INDOT contract B-42795-A bid tabulation
SUPERSTRUCTURE REPAIR AND REHABILITATION. Let by Indiana DOT on January 15, 2025, Howard, Greenfield. 6 bids received; low bid $1,891,742 by Superior Construction Co Inc.
- Owner
- Indiana DOT
- Letting
- 15 JAN 2025
- Pay items
- 94
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Superior Construction Co Inc | $1,891,742 | Low |
| 2 | E & B Paving LLC | $1,987,000 | +5.0% |
| 3 | Rieth-Riley Construction Co., Inc. | $1,988,156 | +5.0% |
| 4 | Milestone Contractors LP | $2,066,959 | +9.0% |
| 5 | Beaty Construction Inc | $2,284,645 | +21% |
| 6 | His Constructors Inc | $2,285,777 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Superior Construction Co Inc | 2. E & B Paving LLC | 3. Rieth-Riley Construction Co., Inc. | 4. Milestone Contractors LP | 5. Beaty Construction Inc | 6. His Constructors Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $75,000 | $40,000 | $19,400 | $31,196 | $22,802 | $29,779 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $92,000 | $99,227 | $99,408 | $103,348 | $113,350 | $89,520 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $37,000 | $39,743 | $39,763 | $41,339 | $45,000 | $36,672 |
| 0011 | Regulated asbestos containing materials, remove (202-03135) | SFT | 15 | $150.00 | $286.00 | $200.00 | $286.00 | $566.00 | $653.05 |
| 0012 | Present structure, remove portions, structure no. 34-00056 (202-51328) | LS | 1 | $249,321 | $270,000 | $224,830 | $225,000 | $417,656 | $123,444 |
| 0013 | Excavation, common (203-02000) | CYS | 460 | $65.00 | $80.00 | $103.20 | $97.00 | $58.60 | $99.25 |
| 0014 | Borrow (203-02070) | CYS | 165 | $0.01 | $1.00 | $0.01 | $206.00 | $90.00 | $106.00 |
| 0015 | Stormwater management budget (205-12108) | DOL | 35,405 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0016 | Stormwater management implementation (205-12616) | LS | 1 | $25,000 | $50,000 | $33,389 | $7,500.00 | $15,000 | $112,867 |
| 0017 | SWQCP preparation (205-12618) | LS | 1 | $1,700.00 | $5,000.00 | $3,500.00 | $7,500.00 | $2,700.00 | $22,857 |
| 0018 | Excavation, foundation, unclassified (206-51230) | CYS | 44 | $82.16 | $60.00 | $58.46 | $69.00 | $120.00 | $104.71 |
| 0019 | Cofferdam (206-51235) | LS | 1 | $21,000 | $60,000 | $65,989 | $100,000 | $100,000 | $88,366 |
| 0020 | Subgrade treatment, type II (207-08264) | SYS | 51 | $34.84 | $50.00 | $66.57 | $42.00 | $40.00 | $108.36 |
| 0021 | Subgrade treatment, type IC (207-09935) | SYS | 1,426 | $35.25 | $50.00 | $37.33 | $45.00 | $42.00 | $27.23 |
| 0022 | Aggregate for end bent backfill (211-06467) | CYS | 20 | $124.56 | $140.00 | $276.42 | $120.00 | $280.00 | $280.10 |
| 0023 | Structure backfill, type 1 (211-09264) | CYS | 18 | $45.14 | $125.00 | $39.20 | $321.00 | $54.00 | $152.66 |
| 0024 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,426 | $5.36 | $5.00 | $3.61 | $3.00 | $5.00 | $4.44 |
| 0025 | Compacted aggregate, no. 53 (301-12234) | CYS | 45 | $106.17 | $115.00 | $178.94 | $98.00 | $160.00 | $153.48 |
| 0026 | Subbase for PCCP (302-06464) | CYS | 37 | $111.79 | $200.00 | $190.51 | $248.00 | $160.00 | $179.34 |
| 0027 | Compacted aggregate, no. 53 (303-01180) | TON | 307 | $37.80 | $35.00 | $73.41 | $53.00 | $50.00 | $74.29 |
| 0028 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 128 | $25.49 | $35.00 | $29.82 | $17.00 | $50.00 | $80.39 |
| 0029 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 100 | $190.00 | $209.00 | $296.73 | $140.80 | $209.00 | $272.98 |
| 0030 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 152 | $160.00 | $127.00 | $196.99 | $111.35 | $127.00 | $146.28 |
| 0031 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 424 | $165.00 | $112.00 | $122.02 | $112.67 | $112.00 | $233.52 |
| 0032 | Joint adhesive, surface (401-10258) | LFT | 394 | $2.00 | $1.00 | $0.87 | $2.89 | $1.00 | $1.31 |
| 0033 | Joint adhesive, intermediate (401-10259) | LFT | 344 | $2.00 | $1.00 | $0.94 | $3.38 | $1.00 | $1.31 |
| 0034 | Liquid asphalt sealant (401-11785) | LFT | 394 | $1.00 | $0.01 | $0.01 | $0.01 | $0.01 | $0.13 |
| 0035 | Asphalt for tack coat (406-05521) | SYS | 3,836 | $0.01 | $0.25 | $0.01 | $0.11 | $0.25 | $0.33 |
| 0036 | Terminal joint, type HMA (503-12477) | LFT | 58 | $361.26 | $450.00 | $361.89 | $375.00 | $565.00 | $521.47 |
| 0037 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $2,500.00 | $3,150.00 | $3,150.00 | $2,500.00 | $2,500.00 | $3,265.26 |
| 0038 | Guardrail terminal system, W-beam curved, type 6 (601-01839) | EACH | 2 | $2,700.00 | $2,850.00 | $2,850.00 | $2,700.00 | $2,700.00 | $3,526.48 |
| 0039 | Guardrail terminal system, W-beam curved, type 3 (601-01846) | EACH | 1 | $2,500.00 | $2,850.00 | $2,850.00 | $2,500.00 | $2,500.00 | $3,265.26 |
| 0040 | Guardrail, remove (601-02241) | LFT | 1,080 | $5.50 | $3.00 | $3.00 | $3.00 | $6.00 | $6.53 |
| 0041 | Hand dig guardrail post holes (601-09238) | EACH | 9 | $75.00 | $80.00 | $80.00 | $75.00 | $75.00 | $97.96 |
| 0042 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 632 | $19.00 | $18.00 | $18.00 | $19.00 | $19.00 | $24.82 |
| 0043 | Guardrail, MGS W-beam, 3 FT 1.5 in. spacing (601-12282) | LFT | 10 | $31.00 | $38.00 | $38.00 | $31.00 | $31.00 | $40.49 |
| 0044 | Guardrail height transition, MGS (601-12289) | EACH | 2 | $795.00 | $1,125.00 | $1,125.00 | $795.00 | $800.00 | $1,038.36 |
| 0045 | Guardrail transition, MGS with curb (601-12291) | EACH | 1 | $2,600.00 | $3,200.00 | $3,200.00 | $2,600.00 | $2,600.00 | $3,395.87 |
| 0046 | Guardrail transition, MGS without curb (601-12292) | EACH | 2 | $2,556.00 | $3,100.00 | $3,100.00 | $2,556.00 | $2,560.00 | $3,338.41 |
| 0047 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $2,850.00 | $2,975.00 | $2,975.00 | $2,850.00 | $2,850.00 | $3,722.40 |
| 0048 | Barrier delineator (602-06729) | EACH | 12 | $20.00 | $25.00 | $32.22 | $5.00 | $30.00 | $34.27 |
| 0049 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 184 | $168.58 | $200.00 | $224.00 | $200.00 | $250.56 | $330.08 |
| 0050 | HMA for approaches, type B (610-07487) | TON | 13 | $300.00 | $280.00 | $278.92 | $259.83 | $300.07 | $365.71 |
| 0051 | Right-of-way marker (615-06490) | EACH | 11 | $180.00 | $150.00 | $150.00 | $180.00 | $180.00 | $235.10 |
| 0052 | Monument, type B (615-06505) | EACH | 2 | $1,500.00 | $1,125.00 | $1,125.00 | $1,500.00 | $1,500.00 | $1,959.16 |
| 0053 | Grout for riprap (616-02281) | CYS | 46 | $410.65 | $150.00 | $407.65 | $356.00 | $430.00 | $195.92 |
| 0054 | Riprap, revetment (616-06405) | TON | 141 | $74.93 | $75.00 | $134.68 | $63.00 | $74.00 | $172.22 |
| 0055 | Riprap, grouted, 36 in. (616-12133) | SYS | 126 | $526.42 | $225.00 | $333.36 | $275.00 | $460.00 | $81.06 |
| 0056 | Geotextile for riprap, type 1A (616-12246) | SYS | 366 | $4.60 | $5.00 | $1.60 | $3.00 | $7.50 | $9.56 |
| 0057 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $300.00 | $300.00 | $300.00 | $300.00 | $300.00 | $391.83 |
| 0058 | Erosion control blanket (621-02770) | SYS | 2,301 | $2.98 | $2.98 | $2.98 | $2.98 | $3.00 | $3.89 |
| 0059 | Mulched seeding, type R (621-06559) | SYS | 1,069 | $0.92 | $0.92 | $0.92 | $0.92 | $0.95 | $2.19 |
| 0060 | Sodding (621-06574) | SYS | 225 | $10.50 | $10.50 | $10.50 | $10.50 | $10.50 | $13.71 |
| 0061 | Seed mixture, floodplain (621-12612) | LBS | 28 | $99.00 | $99.00 | $99.00 | $99.00 | $99.00 | $129.30 |
| 0062 | Field office, type C (628-09403) | MOS | 10 | $1,511.45 | $4,200.00 | $3,651.31 | $3,504.42 | $2,650.00 | $3,213.02 |
| 0063 | Computer system equipment (628-11976) | EACH | 1 | $500.00 | $2,500.00 | $1,073.91 | $450.00 | $1.00 | $940.40 |
| 0064 | Grates, basins, and fittings, cast iron (702-12076) | EACH | 6 | $1,571.92 | $2,500.00 | $1,712.12 | $1,750.00 | $2,100.00 | $1,609.11 |
| 0065 | Concrete, A, substructure (702-51005) | CYS | 14.90 | $2,338.13 | $5,200.00 | $5,008.02 | $2,500.00 | $5,850.00 | $7,666.09 |
| 0066 | Field drilled hole in concrete (702-51863) | EACH | 24 | $22.70 | $40.00 | $33.59 | $20.00 | $25.00 | $77.27 |
| 0067 | Reinforcing bars (703-06028) | LBS | 2,931 | $1.20 | $1.00 | $1.47 | $1.75 | $1.30 | $2.61 |
| 0068 | Reinforcing bars, epoxy coated (703-06029) | LBS | 56,462 | $1.17 | $1.15 | $1.14 | $1.25 | $1.30 | $1.57 |
| 0069 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 38 | $46.61 | $15.00 | $67.08 | $75.00 | $50.00 | $80.00 |
| 0070 | Concrete, C, superstructure (704-51002) | CYS | 134.10 | $999.82 | $1,100.00 | $1,653.67 | $1,500.00 | $1,400.00 | $1,731.04 |
| 0071 | Concrete bridge railing transition, type TPF-1 (706-06351) | EACH | 4 | $5,500.00 | $4,500.00 | $6,530.00 | $4,000.00 | $4,450.00 | $8,528.86 |
| 0072 | Railing, concrete type PF-1 (706-09962) | LFT | 281 | $150.00 | $75.00 | $149.00 | $100.00 | $90.00 | $194.61 |
| 0073 | Railing, steel type PF-1 (706-11404) | LFT | 299 | $71.00 | $70.00 | $70.00 | $86.68 | $71.00 | $92.73 |
| 0074 | Surface seal , bridge no. 34-00056 (709-51821) | LS | 1 | $1.00 | $0.01 | $1.00 | $3,000.00 | $0.01 | $3,996.68 |
| 0075 | Patching concrete structures (710-09158) | SFT | 120 | $100.00 | $100.00 | $196.00 | $100.00 | $200.00 | $130.61 |
| 0076 | Structural steel (711-51038) | LS | 1 | $400,000 | $450,000 | $385,977 | $523,318 | $420,730 | $458,150 |
| 0077 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 62 | $52.14 | $80.00 | $81.01 | $136.00 | $240.00 | $192.61 |
| 0078 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 85 | $74.33 | $70.00 | $90.09 | $51.00 | $160.00 | $179.30 |
| 0079 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 110 | $11.67 | $25.00 | $38.43 | $25.00 | $14.25 | $16.80 |
| 0080 | Pipe, roadway drain casting extension (715-10238) | EACH | 6 | $772.62 | $750.00 | $786.23 | $600.00 | $900.00 | $1,046.70 |
| 0081 | Pipe end section, diameter 15 in. (715-46005) | EACH | 2 | $1,307.42 | $1,500.00 | $720.09 | $800.00 | $1,225.00 | $2,962.26 |
| 0082 | Geotextile for underdrains, type 1A (718-12305) | SYS | 54 | $12.91 | $5.00 | $4.87 | $6.00 | $7.75 | $15.72 |
| 0083 | Longitudinal grooving (722-12732) | SYS | 652 | $5.37 | $10.00 | $5.58 | $6.00 | $6.65 | $7.18 |
| 0084 | Bearing assembly, elastomeric (726-92406) | EACH | 20 | $1,403.91 | $1,600.00 | $1,363.88 | $2,000.00 | $1,800.00 | $1,824.71 |
| 0085 | Road closure sign assembly (801-04308) | EACH | 4 | $242.00 | $242.00 | $242.00 | $242.00 | $250.00 | $261.22 |
| 0086 | Detour route marker assembly (801-06625) | EACH | 26 | $155.00 | $155.00 | $155.00 | $155.00 | $155.00 | $97.96 |
| 0087 | Construction sign, type A (801-06640) | EACH | 10 | $168.00 | $168.00 | $168.00 | $168.00 | $170.00 | $261.22 |
| 0088 | Maintaining traffic (801-06775) | LS | 1 | $75,000 | $15,000 | $1,250.00 | $5,000.00 | $45,000 | $4,571.37 |
| 0089 | Barricade, type III-A (801-07118) | LFT | 48 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 | $23.51 |
| 0090 | Barricade, type III-B (801-07119) | LFT | 40 | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 | $23.51 |
| 0091 | Sign, ground mounted, reset (802-91122) | EACH | 2 | $333.00 | $350.00 | $350.00 | $333.00 | $675.00 | $436.24 |
| 0092 | Line, paint, broken, yellow, 4 in. (808-06712) | LFT | 150 | $2.64 | $2.64 | $2.64 | $2.64 | $2.65 | $1.31 |
| 0093 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 1,200 | $0.70 | $0.70 | $0.70 | $0.70 | $0.70 | $1.31 |
| 0094 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 360 | $0.70 | $0.70 | $0.70 | $0.70 | $0.70 | $1.31 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 15, 2025. Compiled by Mirage Metrics.