INDOT contract R-41176-A bid tabulation
ROAD RECONSTRUCTION. Let by Indiana DOT on April 8, 2026, St. Joseph, LaPorte. 4 bids received; low bid $4,873,100 by E & B Paving LLC.
- Owner
- Indiana DOT
- Letting
- 08 APR 2026
- Pay items
- 113
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | E & B Paving LLC | $4,873,100 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $5,376,248 | +10% |
| 3 | Milestone Contractors LP | $5,496,000 | +13% |
| 4 | HRP Construction Inc | $7,988,000 | +64% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E & B Paving LLC | 2. Rieth-Riley Construction Co., Inc. | 3. Milestone Contractors LP | 4. HRP Construction Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $120,000 | $57,715 | $92,379 | $205,000 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Mobilization and demobilization (110-01001) | LS | 1 | $240,000 | $136,689 | $250,000 | $842,290 |
| 0011 | Tree, 18 in., remove (201-02255) | EACH | 3 | $1.00 | $100.00 | $1.00 | $300.00 |
| 0012 | Tree, 30 in., remove (201-02260) | EACH | 15 | $1.00 | $100.00 | $1.00 | $600.00 |
| 0013 | Tree, 48 in., remove (201-02265) | EACH | 12 | $1.00 | $100.00 | $1.00 | $800.00 |
| 0014 | Tree, 60 in., remove (201-02270) | EACH | 7 | $1.00 | $100.00 | $1.00 | $1,200.00 |
| 0015 | Clearing right-of-way (201-52370) | LS | 1 | $96,000 | $55,592 | $110,000 | $422,000 |
| 0016 | Pipe, remove (202-96133) | LFT | 249 | $30.00 | $32.13 | $15.00 | $15.00 |
| 0017 | Fence, farm field, remove (202-99187) | LFT | 32 | $65.00 | $65.00 | $15.00 | $20.00 |
| 0018 | Excavation, common (203-02000) | CYS | 32,840 | $19.46 | $25.58 | $27.00 | $17.00 |
| 0019 | Stormwater management budget (205-12108) | DOL | 44,332 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0020 | Stormwater management implementation (205-12616) | LS | 1 | $20,266 | $57,439 | $25,000 | $60,000 |
| 0021 | SWQCP preparation (205-12618) | LS | 1 | $4,200.00 | $3,000.00 | $10,000 | $5,000.00 |
| 0022 | Subgrade treatment, type II (207-08264) | SYS | 1,179 | $38.14 | $32.12 | $33.00 | $40.00 |
| 0023 | Subgrade treatment, type ibc (207-12635) | SYS | 24,098 | $11.04 | $11.60 | $11.00 | $17.00 |
| 0024 | Structure backfill, type 2 (211-09265) | CYS | 1,054 | $152.82 | $92.19 | $150.00 | $275.00 |
| 0025 | Geogrid, type IB (214-11796) | SYS | 13,415 | $1.30 | $4.59 | $1.50 | $4.00 |
| 0026 | Compacted aggregate, no. 53 (301-12234) | CYS | 11,644 | $60.56 | $87.46 | $80.00 | $100.00 |
| 0027 | Dense graded subbase (302-07455) | CYS | 34 | $134.68 | $159.29 | $150.00 | $300.00 |
| 0028 | Compacted aggregate, no. 53 (303-01180) | TON | 2,589 | $51.75 | $52.00 | $57.00 | $110.00 |
| 0029 | Widening with HMA, type B (304-07493) | TON | 12 | $924.00 | $495.63 | $290.00 | $496.00 |
| 0030 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 2,247 | $6.08 | $5.41 | $3.00 | $6.00 |
| 0031 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 1,973 | $95.00 | $96.93 | $102.00 | $97.00 |
| 0032 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 4,084 | $85.00 | $88.12 | $92.00 | $88.00 |
| 0033 | QC/QA-HMA, 4, 58E, base, OG, 19.0 MM (401-000069) | TON | 2,425 | $75.00 | $91.38 | $96.00 | $92.00 |
| 0034 | Joint adhesive (401-11526) | LFT | 14,194 | $0.31 | $0.59 | $0.25 | $1.00 |
| 0035 | Inertial profiler, HMA (401-12169) | LS | 1 | $7,000.00 | $994.20 | $3,500.00 | $15,000 |
| 0036 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 15,849 | $0.30 | $2.65 | $2.65 | $2.95 |
| 0037 | Asphalt for tack coat (406-05520) | TON | 9 | $1.00 | $1,342.80 | $750.00 | $1,343.00 |
| 0038 | Fence, farm field, tension wire, 47 in. (603-05727) | LFT | 690 | $18.50 | $18.50 | $18.50 | $30.00 |
| 0039 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 3,621 | $2.69 | $1.05 | $1.53 | $5.00 |
| 0040 | HMA for approaches, type B (610-07487) | TON | 226 | $200.00 | $177.75 | $200.00 | $178.00 |
| 0041 | PCCP for approaches, 6 in. (610-08446) | SYS | 199 | $135.16 | $91.36 | $95.00 | $92.00 |
| 0042 | Mailbox assembly, single (611-06497) | EACH | 12 | $450.00 | $450.00 | $450.00 | $350.00 |
| 0043 | Right-of-way marker (615-06490) | EACH | 29 | $250.00 | $250.00 | $250.00 | $250.00 |
| 0044 | Monument, type B (615-06505) | EACH | 7 | $1,150.00 | $7,228.57 | $1,150.00 | $1,325.00 |
| 0045 | Riprap, revetment (616-06405) | TON | 9 | $350.08 | $1,070.92 | $300.00 | $200.00 |
| 0046 | Geotextile for riprap, type 2B (616-12249) | SYS | 19 | $100.20 | $58.76 | $65.00 | $63.00 |
| 0047 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $500.00 | $1,500.00 | $500.00 | $675.00 |
| 0048 | Seed mixture, type R (621-06553) | LBS | 1,403 | $7.35 | $7.35 | $7.35 | $7.00 |
| 0049 | Mulching material (621-06565) | TON | 15 | $695.00 | $695.00 | $695.00 | $600.00 |
| 0050 | Sodding (621-06574) | SYS | 936 | $13.09 | $13.09 | $11.25 | $9.00 |
| 0051 | Computer system equipment (628-11976) | EACH | 2 | $3,293.67 | $5,371.74 | $600.00 | $3,000.00 |
| 0052 | Computer system (628-11977) | EACH | 2 | $627.37 | $2,685.87 | $2,500.00 | $4,000.00 |
| 0053 | Field office, type D (628-12683) | MOS | 9 | $5,471.36 | $5,288.17 | $6,090.99 | $6,500.00 |
| 0054 | Topsoil processing and distribution (629-000149) | SYS | 24,051 | $1.75 | $6.40 | $7.00 | $18.00 |
| 0055 | Topsoil amendment budget (629-000150) | DOL | 48,101 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0056 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 7,574 | $8.05 | $6.96 | $13.00 | $17.00 |
| 0057 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 412 | $59.69 | $21.63 | $47.00 | $54.00 |
| 0058 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 141 | $93.44 | $81.19 | $78.00 | $140.00 |
| 0059 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 628 | $92.77 | $86.77 | $88.00 | $150.00 |
| 0060 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 853 | $135.06 | $120.82 | $136.00 | $265.00 |
| 0061 | Pipe, type 2, circular, diameter 30 in. (715-05156) | LFT | 2,200 | $132.70 | $205.43 | $148.00 | $305.00 |
| 0062 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 86 | $95.30 | $117.18 | $96.00 | $72.00 |
| 0063 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 779 | $96.80 | $97.23 | $88.06 | $115.00 |
| 0064 | Pipe, type 3, circular, diameter 18 in. (715-05171) | LFT | 217 | $99.93 | $94.37 | $75.00 | $120.00 |
| 0065 | Video inspection for pipe (715-09064) | LFT | 4,904 | $1.60 | $1.60 | $1.60 | $3.50 |
| 0066 | Pipe end section, diameter 12 in. (715-46000) | EACH | 2 | $1,503.73 | $1,110.25 | $1,500.00 | $1,000.00 |
| 0067 | Pipe end section, diameter 15 in. (715-46005) | EACH | 29 | $1,551.76 | $1,169.54 | $1,725.00 | $1,400.00 |
| 0068 | Pipe end section, diameter 18 in. (715-46010) | EACH | 2 | $2,251.84 | $1,110.25 | $1,850.00 | $1,500.00 |
| 0069 | Pipe end section, diameter 30 in. (715-46030) | EACH | 1 | $3,435.58 | $1,951.91 | $3,600.00 | $3,000.00 |
| 0071 | Video inspection for underdrain (718-06532) | LFT | 3,000 | $1.10 | $1.10 | $1.10 | $3.00 |
| 0072 | Geotextile for underdrains, type 1A (718-12305) | SYS | 5,190 | $1.95 | $0.78 | $4.00 | $4.50 |
| 0073 | Aggregate for underdrains (718-52610) | CYS | 657 | $94.83 | $82.99 | $104.00 | $155.00 |
| 0074 | Inlet, type E7 (720-45030) | EACH | 2 | $5,691.66 | $3,950.06 | $4,500.00 | $5,500.00 |
| 0075 | Inlet, type F7 (720-45035) | EACH | 1 | $5,689.41 | $5,174.81 | $4,500.00 | $5,500.00 |
| 0076 | Pipe catch basin, 24 in. (720-45275) | EACH | 4 | $4,981.59 | $4,761.18 | $4,500.00 | $5,000.00 |
| 0077 | Manhole, type D4 (720-45415) | EACH | 6 | $12,001 | $9,596.85 | $12,500 | $15,000 |
| 0078 | Manhole, type C2 (720-90984) | EACH | 7 | $7,540.46 | $7,542.35 | $8,500.00 | $12,500 |
| 0079 | Manhole, type D2 (720-92025) | EACH | 1 | $12,480 | $11,566 | $17,500 | $15,500 |
| 0080 | Road closure sign assembly (801-04308) | EACH | 9 | $500.00 | $261.00 | $325.00 | $325.00 |
| 0081 | Detour route marker assembly (801-06625) | EACH | 16 | $251.00 | $169.00 | $194.00 | $194.00 |
| 0082 | Construction sign, type A (801-06640) | EACH | 11 | $408.00 | $223.00 | $309.00 | $309.00 |
| 0083 | Construction sign, type B (801-06645) | EACH | 3 | $129.00 | $116.00 | $194.00 | $194.00 |
| 0084 | Maintaining traffic (801-06775) | LS | 1 | $159,569 | $17,033 | $0.01 | $90,000 |
| 0085 | Barricade, type III-A (801-07118) | LFT | 96 | $24.00 | $16.69 | $28.00 | $28.00 |
| 0086 | Barricade, type III-B (801-07119) | LFT | 60 | $28.00 | $16.69 | $28.00 | $28.00 |
| 0087 | Sign, sheet, remove (802-04089) | EACH | 7 | $83.26 | $83.26 | $40.00 | $40.00 |
| 0088 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 74 | $29.40 | $29.40 | $13.00 | $13.00 |
| 0089 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 24 | $38.04 | $38.04 | $25.00 | $25.00 |
| 0090 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 23 | $38.90 | $38.90 | $30.00 | $30.00 |
| 0091 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 190 | $32.67 | $32.67 | $15.00 | $15.00 |
| 0092 | Handhole, lighting (807-02191) | EACH | 3 | $2,638.25 | $2,638.25 | $2,085.00 | $2,085.00 |
| 0093 | Lighting foundation, concrete, with grounding, 24 in. X 24 in. X 96 in. (807-03758) | EACH | 2 | $1,985.50 | $1,985.50 | $4,400.00 | $4,400.00 |
| 0094 | Wire, no. 4 copper, in plastic duct, in trench, 4 1/C (807-07580) | LFT | 90 | $30.29 | $30.29 | $16.00 | $16.00 |
| 0095 | Luminaire, high lumen roadway (807-12199) | EACH | 2 | $1,060.59 | $1,060.59 | $760.00 | $760.00 |
| 0096 | Light pole, 40 FT E.M.H., 15 FT mast arm, breakaway base (807-85762) | EACH | 2 | $4,837.66 | $4,837.66 | $4,900.00 | $4,900.00 |
| 0097 | Service point, type II (807-86810) | EACH | 1 | $7,038.43 | $7,038.43 | $7,800.00 | $7,800.00 |
| 0098 | Cable, pole circuit, THWN, no. 10 copper, stranded 1/C (807-86889) | LFT | 380 | $2.58 | $2.58 | $1.60 | $1.60 |
| 0099 | Connector kit, unfused (807-86910) | EACH | 2 | $50.79 | $50.79 | $65.00 | $65.00 |
| 0100 | Connector kit, fused (807-86915) | EACH | 2 | $50.79 | $50.79 | $60.00 | $60.00 |
| 0101 | Multiple compression fitting, waterproofed (807-86925) | EACH | 4 | $47.42 | $47.42 | $89.00 | $89.00 |
| 0102 | Insulation link, non- waterproofed (807-86930) | EACH | 6 | $27.75 | $27.75 | $13.00 | $13.00 |
| 0103 | Insulation link, waterproofed (807-86935) | EACH | 12 | $36.74 | $36.74 | $33.50 | $33.50 |
| 0104 | Sign, underpass, and roadway lighting, location identification (807-86950) | EACH | 2 | $150.96 | $150.96 | $69.00 | $69.00 |
| 0105 | Wire, no. 4 copper, in plastic duct, 4 1/C (807-97237) | LFT | 230 | $10.21 | $10.21 | $16.00 | $16.00 |
| 0106 | Retro-reflectivity testing (808-09381) | LS | 1 | $1,000.00 | $3,000.00 | $1,000.00 | $1,000.00 |
| 0107 | Grooving for pavement markings (808-12032) | LFT | 16,871 | $0.70 | $0.84 | $0.70 | $0.70 |
| 0108 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 8,956 | $2.00 | $0.98 | $2.00 | $2.00 |
| 0109 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 8,146 | $2.00 | $0.98 | $2.00 | $2.00 |
| 0110 | Transverse marking, thermoplastic, crosshatch line, yellow, 8 in. (808-75274) | LFT | 99 | $10.00 | $5.44 | $10.00 | $10.00 |
| 0111 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 78 | $20.00 | $13.78 | $20.00 | $20.00 |
| 0112 | Line, thermoplastic, solid, yellow, 8 in. (808-92027) | LFT | 761 | $2.00 | $3.01 | $2.00 | $2.00 |
| 0113 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 530 | $2.00 | $2.33 | $2.00 | $2.00 |
| 0114 | Outlet protector, type 1 (718-06528) | EACH | 18 | $2,542.00 | $3,237.09 | $2,108.25 | $3,200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of April 8, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way