 | $9.00 |
| 23 | Potassium fert nutr (25000600) | LB | 135 | $4.50 | $10.25 | $9.00 |
| 24 | Mulch method 2 (25100115) | ACRE | 1.50 | $5,000.00 | $8,225.00 | $4,500.00 |
| 25 | Erosion contr blanket (25100630) | SY | 1,304 | $3.65 | $3.75 | $2.80 |
| 26 | Temp eros contr seed (28000250) | LB | 150 | $12.40 | $11.00 | $7.75 |
| 27 | Temp ditch checks (28000305) | LF | 64 | $29.50 | $30.00 | $21.00 |
| 28 | Perimeter eros bar (28000400) | LF | 3,500 | $2.50 | $4.65 | $5.00 |
| 29 | Inlet & pipe protect (28000500) | EACH | 5 | $400.00 | $295.00 | $175.00 |
| 30 | Stone riprap CL A4 (28100107) | SY | 625 | $47.70 | $85.75 | $64.00 |
| 31 | Filter fabric (28200200) | SY | 625 | $4.60 | $6.65 | $8.10 |
| 32 | Agg base cse A 4 (35100300) | SY | 422 | $10.75 | $24.65 | $27.85 |
| 33 | Agg base cse A 6 (35100500) | SY | 2,412 | $15.00 | $14.20 | $11.20 |
| 34 | Proc soil-cem BC 12 (35200420) | SY | 2,412 | $3.65 | $6.25 | $3.90 |
| 35 | Cement (35200500) | 100 WT | 421 | $16.50 | $36.00 | $15.80 |
| 36 | Aggregate-temp access (40201000) | TON | 100 | $45.25 | $0.01 | $63.85 |
| 37 | Bit matls PR CT (40600275) | LB | 5,428 | $2.60 | $2.30 | $2.55 |
| 38 | HMA SC IL-9.5 C N50 (40604050) | TON | 270 | $170.00 | $191.60 | $167.70 |
| 39 | PCC PVT 6 (42000100) | SY | 163 | $98.25 | $181.00 | $175.56 |
| 40 | PC conc sidewalk 4 (42400100) | SF | 2,329 | $8.25 | $14.00 | $19.80 |
| 41 | Detectable warnings (42400800) | SF | 68 | $90.00 | $41.75 | $45.20 |
| 42 | Pavement rem (44000100) | SY | 105 | $34.00 | $33.00 | $29.30 |
| 43 | Comb curb gutter rem (44000500) | LF | 5 | $230.00 | $120.00 | $307.70 |
| 44 | Sidewalk rem (44000600) | SF | 150 | $19.00 | $5.00 | $13.00 |
| 45 | Structure excavation (50200100) | CY | 10 | $146.50 | $150.00 | $175.00 |
| 46 | Conc struct (50300225) | CY | 21.20 | $2,695.00 | $2,760.00 | $3,120.00 |
| 47 | Reinforcement bars (50800105) | LB | 2,200 | $6.50 | $8.50 | $3.00 |
| 48 | Fur STL pile HP12X53 (51201600) | LF | 124 | $316.00 | $323.50 | $208.15 |
| 49 | Driving piles (51202305) | LF | 124 | $0.01 | $0.01 | $0.01 |
| 50 | Pile shoes (51204650) | EACH | 4 | $239.25 | $245.00 | $183.00 |
| 51 | Box cul end sec C1 (54001001) | EACH | 1 | $35,800 | $56,450 | $29,500 |
| 52 | PCBC 8X7 (54010807) | LF | 24 | $1,220.00 | $0.01 | $1,225.00 |
| 53 | PRC flar end sec 12 (54213657) | EACH | 1 | $2,710.00 | $1,475.00 | $2,341.00 |
| 54 | PRC flar end sec 18 (54213663) | EACH | 1 | $2,865.00 | $1,865.00 | $2,747.00 |
| 55 | Storm sew CL A 2 12 (550A0340) | LF | 196 | $58.50 | $61.00 | $77.00 |
| 56 | Storm sew CL A 2 18 (550A0380) | LF | 23 | $107.00 | $77.50 | $98.70 |
| 57 | Storm sewer rem 18 (55100900) | LF | 18 | $50.00 | $37.40 | $41.50 |
| 58 | Man TA 4 dia T24F&G (60219540) | EACH | 1 | $4,250.00 | $3,960.00 | $6,550.00 |
| 59 | Inlets TA T8G (60236200) | EACH | 1 | $2,920.00 | $2,070.00 | $3,925.00 |
| 60 | Inlets TB T8G (60240301) | EACH | 1 | $3,330.00 | $2,420.00 | $4,325.00 |
| 61 | Comb CC&G TB6.24 dow (60605200) | LF | 56 | $127.00 | $322.00 | $114.50 |
| 62 | Guardrail remov (63200310) | LF | 90 | $56.15 | $21.00 | $43.50 |
| 63 | Mobilization (67100100) | LS | 1 | $56,000 | $62,913 | $164,500 |
| 64 | Paint PVT MK line 6 (78001130) | LF | 210 | $8.75 | $5.85 | $8.66 |
| 65 | Paint PVT MK line 24 (78001180) | LF | 118 | $16.20 | $10.35 | $16.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.