INDOT contract B-43733-A bid tabulation
BRIDGE DECK OVERLAY AND SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on July 9, 2025, Jackson, Washington, Seymour. 6 bids received; low bid $6,882,400 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 09 JUL 2025
- Pay items
- 161
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $6,882,400 | Low |
| 2 | Dave Omara Contractor Inc | $7,189,000 | +4.0% |
| 3 | Ragle, Inc. | $7,497,521 | +9.0% |
| 4 | Force Construction Co Inc | $7,637,581 | +11% |
| 5 | Beaty Construction Inc | $8,810,750 | +28% |
| 6 | Milestone Contractors LP | $9,225,438 | +34% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Dave Omara Contractor Inc | 3. Ragle, Inc. | 4. Force Construction Co Inc | 5. Beaty Construction Inc | 6. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $150,000 | $34,000 | $45,750 | $54,110 | $75,000 | $140,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $481,400 | $357,727 | $375,000 | $380,000 | $420,000 | $534,378 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $98,962 | $87,600 | $75,000 | $44,560 | $100,000 | $200,000 |
| 0011 | Pavement removal (202-02240) | SYS | 739 | $40.00 | $100.00 | $45.00 | $34.00 | $90.00 | $93.00 |
| 0012 | Gutter lip, remove (202-02277) | LFT | 58 | $40.00 | $60.00 | $21.52 | $19.00 | $20.00 | $49.25 |
| 0013 | Casting, remove (202-02772) | EACH | 4 | $100.00 | $300.00 | $135.00 | $323.00 | $350.00 | $284.25 |
| 0014 | Present structure, remove portions, structure no. 2 (202-51328) | LS | 1 | $240,000 | $70,000 | $100,000 | $77,940 | $80,000 | $150,000 |
| 0015 | Present structure, remove portions, structure no. 3 (202-51328) | LS | 1 | $480,000 | $150,000 | $200,000 | $74,970 | $150,000 | $325,000 |
| 0016 | Pipe, remove (202-96133) | LFT | 20 | $668.00 | $100.00 | $27.50 | $75.00 | $20.00 | $41.50 |
| 0017 | Excavation, common (203-02000) | CYS | 1,356 | $120.00 | $140.00 | $42.50 | $61.00 | $61.00 | $71.00 |
| 0018 | Borrow (203-02070) | CYS | 57 | $69.00 | $40.00 | $25.00 | $63.00 | $20.00 | $1.20 |
| 0019 | Linear grading (203-08607) | LFT | 517 | $15.00 | $7.00 | $6.50 | $8.40 | $7.00 | $22.50 |
| 0020 | Pump around (205-11626) | EACH | 4 | $5,350.00 | $13,500 | $8,500.00 | $15,250 | $18,000 | $40,000 |
| 0021 | Stormwater management budget (205-12108) | DOL | 123,240 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0022 | Stormwater management implementation (205-12616) | LS | 1 | $60,000 | $50,000 | $35,000 | $51,980 | $61,000 | $28,423 |
| 0023 | SWQCP preparation (205-12618) | LS | 1 | $5,200.00 | $3,500.00 | $1,900.00 | $7,711.00 | $1,900.00 | $1,900.00 |
| 0024 | Cofferdam (206-51235) | LS | 1 | $20,000 | $450,000 | $300,000 | $381,130 | $500,000 | $991,300 |
| 0025 | Subgrade treatment, type II (207-08264) | SYS | 89 | $60.00 | $20.00 | $48.50 | $49.00 | $58.00 | $100.00 |
| 0026 | Subgrade treatment, type IC (207-09935) | SYS | 2,129 | $60.00 | $70.00 | $65.00 | $52.00 | $47.00 | $46.75 |
| 0027 | Aggregate for end bent backfill (211-06467) | CYS | 38 | $150.00 | $140.00 | $200.00 | $124.00 | $90.00 | $184.00 |
| 0028 | Structure backfill, type 2 (211-09265) | CYS | 84 | $36.00 | $120.00 | $163.50 | $127.00 | $50.00 | $293.75 |
| 0029 | Structure backfill, type 5 (211-09268) | CYS | 95 | $307.00 | $250.00 | $232.50 | $306.00 | $188.00 | $261.50 |
| 0030 | Geogrid, type IB (214-11796) | SYS | 602 | $2.50 | $3.00 | $2.50 | $5.90 | $8.00 | $6.30 |
| 0031 | Geotextile for pavement, type 2A (214-12238) | SYS | 270 | $9.00 | $3.00 | $5.50 | $9.10 | $5.00 | $9.30 |
| 0032 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,811 | $5.00 | $3.00 | $5.25 | $6.90 | $5.00 | $6.30 |
| 0033 | Compacted aggregate, no. 8 (301-12233) | CYS | 100 | $145.00 | $100.00 | $150.00 | $92.00 | $240.00 | $91.25 |
| 0034 | Compacted aggregate, no. 53 (301-12234) | CYS | 69 | $150.00 | $80.00 | $190.00 | $90.00 | $270.00 | $105.75 |
| 0035 | Subbase for PCCP (302-06464) | CYS | 230 | $250.00 | $200.00 | $155.00 | $125.00 | $210.00 | $202.25 |
| 0036 | Compacted aggregate, no. 53 (303-01180) | TON | 860 | $50.00 | $40.00 | $70.00 | $57.00 | $73.00 | $64.00 |
| 0037 | Widening with HMA, type B (304-07493) | TON | 24 | $580.00 | $330.00 | $380.00 | $453.00 | $250.00 | $380.00 |
| 0038 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 334 | $20.00 | $13.00 | $15.00 | $18.00 | $8.50 | $20.50 |
| 0039 | Milling, transition (306-08043) | SYS | 5,251 | $10.00 | $6.00 | $1.35 | $5.10 | $6.00 | $14.70 |
| 0040 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 216 | $380.00 | $200.00 | $247.00 | $254.00 | $200.00 | $247.00 |
| 0041 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 381 | $262.00 | $155.00 | $195.00 | $200.00 | $200.00 | $195.00 |
| 0042 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 110 | $335.00 | $236.00 | $277.00 | $285.00 | $200.00 | $277.00 |
| 0043 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 85 | $427.00 | $220.00 | $316.00 | $325.00 | $200.00 | $316.00 |
| 0044 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 580 | $243.00 | $126.00 | $179.00 | $184.00 | $200.00 | $179.00 |
| 0045 | Joint adhesive, surface (401-10258) | LFT | 5,599 | $0.10 | $5.00 | $0.75 | $0.75 | $1.25 | $0.75 |
| 0046 | Joint adhesive, intermediate (401-10259) | LFT | 1,124 | $0.10 | $15.00 | $5.20 | $5.40 | $1.25 | $5.20 |
| 0047 | Asphalt for tack coat (406-05521) | SYS | 9,060 | $0.10 | $0.50 | $0.25 | $0.25 | $0.50 | $0.25 |
| 0048 | Terminal joint, type HMA (503-12477) | LFT | 176 | $225.00 | $700.00 | $400.00 | $532.00 | $500.00 | $380.75 |
| 0049 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $2,825.00 | $2,450.00 | $2,825.00 | $2,905.00 | $2,450.00 | $2,825.00 |
| 0050 | Guardrail terminal system, W-beam curved, type 3 (601-01846) | EACH | 1 | $2,750.00 | $2,500.00 | $2,750.00 | $2,827.00 | $2,500.00 | $2,750.00 |
| 0051 | Guardrail, remove (601-02241) | LFT | 2,095 | $4.00 | $9.50 | $9.50 | $4.10 | $9.50 | $4.00 |
| 0052 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 1,019 | $20.00 | $20.00 | $20.00 | $21.00 | $20.00 | $20.00 |
| 0053 | Guardrail height transition, MGS (601-12289) | EACH | 5 | $950.00 | $800.00 | $950.00 | $977.00 | $800.00 | $950.00 |
| 0054 | Guardrail transition, MGS without curb (601-12292) | EACH | 11 | $3,300.00 | $2,700.00 | $3,300.00 | $3,393.00 | $2,700.00 | $3,300.00 |
| 0055 | Guardrail end treatment, type OS (601-94689) | EACH | 6 | $2,975.00 | $2,900.00 | $2,975.00 | $3,059.00 | $2,900.00 | $2,975.00 |
| 0056 | Guardrail, W-beam, 6 FT 3 in. spacing (601-99105) | LFT | 32 | $21.00 | $21.00 | $21.00 | $22.00 | $21.00 | $21.00 |
| 0057 | Guardrail, W-beam, 3 FT 1.5 in. spacing (601-99106) | LFT | 4 | $65.00 | $36.00 | $65.00 | $67.00 | $36.00 | $65.00 |
| 0058 | Barrier delineator (602-06729) | EACH | 30 | $10.00 | $35.00 | $25.00 | $30.00 | $18.00 | $28.74 |
| 0059 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 1,611 | $3.75 | $1.81 | $3.00 | $3.90 | $1.80 | $7.70 |
| 0060 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 122 | $150.00 | $225.00 | $230.00 | $331.00 | $215.00 | $392.00 |
| 0061 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 849 | $175.00 | $225.00 | $285.00 | $200.00 | $220.00 | $249.25 |
| 0062 | HMA for approaches, type C (610-07488) | TON | 5 | $1,271.00 | $330.00 | $650.00 | $668.00 | $200.00 | $650.00 |
| 0063 | Grout for riprap (616-02281) | CYS | 91 | $450.00 | $400.00 | $400.00 | $317.00 | $240.00 | $355.25 |
| 0064 | Riprap, class 1 (616-05688) | TON | 2,236 | $85.00 | $100.00 | $115.00 | $90.00 | $140.00 | $104.00 |
| 0065 | Riprap, class 2 (616-05689) | TON | 1,966 | $90.00 | $100.00 | $105.00 | $91.00 | $140.00 | $93.50 |
| 0066 | Riprap, revetment (616-06405) | TON | 435 | $75.00 | $65.00 | $70.00 | $77.00 | $110.00 | $157.75 |
| 0067 | Riprap, uniform (616-06451) | TON | 80 | $90.00 | $70.00 | $80.00 | $78.00 | $85.00 | $196.50 |
| 0068 | Geotextile for riprap, type 1A (616-12246) | SYS | 2,422 | $5.00 | $2.50 | $5.00 | $6.50 | $4.00 | $3.75 |
| 0069 | Geotextile for riprap, type 2B (616-12249) | SYS | 1,660 | $5.00 | $4.00 | $6.50 | $7.00 | $6.00 | $6.50 |
| 0070 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $4,000.00 | $4,000.00 | $4,000.00 | $4,113.00 | $5,000.00 | $4,000.00 |
| 0071 | Clean and coat steel piling, bridge no. 1 (619-12507) | LS | 1 | $200,000 | $165,000 | $165,000 | $172,590 | $200,000 | $165,000 |
| 0072 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $975.00 | $975.00 | $975.00 | $1,002.00 | $975.00 | $975.00 |
| 0073 | Erosion control blanket (621-02770) | SYS | 65 | $8.30 | $8.30 | $8.30 | $8.50 | $8.30 | $8.30 |
| 0074 | Mulched seeding, type R (621-06559) | SYS | 1,004 | $5.31 | $5.31 | $5.31 | $5.50 | $5.31 | $5.31 |
| 0075 | Mulching material (621-06565) | TON | 1 | $4,268.00 | $4,268.00 | $4,268.00 | $4,388.00 | $4,268.00 | $4,268.00 |
| 0076 | Sodding (621-06574) | SYS | 522 | $9.98 | $9.98 | $15.00 | $10.00 | $9.98 | $38.75 |
| 0077 | Seed mixture, emergent wetland (621-06737) | LBS | 4 | $297.00 | $297.00 | $297.00 | $305.00 | $20.00 | $297.00 |
| 0078 | Seed mixture, floodplain (621-12612) | LBS | 8 | $201.00 | $201.00 | $201.00 | $207.00 | $201.00 | $201.00 |
| 0079 | Sign, 'DO not spray' (621-52448) | EACH | 8 | $84.00 | $84.00 | $84.00 | $86.00 | $84.00 | $84.00 |
| 0080 | Herbicide treatment (624-92647) | ACRE | 1 | $2,192.00 | $2,192.00 | $2,192.00 | $2,254.00 | $2,192.00 | $3,450.00 |
| 0081 | Computer system equipment (628-11976) | EACH | 4 | $500.00 | $900.00 | $750.00 | $884.00 | $1,500.00 | $700.00 |
| 0082 | Field office, type D (628-12683) | MOS | 18 | $3,500.00 | $2,700.00 | $3,100.00 | $4,422.00 | $5,700.00 | $4,700.00 |
| 0083 | Temporary shoring (702-04325) | LS | 1 | $7,500.00 | $40,000 | $25,000 | $34,510 | $35,000 | $40,000 |
| 0084 | Concrete, A, substructure (702-51005) | CYS | 2 | $6,000.00 | $11,000 | $7,500.00 | $10,240 | $7,000.00 | $32,000 |
| 0085 | Field drilled hole in concrete (702-51863) | EACH | 2,464 | $12.00 | $6.00 | $23.00 | $15.00 | $26.00 | $17.80 |
| 0086 | Reinforcing bars, epoxy coated (703-06029) | LBS | 80,626 | $2.00 | $1.75 | $2.15 | $1.60 | $1.63 | $2.00 |
| 0087 | Embedded galvanic anode (703-08247) | EACH | 366 | $34.00 | $34.00 | $90.00 | $35.00 | $47.00 | $34.00 |
| 0088 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 399 | $25.00 | $40.00 | $40.00 | $44.00 | $42.00 | $32.50 |
| 0089 | Concrete, C, superstructure (704-51002) | CYS | 78.20 | $1,200.00 | $2,700.00 | $2,300.00 | $1,798.00 | $2,400.00 | $3,680.00 |
| 0090 | Railing, concrete type FC (706-11600) | CYS | 79.70 | $875.00 | $875.00 | $1,800.00 | $894.00 | $830.00 | $870.00 |
| 0091 | Concrete bridge railing transition, type TFC (706-11620) | EACH | 8 | $2,500.00 | $2,500.00 | $3,500.00 | $2,570.00 | $1,950.00 | $2,500.00 |
| 0092 | Pneumatically placed mortar (708-51813) | SFT | 1,230 | $88.00 | $88.00 | $88.00 | $90.00 | $58.00 | $88.00 |
| 0093 | Welded steel wire reinforcement (708-51814) | SFT | 1,230 | $12.00 | $12.00 | $12.00 | $12.00 | $10.00 | $12.00 |
| 0094 | Fiber wrap concrete casing system (709-04647) | LS | 1 | $32,160 | $48.00 | $32,160 | $33,070 | $32,160 | $10,000 |
| 0095 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $10,000 | $7,657.00 | $7,657.00 | $7,711.00 | $1.00 | $600.00 |
| 0096 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $6,500.00 | $4,983.00 | $6,500.00 | $7,711.00 | $5,000.00 | $600.00 |
| 0097 | Surface seal , bridge no. 3 (709-51821) | LS | 1 | $6,500.00 | $3,807.00 | $10,000 | $7,711.00 | $1.00 | $600.00 |
| 0098 | Patching concrete structures (710-09158) | SFT | 70 | $32.00 | $32.00 | $32.00 | $33.00 | $32.00 | $32.00 |
| 0099 | Stud shear connectors (711-96800) | EACH | 160 | $20.00 | $20.00 | $20.00 | $21.00 | $20.00 | $20.00 |
| 0100 | Temporary causeway (713-04331) | LS | 1 | $12,500 | $250,000 | $350,000 | $514,940 | $530,000 | $209,800 |
| 0101 | Waterproofing membrane type 2 (714-000086) | SFT | 1,664 | $6.00 | $6.00 | $7.50 | $6.80 | $6.23 | $2.90 |
| 0102 | Structure, reinforced concrete, box sections, 8 FT X 4 FT (714-11177) | LFT | 52 | $1,300.00 | $1,500.00 | $2,450.00 | $1,261.00 | $1,565.00 | $1,120.00 |
| 0103 | Structure, reinforced concrete, box sections, 5 FT X 3 FT (714-11198) | LFT | 54 | $700.00 | $940.00 | $1,300.00 | $619.00 | $1,100.00 | $540.00 |
| 0104 | Geotextile for underdrains, type 2A (718-12307) | SYS | 169 | $12.00 | $2.25 | $4.50 | $8.70 | $8.00 | $6.70 |
| 0105 | Geotextile for underdrains, type 2B (718-12308) | SYS | 120 | $10.00 | $4.00 | $6.50 | $14.00 | $7.00 | $18.70 |
| 0106 | Inlet, cap (720-44296) | EACH | 4 | $500.00 | $1,200.00 | $700.00 | $1,596.00 | $400.00 | $580.00 |
| 0107 | Hydrodemolition (722-01066) | SYS | 5,196 | $75.00 | $73.00 | $75.00 | $77.00 | $57.00 | $72.25 |
| 0108 | Bridge deck overlay budget (722-12380) | DOL | 104,743 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0109 | Bridge deck, remove concrete overlay (722-12463) | SYS | 568 | $30.00 | $6.65 | $12.00 | $12.00 | $21.00 | $35.75 |
| 0110 | Bridge deck, remove concrete surface (722-12464) | SYS | 2,351 | $30.00 | $6.50 | $12.00 | $11.00 | $16.50 | $17.30 |
| 0111 | Longitudinal grooving (722-12732) | SYS | 6,238 | $5.00 | $4.00 | $4.00 | $3.80 | $4.90 | $5.51 |
| 0112 | Bridge deck patching, full depth (722-51401) | SFT | 1,937 | $20.00 | $163.43 | $60.00 | $61.00 | $75.00 | $137.50 |
| 0113 | Overlay dam (722-51874) | SFT | 248 | $150.00 | $350.00 | $55.00 | $52.00 | $175.00 | $92.25 |
| 0114 | Bridge expansion joint, type PCF (724-12773) | LFT | 51 | $100.00 | $80.00 | $215.00 | $79.00 | $65.00 | $168.75 |
| 0115 | Bridge expansion joint, type SS, replace (724-12774) | LFT | 66 | $400.00 | $350.00 | $915.00 | $555.00 | $740.00 | $725.00 |
| 0116 | Bridge expansion joint seal, type PCF, replace (724-12779) | LFT | 49 | $100.00 | $130.00 | $220.00 | $184.00 | $100.00 | $340.00 |
| 0117 | Epoxy injection, crack preparation (727-90308) | LFT | 9 | $105.00 | $105.00 | $105.00 | $108.00 | $105.00 | $105.00 |
| 0118 | Epoxy injection, epoxy material (727-90309) | GAL | 1 | $52.00 | $52.00 | $52.00 | $53.00 | $52.00 | $52.00 |
| 0119 | Epoxy injection, furnishing equipment , bridge no. 3 (727-93560) | LS | 1 | $965.00 | $965.00 | $965.00 | $992.00 | $965.00 | $965.00 |
| 0120 | Bridge deck, remove existing polymer overlay system (738-12917) | SYS | 2,277 | $3.00 | $7.40 | $9.29 | $12.00 | $10.00 | $9.70 |
| 0121 | Construction sign, type D (801-03291) | EACH | 1 | $279.00 | $234.00 | $279.00 | $241.00 | $279.00 | $279.00 |
| 0122 | Road closure sign assembly (801-04308) | EACH | 17 | $309.00 | $431.00 | $309.00 | $443.00 | $309.00 | $309.00 |
| 0123 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 38,254 | $1.25 | $1.91 | $1.98 | $2.10 | $1.98 | $1.98 |
| 0124 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 168 | $11.02 | $10.70 | $11.02 | $11.00 | $11.02 | $11.02 |
| 0125 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 6,996 | $1.75 | $3.57 | $2.44 | $3.90 | $2.44 | $2.44 |
| 0126 | Detour route marker assembly (801-06625) | EACH | 139 | $220.00 | $197.00 | $179.00 | $203.00 | $179.00 | $179.00 |
| 0127 | Construction sign, type A (801-06640) | EACH | 132 | $237.00 | $270.00 | $237.00 | $278.00 | $237.00 | $237.00 |
| 0128 | Construction sign, type B (801-06645) | EACH | 34 | $114.00 | $82.00 | $114.00 | $84.00 | $114.00 | $114.00 |
| 0129 | Flashing arrow sign (801-06710) | DAY | 50 | $19.00 | $33.00 | $19.00 | $34.00 | $19.00 | $19.00 |
| 0130 | Maintaining traffic (801-06775) | LS | 1 | $690,069 | $72,855 | $257,500 | $610,000 | $1,452,000 | $394,636 |
| 0131 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 8 | $3,000.00 | $7,100.00 | $5,000.00 | $5,141.00 | $6,100.00 | $8,600.00 |
| 0132 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 1 | $2,500.00 | $9,850.00 | $6,000.00 | $6,169.00 | $9,850.00 | $6,000.00 |
| 0133 | Barricade, type III-A (801-07118) | LFT | 152 | $25.00 | $16.00 | $16.09 | $16.00 | $16.09 | $16.09 |
| 0134 | Barricade, type III-B (801-07119) | LFT | 312 | $25.00 | $19.00 | $16.09 | $20.00 | $16.09 | $16.09 |
| 0135 | Temporary traffic barrier, type 4 (801-08403) | LFT | 710 | $25.00 | $50.00 | $100.00 | $79.00 | $300.00 | $347.25 |
| 0136 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 3,340 | $20.00 | $70.00 | $80.00 | $52.00 | $35.00 | $58.00 |
| 0137 | Portable changeable message sign (801-11642) | EACH | 4 | $6,571.00 | $8,984.00 | $6,571.00 | $9,237.00 | $6,725.38 | $6,571.00 |
| 0138 | Temporary portable rumble strips (801-12031) | DAY | 360 | $10.00 | $100.00 | $20.00 | $103.00 | $25.00 | $142.00 |
| 0139 | Truck mounted attenuator (801-12042) | DAY | 410 | $150.00 | $126.00 | $373.91 | $865.00 | $126.00 | $800.00 |
| 0140 | Portable signal (801-12081) | LS | 1 | $50,000 | $102,250 | $150,000 | $47,290 | $117,968 | $60,060 |
| 0141 | Driveway assistance device (801-12482) | EACH | 5 | $3,646.00 | $3,646.00 | $5,500.00 | $8,121.00 | $3,646.00 | $2,000.00 |
| 0142 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 6 | $918.00 | $352.00 | $918.00 | $362.00 | $153.00 | $3,646.00 |
| 0143 | Reference post (802-04893) | EACH | 1 | $300.00 | $280.00 | $300.00 | $308.00 | $280.00 | $300.00 |
| 0144 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 42 | $26.00 | $40.00 | $26.00 | $27.00 | $40.00 | $26.00 |
| 0145 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 12 | $26.00 | $95.00 | $26.00 | $27.00 | $95.00 | $26.00 |
| 0146 | Sign, ground mounted, reset (802-91122) | EACH | 1 | $500.00 | $863.86 | $500.00 | $514.00 | $50.00 | $500.00 |
| 0147 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 928 | $0.52 | $0.52 | $0.52 | $0.85 | $0.52 | $0.52 |
| 0148 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 928 | $0.39 | $0.39 | $0.39 | $0.85 | $0.39 | $0.39 |
| 0149 | Line, remove (808-06716) | LFT | 11,257 | $0.79 | $0.79 | $0.79 | $0.85 | $0.79 | $0.79 |
| 0150 | Retro-reflectivity testing (808-09381) | LS | 1 | $3,000.00 | $3,000.00 | $3,000.00 | $12,160 | $3,000.00 | $3,000.00 |
| 0151 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 11,115 | $1.37 | $1.37 | $1.37 | $3.60 | $1.37 | $1.37 |
| 0152 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 590 | $1.37 | $1.37 | $1.37 | $3.60 | $1.37 | $1.37 |
| 0153 | Grooving for pavement markings (808-12032) | LFT | 11,465 | $0.81 | $0.81 | $0.81 | $2.20 | $0.81 | $0.81 |
| 0154 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 70 | $0.69 | $0.69 | $0.69 | $7.20 | $0.69 | $0.69 |
| 0155 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 1,737 | $1.77 | $1.77 | $1.77 | $3.90 | $1.77 | $1.77 |
| 0156 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 560 | $0.52 | $0.52 | $0.52 | $1.50 | $0.52 | $0.52 |
| 0157 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 60 | $2.00 | $25.00 | $30.00 | $82.00 | $79.00 | $76.75 |
| 0158 | Snowplowable raised pavement marker (808-75998) | EACH | 44 | $25.00 | $34.84 | $34.84 | $129.00 | $34.84 | $34.84 |
| 0159 | Bridge deck overlay, latex modified (722-51842) | SYS | 5,247 | $145.00 | $124.00 | $121.75 | |||
| 0160 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 5,247 | $95.00 | $140.00 | $115.00 | |||
| 0161 | Debris removal (202-12542) | EACH | 1 | $5,000.00 | $15,000 | $25,000 | $24,460 | $20,000 | $22,300 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.