INDOT contract B-44406-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on August 5, 2026, Monroe, Seymour. 7 bids received; low bid $1,295,746 by CLR Inc.
- Owner
- Indiana DOT
- Letting
- 05 AUG 2026
- Pay items
- 55
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | CLR Inc | $1,295,746 | Low |
| 2 | E & B Paving LLC | $1,342,000 | +4.0% |
| 3 | Force Construction Co Inc | $1,415,345 | +9.0% |
| 4 | Ragle, Inc. | $1,462,086 | +13% |
| 5 | Milestone Contractors LP | $1,471,338 | +14% |
| 6 | Rieth-Riley Construction Co., Inc. | $1,598,336 | +23% |
| 7 | Beaty Construction Inc | $1,780,400 | +37% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. CLR Inc | 2. E & B Paving LLC | 3. Force Construction Co Inc | 4. Ragle, Inc. | 5. Milestone Contractors LP | 6. Rieth-Riley Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $40,000 | $30,000 | $10,300 | $28,500 | $20,000 | $10,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Mobilization and demobilization (110-01001) | LS | 1 | $64,400 | $65,000 | $70,000 | $73,000 | $72,289 | $79,917 |
| 0008 | Terminal joint, retrofit polymer modified asphalt (503-12480) | SFT | 468 | $139.00 | $91.04 | $94.00 | $91.04 | $100.00 | $141.41 |
| 0009 | Cracks in PCCP, rout and seal (507-07482) | LFT | 300 | $8.00 | $18.00 | $19.00 | $18.00 | $20.00 | $9.00 |
| 0010 | Joints in PCCP, filled (507-08271) | LFT | 75 | $53.00 | $21.67 | $26.00 | $12.00 | $5.00 | $2.00 |
| 0011 | Joints in PCCP, saw and seal (507-08272) | LFT | 600 | $9.00 | $2.71 | $8.20 | $24.00 | $5.00 | $2.00 |
| 0012 | Barrier delineator (602-06729) | EACH | 56 | $21.00 | $10.00 | $43.00 | $14.00 | $55.00 | $60.54 |
| 0013 | Computer system equipment (628-11976) | EACH | 2 | $100.00 | $400.00 | $824.00 | $750.00 | $1,000.00 | $1,210.77 |
| 0014 | Field office, type D (628-12683) | MOS | 6 | $1,200.00 | $3,500.00 | $4,118.00 | $3,800.00 | $3,000.00 | $3,700.00 |
| 0015 | Surface seal , bridge no. 1 (709-51821) | LS | 1 | $8,000.00 | $10,000 | $7,889.00 | $7,662.38 | $8,000.00 | $7,263.00 |
| 0016 | Surface seal , bridge no. 2 (709-51821) | LS | 1 | $4,500.00 | $10,000 | $1,539.00 | $1,494.91 | $1,500.00 | $1,568.00 |
| 0017 | Surface seal , bridge no. 3 (709-51821) | LS | 1 | $5,500.00 | $10,000 | $1,377.00 | $1,337.08 | $1,400.00 | $1,505.00 |
| 0018 | Surface seal , bridge no. 4 (709-51821) | LS | 1 | $4,000.00 | $10,000 | $1,304.00 | $1,266.59 | $1,300.00 | $1,200.00 |
| 0019 | Surface seal , bridge no. 5 (709-51821) | LS | 1 | $10,000 | $10,000 | $4,713.00 | $4,577.35 | $4,600.00 | $5,763.00 |
| 0020 | Surface seal , bridge no. 6 (709-51821) | LS | 1 | $10,000 | $10,000 | $3,734.00 | $3,627.29 | $3,700.00 | $4,191.00 |
| 0021 | Patching concrete structures (710-09158) | SFT | 25 | $37.00 | $150.00 | $15.00 | $15.00 | $15.00 | $195.00 |
| 0022 | Bridge deck overlay, rigid (722-000134) | SYS | 1,215 | $140.00 | $150.00 | $101.00 | $160.00 | $150.00 | $148.42 |
| 0023 | Bridge deck, remove concrete overlay and surface (722-000183) | SYS | 1,215 | $17.00 | $20.00 | $15.00 | $17.50 | $21.00 | $18.78 |
| 0024 | Hydrodemolition (722-01066) | SYS | 1,215 | $155.00 | $100.00 | $84.00 | $105.00 | $165.00 | $105.78 |
| 0025 | Bridge deck overlay budget (722-12380) | DOL | 30,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0026 | Longitudinal grooving (722-12732) | SYS | 1,215 | $9.00 | $8.00 | $5.10 | $5.50 | $4.00 | $5.42 |
| 0027 | Bridge deck patching, full depth (722-51401) | SFT | 61 | $160.00 | $200.00 | $125.00 | $85.00 | $500.00 | $301.57 |
| 0028 | Bridge deck patching, partial depth (722-51852) | SFT | 323 | $1.50 | $2.50 | $2.60 | $2.50 | $2.50 | $4.00 |
| 0029 | Overlay dam (722-51874) | SFT | 125 | $20.00 | $75.00 | $47.00 | $55.00 | $75.00 | $127.78 |
| 0030 | Bridge expansion joint, type PCF, replace (724-12776) | LFT | 133 | $170.00 | $60.00 | $98.00 | $140.00 | $130.00 | $98.10 |
| 0031 | Warranted polymer overlay, bridge deck (738-12855) | SYS | 4,176 | $48.00 | $53.34 | $55.00 | $53.34 | $55.00 | $48.10 |
| 0032 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 15,000 | $0.94 | $0.50 | $1.60 | $1.52 | $1.36 | $1.36 |
| 0033 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 47,800 | $1.25 | $1.00 | $2.00 | $2.04 | $1.75 | $1.75 |
| 0034 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 48 | $11.00 | $12.00 | $11.00 | $11.89 | $10.91 | $10.91 |
| 0035 | Detour route marker assembly (801-06625) | EACH | 66 | $85.00 | $75.00 | $139.00 | $158.00 | $135.00 | $135.00 |
| 0036 | Construction sign, type A (801-06640) | EACH | 131 | $175.00 | $150.00 | $158.00 | $202.00 | $153.00 | $153.00 |
| 0037 | Construction sign, type B (801-06645) | EACH | 24 | $50.00 | $110.00 | $68.00 | $101.00 | $66.00 | $66.00 |
| 0038 | Flashing arrow sign (801-06710) | DAY | 90 | $25.00 | $15.00 | $12.00 | $16.00 | $12.00 | $12.00 |
| 0039 | Maintaining traffic (801-06775) | LS | 1 | $105,894 | $210,126 | $324,894 | $145,000 | $200,000 | $271,224 |
| 0040 | Energy absorbing terminal, CZ, TL-2 (801-07023) | EACH | 2 | $8,500.00 | $6,250.00 | $6,435.00 | $6,250.00 | $6,250.00 | $7,850.00 |
| 0041 | Barricade, type III-A (801-07118) | LFT | 258 | $10.00 | $15.00 | $10.00 | $15.04 | $10.00 | $10.00 |
| 0042 | Barricade, type III-B (801-07119) | LFT | 48 | $10.00 | $15.00 | $12.00 | $15.04 | $12.00 | $12.00 |
| 0043 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 800 | $43.00 | $20.00 | $53.00 | $75.00 | $29.00 | $57.69 |
| 0044 | Portable changeable message sign (801-11642) | EACH | 19 | $2,000.00 | $3,800.00 | $1,544.00 | $4,755.00 | $1,575.00 | $1,500.00 |
| 0045 | Portable signal (801-12081) | LS | 1 | $12,000 | $25,000 | $25,470 | $30,000 | $40,000 | $30,000 |
| 0046 | Fixed temporary signal (801-12082) | LS | 1 | $77,500 | $48,000 | $89,060 | $100,000 | $90,000 | $223,800 |
| 0047 | Temporary pedestrian channelizer (801-12862) | LFT | 24 | $40.00 | $25.00 | $69.00 | $57.65 | $35.00 | $16.00 |
| 0048 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 4 | $300.00 | $500.00 | $225.00 | $881.00 | $500.00 | $219.00 |
| 0049 | Line, paint, solid, white, 4 in. (808-06713) | LFT | 1,030 | $0.55 | $2.00 | $0.50 | $0.85 | $0.55 | $0.50 |
| 0050 | Line, paint, solid, yellow, 4 in. (808-06714) | LFT | 1,030 | $0.55 | $2.00 | $0.50 | $0.85 | $0.55 | $0.50 |
| 0051 | Line, multi-component, solid, white, 4 in. (808-10033) | LFT | 2,035 | $1.50 | $1.50 | $1.50 | $0.92 | $1.55 | $1.50 |
| 0052 | Line, multi-component, solid, yellow, 4 in. (808-10034) | LFT | 2,035 | $1.50 | $1.50 | $1.50 | $0.92 | $1.55 | $1.50 |
| 0053 | Transverse marking, multi-component, crosshatch line, yellow, 12 in. (808-10042) | LFT | 150 | $10.00 | $12.00 | $8.20 | $9.62 | $8.05 | $8.00 |
| 0054 | Line, multi-component, solid, yellow, 8 in. (808-10058) | LFT | 420 | $3.00 | $2.00 | $3.10 | $3.04 | $3.05 | $3.00 |
| 0055 | Snowplowable raised pavement marker (808-75998) | EACH | 4 | $205.00 | $100.00 | $103.00 | $122.00 | $105.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 5, 2026. Compiled by Mirage Metrics.