INDOT contract B-42792-A bid tabulation
BRIDGE DECK REPLACEMENT. Let by Indiana DOT on January 14, 2026, Madison, Greenfield. 7 bids received; low bid $2,094,000 by Pontem Contractors Inc.
- Owner
- Indiana DOT
- Letting
- 14 JAN 2026
- Pay items
- 93
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pontem Contractors Inc | $2,094,000 | Low |
| 2 | Beaty Construction Inc | $2,241,122 | +7.0% |
| 3 | Superior Construction Co Inc | $2,300,000 | +10% |
| 4 | William Charles Construction Company | $2,500,662 | +19% |
| 5 | Milestone Contractors LP | $2,577,117 | +23% |
| 6 | E & B Paving LLC | $2,772,000 | +32% |
| 7 | Icc Group Inc | $2,857,000 | +36% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pontem Contractors Inc | 2. Beaty Construction Inc | 3. Superior Construction Co Inc | 4. William Charles Construction Company | 5. Milestone Contractors LP | 6. E & B Paving LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $20,000 | $15,000 | $35,000 | $25,000 | $26,500 | $50,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $100,500 | $105,000 | $115,000 | $125,000 | $128,856 | $140,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $60,350 | $18,000 | $23,000 | $20,000 | $77,314 | $83,126 |
| 0011 | Pavement removal (202-02240) | SYS | 213 | $39.90 | $38.00 | $41.00 | $33.00 | $71.00 | $50.00 |
| 0012 | Paved side ditch, remove (202-02272) | LFT | 337 | $16.80 | $7.00 | $6.00 | $8.00 | $32.00 | $10.00 |
| 0013 | Present structure, remove portions, structure no. 48-00107 (202-51328) | LS | 1 | $381,288 | $225,000 | $821,808 | $400,000 | $660,116 | $790,000 |
| 0014 | Excavation, common (203-02000) | CYS | 400 | $73.50 | $54.00 | $15.00 | $45.00 | $65.00 | $75.00 |
| 0015 | Borrow (203-02070) | CYS | 80 | $34.65 | $20.00 | $0.01 | $80.00 | $11.00 | $1.00 |
| 0016 | Stormwater management budget (205-12108) | DOL | 21,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0017 | Stormwater management implementation (205-12616) | LS | 1 | $15,000 | $9,900.00 | $6,000.00 | $15,000 | $3,600.00 | $7,500.00 |
| 0018 | Excavation, foundation, unclassified (206-51230) | CYS | 22 | $72.32 | $58.00 | $78.00 | $60.00 | $194.00 | $75.00 |
| 0019 | Cofferdam (206-51235) | LS | 1 | $100,000 | $110,000 | $18,000 | $100,000 | $42,500 | $50,000 |
| 0020 | Subgrade treatment, type II (207-08264) | SYS | 184 | $21.00 | $38.00 | $35.00 | $30.00 | $46.00 | $45.00 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 1,098 | $38.85 | $49.00 | $35.00 | $60.00 | $63.00 | $50.00 |
| 0022 | Aggregate for end bent backfill (211-06467) | CYS | 22 | $116.00 | $160.00 | $180.00 | $170.00 | $164.00 | $150.00 |
| 0023 | Structure backfill, type 2 (211-09265) | CYS | 57 | $84.00 | $77.00 | $175.00 | $150.00 | $154.00 | $100.00 |
| 0024 | Geotextile for pavement, type 2B (214-12239) | SYS | 374 | $5.25 | $5.00 | $10.00 | $5.00 | $5.40 | $4.00 |
| 0025 | Compacted aggregate, no. 2 (301-12231) | CYS | 245 | $70.50 | $92.00 | $150.00 | $100.00 | $140.00 | $200.00 |
| 0026 | Compacted aggregate, no. 53 (301-12234) | CYS | 144 | $82.95 | $123.00 | $105.00 | $120.00 | $119.00 | $45.00 |
| 0027 | Subbase for PCCP (302-06464) | CYS | 36 | $232.57 | $173.00 | $150.00 | $140.00 | $180.00 | $165.00 |
| 0028 | Dense graded subbase (302-07455) | CYS | 17 | $89.25 | $153.00 | $210.00 | $120.00 | $273.00 | $150.00 |
| 0029 | Compacted aggregate, no. 53 (303-01180) | TON | 47 | $63.00 | $90.00 | $52.00 | $75.00 | $100.00 | $150.00 |
| 0030 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 96 | $11.83 | $25.00 | $8.00 | $11.00 | $18.00 | $10.00 |
| 0031 | Milling, transition (306-08043) | SYS | 667 | $4.86 | $7.00 | $2.50 | $15.00 | $12.00 | $10.00 |
| 0032 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 95 | $207.90 | $166.50 | $166.50 | $166.50 | $220.00 | $167.00 |
| 0033 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 100 | $190.05 | $168.00 | $168.00 | $168.00 | $210.00 | $169.00 |
| 0034 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 394 | $133.35 | $124.00 | $124.00 | $124.00 | $150.00 | $113.00 |
| 0035 | Joint adhesive (401-11526) | LFT | 590 | $1.47 | $2.75 | $2.75 | $2.75 | $1.60 | $0.60 |
| 0036 | Asphalt for tack coat (406-05520) | TON | 1 | $4,200.00 | $1.00 | $1.00 | $1.00 | $840.00 | $600.00 |
| 0037 | Terminal joint, type HMA (503-12477) | LFT | 59 | $303.25 | $350.00 | $310.00 | $300.00 | $311.00 | $350.00 |
| 0038 | Guardrail terminal system, W-beam, curved, modified (601-01704) | EACH | 1 | $2,966.25 | $750.00 | $2,825.00 | $2,825.00 | $2,825.00 | $2,825.00 |
| 0039 | Guardrail, remove (601-02241) | LFT | 404 | $3.15 | $0.10 | $3.00 | $3.00 | $3.00 | $3.00 |
| 0040 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 50 | $19.95 | $25.00 | $19.00 | $19.00 | $19.00 | $19.00 |
| 0041 | Guardrail height transition, MGS (601-12289) | EACH | 2 | $840.00 | $3,600.00 | $800.00 | $800.00 | $800.00 | $800.00 |
| 0042 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,228.75 | $3,500.00 | $3,075.00 | $3,075.00 | $3,075.00 | $3,075.00 |
| 0043 | Guardrail end treatment, type OS (601-94689) | EACH | 1 | $2,992.50 | $2,400.00 | $2,850.00 | $2,850.00 | $2,850.00 | $2,850.00 |
| 0044 | Barrier delineator (602-06729) | EACH | 22 | $134.73 | $18.00 | $25.00 | $50.00 | $21.00 | $20.00 |
| 0045 | Curb, HMA (605-05523) | LFT | 219 | $58.80 | $38.30 | $38.30 | $38.30 | $24.00 | $57.00 |
| 0046 | Gutter, concrete, type A (607-06175) | LFT | 55 | $65.58 | $98.00 | $74.84 | $90.00 | $99.00 | $151.00 |
| 0047 | Paved side ditch, type B (607-06340) | LFT | 133 | $57.63 | $88.00 | $133.90 | $75.00 | $112.00 | $123.00 |
| 0048 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 144 | $197.92 | $200.00 | $160.00 | $200.00 | $160.00 | $200.00 |
| 0049 | HMA for approaches, type B (610-07487) | TON | 42 | $196.35 | $154.40 | $154.40 | $154.40 | $235.00 | $292.00 |
| 0050 | PCCP for approaches, 6 in. (610-08446) | SYS | 94 | $135.45 | $107.00 | $96.63 | $130.00 | $115.00 | $128.00 |
| 0051 | Mailbox assembly, single (611-06497) | EACH | 3 | $262.50 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 0052 | Right-of-way marker (615-06490) | EACH | 2 | $157.50 | $450.00 | $150.00 | $150.00 | $150.00 | $150.00 |
| 0053 | Monument, type B (615-06505) | EACH | 2 | $1,008.00 | $1,800.00 | $960.00 | $960.00 | $960.00 | $960.00 |
| 0054 | Riprap, class 1 (616-05688) | TON | 248 | $220.42 | $164.00 | $170.00 | $150.00 | $165.00 | $120.00 |
| 0055 | Riprap, revetment (616-06405) | TON | 1,480 | $85.58 | $72.00 | $50.00 | $80.00 | $53.50 | $50.00 |
| 0056 | Geotextile for riprap, type 2A (616-12248) | SYS | 2,443 | $3.64 | $5.00 | $1.50 | $3.00 | $4.50 | $4.00 |
| 0057 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $577.50 | $550.00 | $550.00 | $550.00 | $550.00 | $550.00 |
| 0058 | Mulched seeding, type U (621-06560) | SYS | 1,212 | $3.44 | $3.28 | $3.28 | $3.28 | $3.28 | $3.28 |
| 0059 | Water (621-06567) | KGAL | 3 | $10.50 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 0060 | Sodding (621-06574) | SYS | 58 | $38.78 | $10.35 | $10.35 | $10.35 | $10.35 | $10.35 |
| 0061 | Sodding, nursery (621-06575) | SYS | 512 | $27.58 | $12.01 | $10.35 | $10.35 | $10.35 | $10.35 |
| 0062 | Field office, type A (628-09401) | MOS | 12 | $2,926.73 | $3,500.00 | $1,850.00 | $3,500.00 | $3,000.00 | $3,000.00 |
| 0063 | Concrete, A, substructure (702-51005) | CYS | 12 | $1,739.11 | $1,150.00 | $1,650.00 | $2,000.00 | $2,500.00 | $500.00 |
| 0064 | Field drilled hole in concrete (702-51863) | EACH | 72 | $18.12 | $38.00 | $23.00 | $30.00 | $12.00 | $20.00 |
| 0065 | Reinforcing bars, epoxy coated (703-06029) | LBS | 135,375 | $1.41 | $1.54 | $1.20 | $1.75 | $1.90 | $1.50 |
| 0066 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 32 | $50.69 | $47.00 | $56.00 | $50.00 | $43.00 | $15.00 |
| 0067 | Concrete, C, superstructure (704-51002) | CYS | 391 | $864.17 | $1,350.00 | $835.00 | $1,500.00 | $1,300.00 | $1,750.00 |
| 0068 | Railing, concrete type FC (706-09960) | LFT | 728 | $70.35 | $70.00 | $68.00 | $68.00 | $49.00 | $68.00 |
| 0069 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 4 | $1,470.00 | $2,100.00 | $2,000.00 | $2,000.00 | $2,400.00 | $2,000.00 |
| 0070 | Surface seal (709-51821) | LS | 1 | $5,250.00 | $1.00 | $0.01 | $15,000 | $1,300.00 | $0.01 |
| 0071 | Patching concrete structures (710-09158) | SFT | 184 | $183.75 | $153.71 | $180.00 | $175.00 | $175.00 | $175.00 |
| 0072 | Jacking and supporting beams (711-51877) | LS | 1 | $43,680 | $185,000 | $85,000 | $105,000 | $36,000 | $1,000.00 |
| 0073 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 170 | $60.90 | $153.00 | $44.00 | $65.00 | $85.00 | $120.00 |
| 0074 | Pipe, type 2, deformed, min. area 1.83 SFT (715-05327) | LFT | 30 | $157.50 | $191.00 | $125.00 | $150.00 | $120.00 | $150.00 |
| 0075 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 120 | $11.02 | $15.00 | $14.00 | $20.00 | $18.00 | $15.00 |
| 0076 | Pipe end section, diameter 18 in. (715-46010) | EACH | 1 | $1,123.13 | $769.00 | $1,200.00 | $1,200.00 | $1,475.00 | $1,500.00 |
| 0077 | Pipe end section, min. area 1.8 SFT (715-46055) | EACH | 2 | $2,947.27 | $1,411.00 | $1,500.00 | $1,500.00 | $2,150.00 | $2,500.00 |
| 0078 | Geotextile for underdrains, type 2A (718-12307) | SYS | 54 | $12.13 | $9.00 | $15.00 | $11.00 | $13.40 | $4.00 |
| 0079 | Longitudinal grooving (722-12732) | SYS | 1,132 | $11.20 | $4.78 | $3.39 | $7.00 | $3.00 | $2.50 |
| 0080 | Bearing assembly, elastomeric (726-92406) | EACH | 50 | $480.64 | $600.00 | $350.00 | $1,600.00 | $510.00 | $350.00 |
| 0081 | Construction sign, type C (801-03290) | EACH | 2 | $367.50 | $350.00 | $350.00 | $850.00 | $350.00 | $350.00 |
| 0082 | Construction sign, type D (801-03291) | EACH | 4 | $178.50 | $400.00 | $170.00 | $550.00 | $170.00 | $170.00 |
| 0083 | Road closure sign assembly (801-04308) | EACH | 4 | $315.00 | $500.00 | $300.00 | $300.00 | $300.00 | $300.00 |
| 0084 | Detour route marker assembly (801-06625) | EACH | 24 | $120.75 | $200.00 | $115.00 | $115.00 | $115.00 | $115.00 |
| 0085 | Construction sign, type A (801-06640) | EACH | 7 | $189.00 | $300.00 | $180.00 | $180.00 | $180.00 | $180.00 |
| 0086 | Maintaining traffic (801-06775) | LS | 1 | $15,196 | $27,000 | $25,000 | $10,000 | $16,500 | $5,000.00 |
| 0087 | Barricade, type III-A (801-07118) | LFT | 60 | $16.80 | $25.00 | $16.00 | $16.00 | $16.00 | $16.00 |
| 0088 | Barricade, type III-B (801-07119) | LFT | 48 | $16.80 | $48.00 | $16.00 | $16.00 | $16.00 | $16.00 |
| 0089 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 6 | $39.90 | $25.00 | $38.00 | $38.00 | $38.00 | $38.00 |
| 0090 | Sign post, type A (802-76055) | LFT | 10 | $29.40 | $20.00 | $28.00 | $28.00 | $28.00 | $28.00 |
| 0091 | Line, multi-component, solid, white, 4 in. (808-10033) | LFT | 1,600 | $1.05 | $2.50 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0092 | Line, multi-component, solid, yellow, 4 in. (808-10034) | LFT | 2,170 | $1.05 | $2.50 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0093 | Line, multi-component, broken, yellow, 4 in. (808-10036) | LFT | 142 | $1.37 | $2.50 | $1.30 | $1.30 | $1.30 | $1.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 14, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way