INDOT contract B-45066-A bid tabulation
BRIDGE DECK OVERLAY. Let by Indiana DOT on September 2, 2026, Noble, Fort Wayne. 5 bids received; low bid $1,409,589 by Pioneer Associates Inc.
- Owner
- Indiana DOT
- Letting
- 02 SEP 2026
- Pay items
- 75
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pioneer Associates Inc | $1,409,589 | Low |
| 2 | Milestone Contractors LP | $1,437,984 | +2.0% |
| 3 | E & B Paving LLC | $1,472,000 | +4.0% |
| 4 | R L McCoy Inc | $1,750,565 | +24% |
| 5 | Rieth-Riley Construction Co., Inc. | $1,873,789 | +33% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pioneer Associates Inc | 2. Milestone Contractors LP | 3. E & B Paving LLC | 4. R L McCoy Inc | 5. Rieth-Riley Construction Co., Inc. |
|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $12,500 | $20,000 | $12,000 | $22,000 | $15,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices and markings (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $95,800 | $71,899 | $73,670 | $87,500 | $285,000 |
| 0010 | Pavement removal (202-02240) | SYS | 210 | $65.00 | $75.00 | $90.00 | $150.00 | $57.00 |
| 0011 | Guardrail end treatment, remove (202-93741) | EACH | 4 | $531.00 | $531.00 | $531.00 | $531.00 | $531.00 |
| 0012 | Excavation, common (203-02000) | CYS | 535 | $80.00 | $44.50 | $250.00 | $130.00 | $90.00 |
| 0013 | Linear grading (203-08607) | LFT | 1,007 | $7.00 | $5.00 | $5.00 | $14.00 | $6.69 |
| 0014 | Stormwater management budget (205-12108) | DOL | 3,400 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $2,500.00 | $2,000.00 | $15,000 | $15,000 | $19,521 |
| 0016 | Excavation, foundation, unclassified (206-51230) | CYS | 30 | $125.00 | $850.00 | $0.01 | $450.00 | $1.00 |
| 0017 | Cofferdam (206-51235) | LS | 1 | $28,500 | $84,000 | $50,000 | $200,000 | $350,000 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 1,529 | $46.00 | $70.00 | $55.00 | $55.00 | $65.00 |
| 0019 | Geotextile for pavement, type 2B (214-12239) | SYS | 1,739 | $4.00 | $6.50 | $5.00 | $5.50 | $6.35 |
| 0020 | Subbase for PCCP (302-06464) | CYS | 54 | $190.00 | $350.00 | $150.00 | $210.00 | $165.00 |
| 0021 | Compacted aggregate, no. 53 (303-01180) | TON | 55 | $65.00 | $250.00 | $80.00 | $175.00 | $159.00 |
| 0022 | Milling, transition (306-08043) | SYS | 480 | $9.00 | $14.00 | $10.00 | $15.00 | $10.57 |
| 0023 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 177 | $235.00 | $235.00 | $265.46 | $235.00 | $240.00 |
| 0024 | QC/QA-HMA, 2, 58H, intermediate, 19.0 MM (401-000040) | TON | 210 | $155.00 | $155.00 | $233.25 | $155.00 | $180.00 |
| 0025 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 674 | $125.00 | $125.00 | $138.59 | $125.00 | $150.00 |
| 0026 | Joint adhesive (401-11526) | LFT | 3,736 | $0.35 | $0.35 | $0.57 | $0.35 | $0.50 |
| 0027 | Asphalt for tack coat (406-05520) | TON | 1 | $800.00 | $800.00 | $1.07 | $800.00 | $1,000.00 |
| 0028 | Guardrail, remove (601-02241) | LFT | 900 | $4.00 | $4.00 | $4.00 | $4.00 | $4.00 |
| 0029 | Guardrail terminal system, W-beam, curved, type 7 (601-05071) | EACH | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0030 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 638 | $22.00 | $22.00 | $22.00 | $22.00 | $22.00 |
| 0031 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $950.00 | $950.00 | $950.00 | $950.00 | $950.00 |
| 0032 | Guardrail transition, MGS without curb (601-12292) | EACH | 4 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0033 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $4,500.00 | $2,900.00 | $2,900.00 | $2,900.00 | $2,900.00 |
| 0034 | Milled HMA corrugations, conventional (606-12399) | LFT | 480 | $22.00 | $5.50 | $5.29 | $20.00 | $1.22 |
| 0035 | Reinforced concrete bridge approach, 12 in. (609-06259) | SYS | 210 | $250.00 | $200.00 | $300.00 | $350.00 | $200.00 |
| 0036 | Riprap, revetment (616-06405) | TON | 182 | $165.00 | $129.50 | $100.00 | $240.00 | $320.00 |
| 0037 | Geotextile for riprap, type 2A (616-12248) | SYS | 234 | $6.00 | $9.50 | $5.00 | $10.00 | $10.00 |
| 0038 | Disposal of cleaning waste, non-hazardous, bridge no. 1 (619-12460) | LS | 1 | $300.00 | $1,000.00 | $2,000.00 | $300.00 | $1,000.00 |
| 0039 | Clean and coat steel piling, bridge no. 1 (619-12507) | LS | 1 | $64,000 | $47,000 | $55,000 | $47,000 | $47,000 |
| 0041 | Field office, type C (628-09403) | MOS | 6 | $4,600.00 | $5,425.00 | $3,450.00 | $3,500.00 | $4,765.00 |
| 0042 | Reinforcing bars, epoxy coated (703-06029) | LBS | 10,898 | $2.00 | $3.20 | $2.00 | $2.20 | $1.72 |
| 0043 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 84 | $60.00 | $63.50 | $15.00 | $70.00 | $72.00 |
| 0044 | Deck drain , plug drains (704-51106) | EACH | 32 | $500.00 | $165.00 | $1,000.00 | $1,250.00 | $350.00 |
| 0045 | Surface seal (709-51821) | LS | 1 | $3,000.00 | $2,500.00 | $5,500.00 | $8,000.00 | $3,000.00 |
| 0046 | Patching concrete structures (710-09158) | SFT | 950 | $165.00 | $238.13 | $238.13 | $210.00 | $165.00 |
| 0047 | Pipe, roadway drain casting extension (715-10238) | EACH | 7 | $700.00 | $455.00 | $300.00 | $800.00 | $371.00 |
| 0048 | Bridge deck overlay, rigid (722-000134) | SYS | 587 | $225.00 | $130.00 | $185.00 | $160.00 | $132.00 |
| 0049 | Hydrodemolition (722-01066) | SYS | 587 | $200.00 | $135.00 | $140.00 | $160.00 | $110.00 |
| 0050 | Bridge deck overlay budget (722-12380) | DOL | 10,700 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0051 | Longitudinal grooving (722-12732) | SYS | 797 | $15.00 | $7.50 | $7.50 | $16.00 | $6.50 |
| 0052 | Bridge deck patching, full depth (722-51401) | SFT | 264 | $45.00 | $45.00 | $0.01 | $20.00 | $1.00 |
| 0053 | Overlay dam (722-51874) | SFT | 92 | $55.00 | $61.25 | $90.00 | $85.00 | $135.00 |
| 0054 | Epoxy injection, crack preparation (727-90308) | LFT | 250 | $66.00 | $111.36 | $111.36 | $75.00 | $90.00 |
| 0055 | Epoxy injection, furnishing equipment (727-93560) | LS | 1 | $750.00 | $100.00 | $100.00 | $2,500.00 | $3,700.00 |
| 0056 | Construction sign, type C (801-03290) | EACH | 4 | $226.00 | $226.00 | $226.00 | $226.00 | $226.00 |
| 0057 | Construction sign, type D (801-03291) | EACH | 6 | $245.00 | $245.00 | $245.00 | $245.00 | $245.00 |
| 0058 | Road closure sign assembly (801-04308) | EACH | 4 | $241.00 | $241.00 | $241.00 | $241.00 | $241.00 |
| 0059 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 7,906 | $2.00 | $2.01 | $2.01 | $2.01 | $2.01 |
| 0060 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $12.00 | $11.06 | $11.06 | $11.06 | $11.06 |
| 0061 | Detour route marker assembly (801-06625) | EACH | 8 | $152.00 | $152.00 | $152.00 | $152.00 | $152.00 |
| 0062 | Construction sign, type A (801-06640) | EACH | 27 | $196.00 | $196.00 | $196.00 | $196.00 | $196.00 |
| 0063 | Construction sign, type B (801-06645) | EACH | 10 | $101.00 | $101.00 | $101.00 | $101.00 | $101.00 |
| 0064 | Maintaining traffic (801-06775) | LS | 1 | $52,500 | $64,379 | $31,000 | $100,000 | $70,444 |
| 0065 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 2 | $8,000.00 | $4,602.00 | $2,000.00 | $4,602.00 | $8,100.00 |
| 0066 | Barricade, type III-A (801-07118) | LFT | 108 | $15.00 | $15.04 | $15.04 | $15.04 | $15.04 |
| 0068 | Portable signal (801-12081) | LS | 1 | $22,500 | $19,156 | $10,000 | $22,088 | $23,200 |
| 0069 | Driveway assistance device (801-12482) | EACH | 2 | $5,500.00 | $3,444.00 | $1,000.00 | $2,944.00 | $3,444.00 |
| 0070 | Temporary buzz strips (801-97643) | LFT | 864 | $13.00 | $12.80 | $12.80 | $12.80 | $12.80 |
| 0071 | Sign, ground mounted, reset (802-91122) | EACH | 1 | $180.00 | $177.00 | $177.00 | $177.00 | $177.00 |
| 0072 | Line, remove (808-06716) | LFT | 880 | $1.00 | $0.92 | $0.92 | $0.92 | $0.92 |
| 0073 | Line, paint, broken, yellow, 6 in. (808-12764) | LFT | 380 | $3.00 | $2.77 | $2.77 | $2.77 | $2.77 |
| 0074 | Line, paint, solid, white, 6 in. (808-75007) | LFT | 1,166 | $0.50 | $0.39 | $0.39 | $0.39 | $0.39 |
| 0075 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 2 | $100.00 | $44.00 | $50.00 | $120.00 | $81.00 |
| 0076 | Bridge deck, remove concrete surface (722-12464) | SYS | 587 | $32.00 | $17.00 | $25.00 | $35.00 | $26.00 |
| 0077 | Temporary traffic barrier, type 2 (801-08401) | LFT | 520 | $60.00 | $51.00 | $30.00 | $80.00 | $45.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of September 2, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.