INDOT contract B-43796-A bid tabulation
BRIDGE DECK OVERLAY AND BRIDGE COATING. Let by Indiana DOT on August 6, 2025, Huntington, Fort Wayne. 3 bids received; low bid $2,271,604 by R L McCoy Inc.
- Owner
- Indiana DOT
- Letting
- 06 AUG 2025
- Pay items
- 109
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | R L McCoy Inc | $2,271,604 | Low |
| 2 | Milestone Contractors LP | $2,418,731 | +6.0% |
| 3 | E & B Paving LLC | $2,850,500 | +25% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R L McCoy Inc | 2. Milestone Contractors LP | 3. E & B Paving LLC |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $10,000 | $28,500 | $50,587 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 2 | $1,000.00 | $2,190.00 | $2,000.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $113,500 | $120,937 | $151,000 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $22,700 | $25,150 | $31,000 |
| 0013 | Debris, remove, structure no. 2 (201-90788) | LS | 1 | $100,000 | $89,000 | $320,000 |
| 0014 | Conduit, remove (202-01845) | LFT | 1,036 | $35.00 | $10.00 | $2.00 |
| 0015 | Pavement removal (202-02240) | SYS | 538 | $50.00 | $49.00 | $75.00 |
| 0016 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $304,000 | $202,377 | $175,000 |
| 0017 | Sidewalk concrete, remove (202-52710) | SYS | 167 | $28.00 | $30.00 | $30.00 |
| 0018 | Bridge railing, remove (202-62420) | LFT | 97 | $55.00 | $85.00 | $25.00 |
| 0019 | Inlet, remove (202-91385) | EACH | 1 | $1,100.00 | $1,410.00 | $1,500.00 |
| 0020 | Pipe, remove (202-96133) | LFT | 65 | $35.00 | $18.00 | $20.00 |
| 0021 | Concrete, remove (202-99080) | CYS | 5 | $2,300.00 | $5,225.00 | $500.00 |
| 0022 | Excavation, common (203-02000) | CYS | 155 | $95.00 | $135.00 | $200.00 |
| 0023 | Linear grading (203-08607) | LFT | 167 | $10.00 | $21.00 | $5.00 |
| 0024 | Stormwater management budget (205-12108) | DOL | 13,504 | $1.00 | $1.00 | $1.00 |
| 0025 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $5,500.00 | $40,000 |
| 0026 | Subgrade treatment, type IC (207-09935) | SYS | 616 | $50.00 | $56.00 | $50.00 |
| 0027 | Aggregate for end bent backfill (211-06467) | CYS | 26 | $180.00 | $210.00 | $120.00 |
| 0028 | Structure backfill, type 2 (211-09265) | CYS | 26 | $45.00 | $219.00 | $60.00 |
| 0029 | Drilled hole for flowable backfill (213-08068) | EACH | 4 | $200.00 | $415.00 | $300.00 |
| 0030 | Flowable backfill, non- removable (213-09269) | CYS | 4 | $760.00 | $1,165.00 | $500.00 |
| 0031 | Geotextile for pavement, type 2B (214-12239) | SYS | 616 | $7.00 | $8.00 | $7.50 |
| 0032 | Subbase for PCCP (302-06464) | CYS | 155 | $130.00 | $210.00 | $120.00 |
| 0033 | Milling, transition (306-08043) | SYS | 218 | $25.00 | $29.16 | $30.00 |
| 0034 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 19 | $435.00 | $435.00 | $750.00 |
| 0035 | Joint adhesive, surface (401-10258) | LFT | 150 | $1.55 | $1.55 | $0.25 |
| 0036 | Asphalt for tack coat (406-05521) | SYS | 222 | $0.60 | $0.25 | $0.25 |
| 0037 | D-1 contraction joint (503-05240) | LFT | 70 | $48.00 | $31.00 | $20.00 |
| 0038 | Jointed reinforced concrete pavement, 12 in. (503-12476) | SYS | 320 | $200.00 | $173.00 | $150.00 |
| 0039 | Terminal joint, type PCCP (503-12478) | LFT | 80 | $425.00 | $430.00 | $200.00 |
| 0040 | Expansion joint with load transfer (503-12479) | LFT | 77 | $40.00 | $57.00 | $20.00 |
| 0041 | Sidewalk, concrete (604-06070) | SYS | 97 | $100.00 | $121.00 | $87.00 |
| 0042 | Curb, remove (605-02278) | LFT | 179 | $12.00 | $27.00 | $10.00 |
| 0043 | Curb, integral concrete (605-06090) | LFT | 160 | $45.00 | $74.00 | $30.00 |
| 0044 | Curb and gutter, concrete (605-06140) | LFT | 15 | $200.00 | $120.00 | $113.00 |
| 0045 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 262 | $215.00 | $209.00 | $200.00 |
| 0046 | Riprap, revetment (616-06405) | TON | 851 | $130.00 | $80.00 | $100.00 |
| 0047 | Geotextile for riprap, type 1A (616-12246) | SYS | 1,303 | $4.00 | $4.50 | $5.00 |
| 0048 | Clean steel bridge, partial, QP-2, bridge no. 1 (619-11050) | LS | 1 | $10,000 | $10.00 | $28,000 |
| 0049 | Clean steel bridge, QP-2, bridge no. 2 (619-11052) | LS | 1 | $240,000 | $240,000 | $215,000 |
| 0050 | Clean steel bridge, QP-2, bridge no. 3 (619-11052) | LS | 1 | $70,000 | $70,000 | $110,000 |
| 0051 | Disposal of cleaning waste, hazardous, bridge no. 1 (619-12459) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0052 | Disposal of cleaning waste, hazardous, bridge no. 2 (619-12459) | LS | 1 | $5,000.00 | $5,000.00 | $1,000.00 |
| 0053 | Disposal of cleaning waste, hazardous, bridge no. 3 (619-12459) | LS | 1 | $5,000.00 | $5,000.00 | $1,000.00 |
| 0054 | Coat steel bridge, bridge no. 2 (619-51859) | LS | 1 | $70,000 | $70,000 | $85,000 |
| 0055 | Coat steel bridge, bridge no. 3 (619-51859) | LS | 1 | $40,000 | $40,000 | $60,000 |
| 0056 | Coat steel bridge, partial, bridge no. 1 (619-51860) | LS | 1 | $8,000.00 | $8,000.00 | $12,000 |
| 0057 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $425.00 | $425.00 | $750.00 |
| 0058 | Erosion control blanket (621-02770) | SYS | 162 | $5.92 | $5.92 | $20.00 |
| 0059 | Mulched seeding, type R (621-06559) | SYS | 162 | $3.02 | $3.02 | $12.00 |
| 0060 | Field office, type D (628-12683) | MOS | 12 | $3,625.00 | $4,800.00 | $4,400.00 |
| 0061 | Field drilled hole in concrete (702-51863) | EACH | 286 | $26.00 | $35.00 | $20.00 |
| 0062 | Concrete, C, substructure (702-92857) | CYS | 44.70 | $1,800.00 | $2,300.00 | $1,050.00 |
| 0063 | Reinforcing bars, epoxy coated (703-06029) | LBS | 35,582 | $1.50 | $2.50 | $1.10 |
| 0064 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 43 | $53.00 | $50.00 | $30.00 |
| 0065 | Concrete, C, superstructure (704-51002) | CYS | 97.30 | $950.00 | $1,500.00 | $650.00 |
| 0066 | Concrete bridge railing transition, type TTX (706-06372) | EACH | 2 | $8,400.00 | $14,350 | $13,640 |
| 0067 | Concrete bridge railing transition, type TTX , modified (706-06372) | EACH | 2 | $8,800.00 | $14,550 | $13,820 |
| 0068 | Railing, concrete type TX (706-09965) | LFT | 34 | $400.00 | $728.00 | $691.00 |
| 0069 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $13,000 | $8,150.00 | $15,000 |
| 0070 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $11,000 | $6,800.00 | $15,000 |
| 0071 | Patching concrete structures (710-09158) | SFT | 37 | $173.00 | $173.00 | $85.00 |
| 0072 | Anchor plate (711-02707) | EACH | 14 | $225.00 | $1,080.00 | $800.00 |
| 0073 | Jacking and supporting superstructure , bridge no. 1 (711-90114) | LS | 1 | $30,000 | $52,765 | $100,000 |
| 0074 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 96 | $85.00 | $110.00 | $50.00 |
| 0075 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 210 | $30.00 | $23.00 | $25.00 |
| 0076 | Inlet, type A8 (720-45015) | EACH | 1 | $4,500.00 | $3,400.00 | $2,500.00 |
| 0077 | Hydrodemolition (722-01066) | SYS | 1,065 | $65.00 | $63.00 | $80.00 |
| 0078 | Bridge deck overlay budget (722-12380) | DOL | 17,400 | $1.00 | $1.00 | $1.00 |
| 0079 | Bridge deck, remove concrete surface (722-12464) | SYS | 1,065 | $6.00 | $6.75 | $7.50 |
| 0080 | Longitudinal grooving (722-12732) | SYS | 1,334 | $5.00 | $3.39 | $6.00 |
| 0081 | Bridge deck patching, full depth (722-51401) | SFT | 192 | $15.00 | $50.00 | $25.00 |
| 0082 | Bridge deck patching, partial depth (722-51852) | SFT | 347 | $4.00 | $19.25 | $5.00 |
| 0083 | Epoxy injection, crack preparation (727-90308) | LFT | 30 | $111.00 | $111.00 | $75.00 |
| 0084 | Epoxy injection, epoxy material (727-90309) | GAL | 7 | $50.00 | $50.00 | $25.00 |
| 0085 | Epoxy injection, furnishing equipment , bridge no. 2 (727-93560) | LS | 1 | $600.00 | $600.00 | $1,500.00 |
| 0086 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 1,927 | $39.00 | $43.26 | $45.25 |
| 0087 | Polymer overlay, other concrete surface (738-12856) | SYS | 206 | $23.00 | $23.00 | $45.25 |
| 0088 | Construction sign, type C (801-03290) | EACH | 4 | $255.00 | $255.00 | $255.00 |
| 0089 | Construction sign, type D (801-03291) | EACH | 5 | $277.00 | $277.00 | $277.00 |
| 0090 | Road closure sign assembly (801-04308) | EACH | 7 | $279.00 | $279.00 | $279.00 |
| 0091 | Temporary panel signs (801-06201) | SFT | 126 | $75.00 | $63.00 | $75.00 |
| 0092 | Temporary panel sign supports (801-06202) | LFT | 60 | $50.00 | $88.00 | $50.00 |
| 0093 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 11,044 | $1.97 | $1.97 | $1.00 |
| 0094 | Detour route marker assembly (801-06625) | EACH | 42 | $168.00 | $168.00 | $168.00 |
| 0095 | Construction sign, type A (801-06640) | EACH | 34 | $224.00 | $224.00 | $224.00 |
| 0096 | Construction sign, type B (801-06645) | EACH | 8 | $112.00 | $112.00 | $112.00 |
| 0097 | Maintaining traffic (801-06775) | LS | 1 | $15,000 | $75,000 | $300,000 |
| 0098 | Barricade, type III-A (801-07118) | LFT | 108 | $15.84 | $15.84 | $15.84 |
| 0099 | Barricade, type III-B (801-07119) | LFT | 132 | $15.84 | $15.84 | $15.84 |
| 0100 | Temporary pedestrian channelizer (801-12862) | LFT | 38 | $34.68 | $41.91 | $50.00 |
| 0101 | Wire, no. 4 copper, in conduit, bridge 1/C (807-01653) | LFT | 192 | $18.00 | $5.50 | $18.00 |
| 0102 | Light structure, remove and reset (807-02370) | EACH | 2 | $5,000.00 | $1,250.00 | $5,000.00 |
| 0103 | Conduit, steel, galvanized, 2 in. (807-06592) | LFT | 48 | $55.00 | $40.00 | $55.00 |
| 0104 | Cable, pole circuit, THWN, no. 10 copper, stranded 1/C (807-86889) | LFT | 180 | $5.00 | $2.00 | $5.00 |
| 0105 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 1,186 | $1.88 | $1.88 | $1.88 |
| 0106 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 1,262 | $1.88 | $1.88 | $1.88 |
| 0107 | Pavement message marking, multi- component, lane indication arrow (808-10077) | EACH | 1 | $277.00 | $277.00 | $277.00 |
| 0108 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 144 | $4.22 | $4.22 | $4.22 |
| 0110 | Bridge deck overlay, silica fume modified (722-01061) | SYS | 1,074 | $68.00 | $71.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.