INDOT contract B-43794-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on August 6, 2025, Allen, Dekalb, Steuben, Fort Wayne. 4 bids received; low bid $2,567,890 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 06 AUG 2025
- Pay items
- 104
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $2,567,890 | Low |
| 2 | Milestone Contractors LP | $2,968,450 | +16% |
| 3 | Ram Construction SRVCS of Michigan Inc | $2,995,701 | +17% |
| 4 | Pioneer Associates Inc | $3,099,511 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Milestone Contractors LP | 3. Ram Construction SRVCS of Michigan Inc | 4. Pioneer Associates Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $20,000 | $55,000 | $10,000 | $25,600 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $130,000 | $148,423 | $297,720 | $324,500 |
| 0011 | Clearing right-of-way (201-52370) | LS | 1 | $15,000 | $45,000 | $10,000 | $79,500 |
| 0012 | Pavement removal (202-02240) | SYS | 368 | $65.00 | $95.00 | $52.00 | $90.00 |
| 0013 | Present structure, remove portions, structure no. 6 (202-51328) | LS | 1 | $110,000 | $80,000 | $48,500 | $59,000 |
| 0014 | Excavation, common (203-02000) | CYS | 125 | $90.00 | $270.00 | $90.00 | $160.00 |
| 0015 | Linear grading (203-08607) | LFT | 255 | $5.00 | $18.50 | $5.00 | $14.00 |
| 0016 | Linear grading , shoulder clipping (203-08607) | LFT | 4,202 | $5.00 | $15.29 | $2.00 | $4.00 |
| 0017 | Stormwater management budget (205-12108) | DOL | 3,100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $10,000 | $4,000.00 | $15,000 | $18,000 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 198 | $70.00 | $120.00 | $94.00 | $168.00 |
| 0020 | Flowable backfill, non- removable (213-09269) | CYS | 30 | $300.00 | $550.00 | $150.00 | $300.00 |
| 0021 | Geotextile for pavement, type 2B (214-12239) | SYS | 396 | $15.00 | $7.00 | $6.00 | $9.00 |
| 0022 | Subbase for PCCP (302-06464) | CYS | 44 | $150.00 | $400.00 | $205.00 | $350.00 |
| 0023 | Compacted aggregate, no. 53 (303-01180) | TON | 181 | $143.00 | $85.00 | $75.00 | $105.00 |
| 0024 | Milling, transition (306-08043) | SYS | 695 | $2.00 | $20.00 | $5.00 | $6.00 |
| 0025 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 72 | $262.00 | $200.00 | $200.00 | $200.00 |
| 0026 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 24 | $353.00 | $300.00 | $300.00 | $300.00 |
| 0027 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 82 | $225.00 | $165.00 | $165.00 | $165.00 |
| 0028 | Joint adhesive, surface (401-10258) | LFT | 642 | $0.50 | $0.46 | $0.46 | $0.50 |
| 0029 | Joint adhesive, intermediate (401-10259) | LFT | 132 | $2.00 | $1.85 | $1.85 | $2.00 |
| 0030 | Asphalt for tack coat (406-05520) | TON | 1 | $550.00 | $850.00 | $850.00 | $850.00 |
| 0031 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 1 | $4,000.00 | $1,750.00 | $1,750.00 | $1,750.00 |
| 0032 | Terminal joint, retrofit polymer modified asphalt (503-12480) | SFT | 484 | $106.60 | $250.00 | $145.00 | $135.00 |
| 0033 | Joints in PCCP, filled (507-08271) | LFT | 412 | $15.00 | $17.00 | $45.00 | $25.00 |
| 0034 | Guardrail transition, type TGB (601-01522) | EACH | 1 | $3,750.00 | $3,750.00 | $3,750.00 | $2,500.00 |
| 0035 | Guardrail, remove (601-02241) | LFT | 509 | $8.00 | $8.00 | $8.00 | $17.00 |
| 0036 | Guardrail, W-beam, cable terminal anchor (601-06855) | EACH | 1 | $1,400.00 | $1,400.00 | $1,400.00 | $1,500.00 |
| 0037 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 25 | $30.00 | $30.00 | $30.00 | $22.00 |
| 0038 | Guardrail transition, MGS without curb (601-12292) | EACH | 3 | $3,850.00 | $3,850.00 | $3,850.00 | $2,900.00 |
| 0039 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,250.00 | $3,250.00 | $3,250.00 | $4,236.20 |
| 0040 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 176 | $315.00 | $300.00 | $360.00 | $440.00 |
| 0041 | Inspection hole (616-93772) | EACH | 6 | $200.00 | $700.00 | $250.00 | $300.00 |
| 0042 | Mobilization and demobilization for seeding (621-01004) | EACH | 2 | $725.00 | $725.00 | $1,500.00 | $725.00 |
| 0043 | Mulched seeding, type R (621-06559) | SYS | 309 | $5.78 | $5.78 | $35.00 | $6.00 |
| 0044 | Field office, type D (628-12683) | MOS | 12 | $4,500.00 | $5,700.00 | $3,000.00 | $6,300.00 |
| 0045 | Reinforcing bars, epoxy coated (703-06029) | LBS | 12,818 | $2.00 | $4.50 | $2.00 | $3.30 |
| 0046 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 100 | $30.00 | $50.00 | $50.00 | $80.00 |
| 0047 | Concrete, C, superstructure (704-51002) | CYS | 5.60 | $5,000.00 | $7,000.00 | $5,850.00 | $7,200.00 |
| 0048 | Railing, concrete type FC , modified (706-11600) | CYS | 0.80 | $8,500.00 | $9,000.00 | $13,215 | $15,000 |
| 0049 | Concrete bridge railing transition, type TFC , modified (706-11620) | EACH | 4 | $7,500.00 | $4,000.00 | $5,250.00 | $6,200.00 |
| 0050 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $5,000.00 | $3,000.00 | $3,712.00 | $5,000.00 |
| 0051 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $5,000.00 | $3,000.00 | $3,712.00 | $5,000.00 |
| 0052 | Surface seal , bridge no. 3 (709-51821) | LS | 1 | $5,000.00 | $3,000.00 | $3,809.00 | $5,500.00 |
| 0053 | Surface seal , bridge no. 6 (709-51821) | LS | 1 | $7,500.00 | $5,200.00 | $6,997.00 | $8,000.00 |
| 0054 | Patching concrete structures (710-09158) | SFT | 456 | $85.00 | $176.00 | $177.80 | $182.00 |
| 0055 | Hydrodemolition (722-01066) | SYS | 826 | $100.00 | $135.00 | $105.00 | $152.00 |
| 0056 | Bridge deck overlay budget (722-12380) | DOL | 15,800 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0057 | Bridge deck, remove concrete surface (722-12464) | SYS | 826 | $15.00 | $25.00 | $14.00 | $16.00 |
| 0058 | Longitudinal grooving (722-12732) | SYS | 998 | $10.00 | $8.52 | $8.00 | $10.00 |
| 0059 | Bridge deck patching, full depth (722-51401) | SFT | 80 | $35.00 | $80.00 | $75.00 | $65.00 |
| 0060 | Bridge deck patching, partial depth (722-51852) | SFT | 523 | $5.00 | $4.00 | $5.00 | $3.50 |
| 0061 | Overlay dam (722-51874) | SFT | 73 | $80.00 | $110.00 | $90.00 | $150.00 |
| 0062 | Bridge expansion joint, type SS, replace (724-12774) | LFT | 73 | $450.00 | $810.00 | $425.00 | $1,000.00 |
| 0063 | Epoxy injection, crack preparation (727-90308) | LFT | 21 | $75.00 | $111.00 | $50.00 | $120.00 |
| 0064 | Epoxy injection, epoxy material (727-90309) | GAL | 2 | $100.00 | $50.00 | $100.00 | $25.00 |
| 0065 | Epoxy injection, furnishing equipment , bridge no. 6 (727-93560) | LS | 1 | $1,500.00 | $600.00 | $2,500.00 | $2,600.00 |
| 0066 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 3,275 | $52.55 | $50.00 | $45.00 | $50.00 |
| 0067 | Polymer overlay, other concrete surface (738-12856) | SYS | 971 | $38.49 | $50.00 | $45.00 | $50.00 |
| 0068 | Temporary pavement marking, 6 in. (801-06206) | LFT | 985 | $2.16 | $0.50 | $2.16 | $0.50 |
| 0069 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 41,822 | $1.50 | $2.15 | $1.97 | $2.15 |
| 0070 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $12.64 | $14.00 | $12.64 | $14.00 |
| 0071 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 506 | $3.89 | $3.25 | $3.89 | $3.25 |
| 0072 | Temporary pavement marking, removable, 24 in. (801-06577) | LFT | 36 | $12.64 | $14.00 | $12.64 | $14.00 |
| 0073 | Construction sign, type A (801-06640) | EACH | 174 | $239.00 | $200.00 | $239.00 | $200.00 |
| 0074 | Construction sign, type B (801-06645) | EACH | 10 | $114.00 | $150.00 | $114.00 | $150.00 |
| 0075 | Flashing arrow sign (801-06710) | DAY | 68 | $15.00 | $25.00 | $15.00 | $25.00 |
| 0076 | Maintaining traffic (801-06775) | LS | 1 | $274,802 | $262,985 | $460,363 | $215,500 |
| 0077 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $6,950.00 | $6,950.00 | $6,950.00 | $2,065.00 |
| 0078 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 6 | $7,950.00 | $7,950.00 | $7,950.00 | $7,250.00 |
| 0079 | Barricade, type III-A (801-07118) | LFT | 40 | $15.81 | $20.00 | $15.81 | $20.00 |
| 0080 | Temporary traffic barrier, type 2 (801-08401) | LFT | 3,310 | $50.00 | $51.00 | $50.00 | $54.00 |
| 0081 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 300 | $50.00 | $90.00 | $50.00 | $68.00 |
| 0082 | Portable changeable message sign (801-11642) | EACH | 24 | $3,500.00 | $6,250.00 | $5,492.00 | $6,250.00 |
| 0083 | Truck mounted attenuator (801-12042) | DAY | 68 | $500.00 | $776.42 | $50.00 | $645.00 |
| 0084 | Portable signal (801-12081) | LS | 1 | $12,000 | $75,000 | $78,500 | $89,500 |
| 0085 | Law enforcement officer (801-12324) | HRS | 792 | $60.00 | $60.00 | $60.00 | $60.00 |
| 0086 | Automated work zone information system (801-12544) | EACH | 74 | $3,000.00 | $1,000.00 | $3,879.00 | $1,000.00 |
| 0087 | Queue truck (801-12652) | DAY | 56 | $2,000.00 | $2,600.00 | $650.00 | $2,055.00 |
| 0088 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 16 | $1,473.00 | $350.00 | $1,473.00 | $350.00 |
| 0089 | Conduit, steel, galvanized, 2 in. (807-06592) | LFT | 10 | $10.00 | $200.00 | $50.00 | $50.00 |
| 0090 | Line, remove (808-06716) | LFT | 16,272 | $0.54 | $0.50 | $0.54 | $0.50 |
| 0091 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 940 | $1.64 | $2.00 | $1.64 | $2.00 |
| 0092 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 940 | $1.64 | $2.00 | $1.64 | $2.00 |
| 0093 | Grooving for pavement markings (808-12032) | LFT | 856 | $2.09 | $1.00 | $2.09 | $1.00 |
| 0094 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 30 | $3.66 | $0.50 | $3.66 | $0.50 |
| 0095 | Line, preformed plastic, broken, black, 6 in. (808-12783) | LFT | 920 | $9.32 | $7.75 | $9.32 | $7.75 |
| 0096 | Line, paint, broken, white, 6 in. (808-75002) | LFT | 920 | $3.94 | $0.50 | $3.94 | $0.50 |
| 0097 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 4,274 | $0.41 | $0.50 | $0.41 | $0.50 |
| 0098 | Line, paint, solid, yellow, 6 in. (808-75047) | LFT | 3,256 | $0.41 | $0.50 | $0.41 | $0.50 |
| 0099 | Line, preformed plastic, solid, white, 6 in. (808-75052) | LFT | 3,640 | $7.44 | $7.75 | $7.44 | $7.75 |
| 0100 | Line, preformed plastic, broken, white, 6 in. (808-75055) | LFT | 920 | $9.32 | $7.75 | $9.32 | $7.75 |
| 0101 | Line, preformed plastic, solid, yellow, 6 in. (808-75057) | LFT | 2,740 | $7.44 | $7.75 | $7.44 | $7.75 |
| 0102 | Prismatic reflector (808-75994) | EACH | 24 | $9.85 | $100.00 | $9.85 | $100.00 |
| 0103 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 4 | $50.00 | $140.00 | $50.00 | $100.00 |
| 0105 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 826 | $150.00 | $150.00 | $195.00 | $260.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.