INDOT contract B-43624-A bid tabulation
BRIDGE REPLACEMENT. Let by Indiana DOT on November 13, 2025, Wells, Fort Wayne. 6 bids received; low bid $985,423 by Duncan Robertson Inc.
- Owner
- Indiana DOT
- Letting
- 13 NOV 2025
- Pay items
- 65
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Duncan Robertson Inc | $985,423 | Low |
| 2 | His Constructors Inc | $1,026,946 | +4.0% |
| 3 | Pontem Contractors Inc | $1,091,407 | +11% |
| 4 | Miller Bros Construction Inc | $1,159,916 | +18% |
| 5 | Milestone Contractors LP | $1,185,117 | +20% |
| 6 | R L McCoy Inc | $1,328,183 | +35% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Duncan Robertson Inc | 2. His Constructors Inc | 3. Pontem Contractors Inc | 4. Miller Bros Construction Inc | 5. Milestone Contractors LP | 6. R L McCoy Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $12,500 | $20,000 | $20,000 | $8,160.00 | $25,000 | $20,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $50,000 | $51,347 | $54,500 | $57,996 | $59,256 | $66,400 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $30,000 | $30,808 | $32,500 | $21,623 | $21,000 | $39,800 |
| 0011 | Present structure, remove, structure no. 90-00071 (202-51330) | LS | 1 | $50,000 | $55,000 | $106,826 | $106,575 | $100,000 | $144,000 |
| 0012 | Excavation, common (203-02000) | CYS | 655 | $50.00 | $56.00 | $67.53 | $48.21 | $96.00 | $78.00 |
| 0013 | Excavation, waterway (203-51223) | CYS | 210 | $50.00 | $32.00 | $55.28 | $94.58 | $80.00 | $64.00 |
| 0014 | Stormwater management budget (205-12108) | DOL | 25,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $20,000 | $2,500.00 | $5,020.53 | $7,300.00 | $2,550.00 | $6,000.00 |
| 0016 | Excavation, wet (206-51220) | CYS | 165 | $150.00 | $53.00 | $76.40 | $108.99 | $136.00 | $120.00 |
| 0017 | Excavation, foundation, unclassified (206-51230) | CYS | 38 | $150.00 | $59.00 | $64.79 | $182.19 | $168.00 | $80.00 |
| 0018 | Cofferdam (206-51235) | LS | 1 | $10,000 | $32,449 | $75,000 | $75,140 | $104,891 | $110,000 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 1,540 | $40.00 | $26.00 | $35.91 | $25.91 | $32.00 | $48.00 |
| 0020 | Structure backfill, type 1 (211-09264) | CYS | 5 | $85.00 | $260.00 | $116.23 | $134.45 | $326.00 | $80.00 |
| 0021 | Structure backfill, type 4 (211-09267) | CYS | 18 | $300.00 | $301.00 | $218.23 | $388.56 | $313.00 | $375.00 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 150 | $5.00 | $13.00 | $5.37 | $14.78 | $14.00 | $11.00 |
| 0023 | Compacted aggregate, no. 53 (301-12234) | CYS | 245 | $75.00 | $73.00 | $77.17 | $103.14 | $97.00 | $80.00 |
| 0024 | Subbase for PCCP (302-06464) | CYS | 38 | $100.00 | $130.00 | $146.96 | $168.37 | $254.00 | $145.00 |
| 0025 | Compacted aggregate, no. 53 (303-01180) | TON | 270 | $55.00 | $35.00 | $49.68 | $43.37 | $52.00 | $46.00 |
| 0026 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 115 | $132.00 | $120.00 | $126.00 | $120.00 | $120.00 | $120.00 |
| 0027 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 195 | $105.00 | $95.00 | $99.75 | $95.00 | $95.00 | $95.00 |
| 0028 | Joint adhesive (401-11526) | LFT | 1,160 | $0.77 | $0.70 | $0.74 | $0.70 | $0.70 | $0.70 |
| 0029 | Asphalt for tack coat (406-05521) | SYS | 1,350 | $0.40 | $0.35 | $0.37 | $0.35 | $0.35 | $0.35 |
| 0030 | Guardrail, W-beam, shop curved, 6 FT 3 in. spacing (601-02103) | LFT | 62 | $44.00 | $22.00 | $23.10 | $22.00 | $22.00 | $22.00 |
| 0031 | Guardrail, remove (601-02241) | LFT | 100 | $7.70 | $7.00 | $7.35 | $7.00 | $7.00 | $7.00 |
| 0032 | Guardrail transition, type TGS-1 (601-06374) | EACH | 4 | $1,650.00 | $1,225.00 | $1,286.25 | $1,225.00 | $1,225.00 | $1,225.00 |
| 0033 | Guardrail terminal (601-52540) | EACH | 2 | $88.00 | $2,850.00 | $2,992.50 | $2,850.00 | $2,850.00 | $2,850.00 |
| 0034 | Guardrail end treatment, type OS , 27 inch (601-94689) | EACH | 2 | $3,300.00 | $2,900.00 | $3,045.00 | $2,900.00 | $2,900.00 | $2,900.00 |
| 0035 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 19 | $25.00 | $30.00 | $31.50 | $30.00 | $30.00 | $30.00 |
| 0036 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 150 | $225.00 | $200.00 | $214.20 | $173.64 | $165.00 | $260.00 |
| 0037 | Monument, type B (615-06505) | EACH | 2 | $1,070.00 | $975.00 | $1,023.75 | $975.00 | $975.00 | $975.00 |
| 0038 | Riprap, revetment (616-06405) | TON | 365 | $45.00 | $84.00 | $52.54 | $100.25 | $38.00 | $75.00 |
| 0039 | Geotextile for riprap, type 1A (616-12246) | SYS | 550 | $3.50 | $4.00 | $4.81 | $5.47 | $4.80 | $4.00 |
| 0040 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $495.00 | $450.00 | $472.50 | $450.00 | $450.00 | $450.00 |
| 0041 | Mulched seeding, type R (621-06559) | SYS | 2,800 | $2.20 | $1.98 | $2.08 | $1.98 | $1.98 | $1.98 |
| 0042 | Water (621-06567) | KGAL | 1 | $11.00 | $10.00 | $10.50 | $1.00 | $10.00 | $10.00 |
| 0043 | Sodding (621-06574) | SYS | 45 | $48.00 | $43.50 | $65.73 | $43.50 | $43.50 | $43.50 |
| 0044 | Field office, type C (628-09403) | MOS | 6 | $2,750.00 | $2,800.00 | $3,725.87 | $3,812.72 | $3,150.00 | $3,900.00 |
| 0045 | Pile shoe, HP 12 X 53 (701-09739) | EACH | 32 | $200.00 | $110.00 | $120.10 | $138.66 | $176.00 | $150.00 |
| 0046 | Pile, steel H, HP 12 X 53 (701-51195) | LFT | 600 | $95.00 | $86.00 | $61.77 | $105.14 | $116.00 | $75.00 |
| 0047 | Concrete, A, substructure (702-51005) | CYS | 87 | $680.00 | $850.00 | $811.93 | $704.13 | $660.00 | $800.00 |
| 0048 | Concrete, B, footings (702-51015) | CYS | 33.80 | $680.00 | $650.00 | $597.46 | $729.39 | $651.00 | $1,100.00 |
| 0049 | Reinforcing bars (703-06028) | LBS | 23,596 | $1.40 | $1.48 | $1.34 | $1.46 | $2.03 | $1.30 |
| 0050 | Reinforcing bars, epoxy coated (703-06029) | LBS | 56,053 | $1.40 | $1.50 | $1.45 | $1.58 | $1.70 | $1.40 |
| 0051 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 28 | $65.00 | $53.00 | $49.28 | $53.84 | $49.00 | $58.00 |
| 0052 | Concrete, C, superstructure (704-51002) | CYS | 175.30 | $950.00 | $1,300.00 | $976.32 | $1,267.48 | $995.00 | $1,450.00 |
| 0053 | Railing, steel type TS-1 (706-06344) | LFT | 200 | $95.00 | $82.00 | $77.70 | $74.00 | $106.00 | $74.00 |
| 0054 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 24 | $130.00 | $52.00 | $85.85 | $131.46 | $59.00 | $120.00 |
| 0055 | Pipe end section, diameter 15 in. (715-46005) | EACH | 1 | $1,100.00 | $583.00 | $1,310.39 | $1,119.47 | $1,100.00 | $700.00 |
| 0056 | Longitudinal grooving (722-12732) | SYS | 419 | $12.00 | $9.50 | $14.30 | $8.35 | $5.00 | $15.00 |
| 0057 | Road closure sign assembly (801-04308) | EACH | 4 | $365.00 | $332.00 | $348.60 | $332.00 | $200.00 | $332.00 |
| 0058 | Detour route marker assembly (801-06625) | EACH | 4 | $180.00 | $163.00 | $171.15 | $163.00 | $100.00 | $163.00 |
| 0059 | Construction sign, type A (801-06640) | EACH | 8 | $265.00 | $241.00 | $253.05 | $241.00 | $200.00 | $241.00 |
| 0060 | Construction sign, type B (801-06645) | EACH | 2 | $110.00 | $102.00 | $107.10 | $102.00 | $75.00 | $102.00 |
| 0061 | Maintaining traffic (801-06775) | LS | 1 | $12,500 | $2,500.00 | $9,649.71 | $6,699.25 | $3,350.00 | $500.00 |
| 0062 | Barricade, type III-A (801-07118) | LFT | 48 | $17.50 | $16.06 | $16.86 | $16.06 | $18.00 | $16.06 |
| 0063 | Barricade, type III-B (801-07119) | LFT | 48 | $17.50 | $16.06 | $16.86 | $16.06 | $18.00 | $16.06 |
| 0064 | Line, paint, broken, yellow, 4 in. (808-06712) | LFT | 175 | $2.70 | $2.44 | $2.56 | $2.44 | $1.50 | $2.44 |
| 0065 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 1,400 | $0.85 | $0.78 | $0.82 | $0.78 | $1.00 | $0.78 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of November 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.