INDOT contract R-41481-A bid tabulation
AUXILIARY LANES, ACCEL AND DECEL OR TURN LANES. Let by Indiana DOT on January 22, 2025, Johnson, Seymour. 3 bids received; low bid $66,256,195 by Milestone Contractors LP.
- Owner
- Indiana DOT
- Letting
- 22 JAN 2025
- Pay items
- 282
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Milestone Contractors LP | $66,256,195 | Low |
| 2 | Rieth-Riley Construction Co., Inc. | $67,163,393 | +1.0% |
| 3 | E & B Paving LLC | $79,768,555 | +20% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Milestone Contractors LP | 2. Rieth-Riley Construction Co., Inc. | 3. E & B Paving LLC |
|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $950,000 | $375,900 | $3,246,090 |
| 0002 | Construction engineering GPS rover (105-11823) | LS | 1 | $75,000 | $35,001 | $50,000 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, PCCP (109-08441) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0009 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0011 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0012 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 |
| 0013 | Mobilization and demobilization (110-01001) | LS | 1 | $3,388,973 | $2,805,326 | $5,492,793 |
| 0014 | Clearing right-of-way (201-52370) | LS | 1 | $1,050,000 | $467,477 | $760,000 |
| 0015 | Pavement removal (202-02240) | SYS | 68 | $98.50 | $45.80 | $60.00 |
| 0016 | Center curb, concrete, remove (202-02273) | SYS | 797 | $26.75 | $65.47 | $114.98 |
| 0017 | Curb, concrete, remove (202-02278) | LFT | 1,884 | $16.00 | $9.58 | $22.35 |
| 0018 | Curb and gutter, remove (202-02279) | LFT | 10,340 | $16.75 | $10.13 | $29.53 |
| 0019 | Casting, remove (202-02772) | EACH | 8 | $800.00 | $165.72 | $449.89 |
| 0020 | Regulated materials, dispose, type C (202-05545) | CYS | 100 | $175.00 | $175.00 | $175.00 |
| 0021 | Regulated materials, remove, type C (202-05550) | CYS | 100 | $175.00 | $175.00 | $175.00 |
| 0022 | Regulated materials, transport, type C (202-05555) | CYS | 100 | $175.00 | $175.00 | $175.00 |
| 0023 | Testing for wastes, type C (202-07603) | EACH | 12 | $1,500.00 | $1,500.00 | $1,500.00 |
| 0024 | Present structure, remove portions, structure no. 1 (202-51328) | LS | 1 | $750,000 | $158,710 | $422,000 |
| 0025 | Present structure, remove, structure no. 2 (202-51330) | LS | 1 | $450,000 | $99,619 | $72,000 |
| 0026 | Sidewalk concrete, remove (202-52710) | SYS | 2,692 | $19.50 | $17.57 | $21.92 |
| 0027 | Handhole, remove (202-86946) | EACH | 4 | $960.00 | $938.00 | $938.00 |
| 0028 | Inlet, remove (202-91385) | EACH | 62 | $950.00 | $807.81 | $742.03 |
| 0030 | Manhole, remove (202-93047) | EACH | 7 | $1,900.00 | $1,132.07 | $1,061.09 |
| 0031 | Pipe, remove (202-96133) | LFT | 11,393 | $27.25 | $39.31 | $22.98 |
| 0032 | Excavation, common (203-02000) | CYS | 42,825 | $33.00 | $59.11 | $98.00 |
| 0033 | Borrow (203-02070) | CYS | 139,800 | $1.00 | $37.75 | $25.00 |
| 0034 | Pump around (205-11626) | EACH | 3 | $40,000 | $28,423 | $21,000 |
| 0035 | Stormwater management budget (205-12108) | DOL | 759,295 | $1.00 | $1.00 | $1.00 |
| 0036 | Stormwater management implementation (205-12616) | LS | 1 | $408,600 | $452,590 | $1,903,973 |
| 0037 | SWQCP preparation (205-12618) | LS | 1 | $15,000 | $137,900 | $5,800.00 |
| 0038 | Excavation, foundation, unclassified (206-51230) | CYS | 27 | $119.00 | $94.04 | $170.50 |
| 0039 | Subgrade treatment, type II (207-08264) | SYS | 14,485 | $24.50 | $26.35 | $32.99 |
| 0040 | Subgrade treatment, type III (207-08266) | SYS | 32,001 | $0.01 | $2.82 | $5.85 |
| 0041 | Subgrade treatment, type IC (207-09935) | SYS | 46,809 | $31.50 | $34.49 | $25.00 |
| 0042 | Subgrade treatment, type ibc (207-12635) | SYS | 49,072 | $32.00 | $20.00 | $16.10 |
| 0043 | B borrow (211-02050) | CYS | 2,902 | $35.50 | $66.76 | $65.53 |
| 0044 | Aggregate for end bent backfill (211-06467) | CYS | 10 | $190.00 | $310.63 | $215.00 |
| 0045 | Structure backfill, type 1 (211-09264) | CYS | 27,071 | $66.50 | $66.72 | $83.53 |
| 0046 | Structure backfill, type 2 (211-09265) | CYS | 93 | $109.00 | $86.16 | $92.22 |
| 0047 | Structure backfill, type 5 (211-09268) | CYS | 2,677 | $250.00 | $208.38 | $192.34 |
| 0048 | Geogrid, type IB (214-11796) | SYS | 13,641 | $6.35 | $2.52 | $3.85 |
| 0049 | Geotextile for pavement, type 2B (214-12239) | SYS | 5,219 | $6.90 | $3.25 | $5.93 |
| 0050 | Compacted aggregate, no. 2 (301-12231) | CYS | 34 | $83.50 | $72.42 | $100.00 |
| 0051 | Compacted aggregate, no. 8 (301-12233) | CYS | 2,902 | $88.00 | $81.12 | $100.00 |
| 0052 | Compacted aggregate, no. 53 (301-12234) | CYS | 15,007 | $85.00 | $90.62 | $76.19 |
| 0053 | Subbase for PCCP (302-06464) | CYS | 29 | $392.00 | $309.06 | $308.00 |
| 0054 | Dense graded subbase (302-07455) | CYS | 1,819 | $115.00 | $80.49 | $82.31 |
| 0055 | Widening with HMA, type D (304-07789) | TON | 2,587 | $133.00 | $172.69 | $140.00 |
| 0056 | HMA patching, full depth, type D (304-12627) | TON | 2,379 | $269.00 | $213.31 | $200.00 |
| 0057 | HMA patching, partial depth, type D (304-12628) | TON | 404 | $155.00 | $267.06 | $356.00 |
| 0059 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 1,304 | $212.00 | $199.24 | $210.00 |
| 0060 | QC/QA-HMA, 4, 58E, surface, 9.5 MM (401-000009) | TON | 19,565 | $157.00 | $134.78 | $210.00 |
| 0061 | QC/QA-HMA, 4, 58E, intermediate, 19.0 MM (401-000045) | TON | 40,272 | $119.00 | $122.00 | $105.00 |
| 0062 | QC/QA-HMA, 4, 58S, base, 19.0 MM (401-000056) | TON | 15,176 | $118.00 | $136.94 | $115.00 |
| 0064 | Joint adhesive, intermediate (401-10259) | LFT | 128,280 | $0.85 | $0.66 | $0.50 |
| 0066 | HMA spray paver emulsion (401-12664) | TON | 381 | $1,100.00 | $701.49 | $1,000.00 |
| 0067 | HMA for temporary pavement, type D (402-10087) | TON | 5,310 | $130.00 | $141.64 | $115.00 |
| 0068 | Asphalt for tack coat (406-05520) | TON | 32 | $710.00 | $0.01 | $1.00 |
| 0069 | PCCP, 9 in. (502-06457) | SYS | 1,139 | $113.00 | $125.31 | $90.00 |
| 0070 | D-1 contraction joint (503-05240) | LFT | 1,200 | $24.25 | $19.18 | $25.00 |
| 0071 | Fence , safety (603-03829) | LFT | 4,555 | $42.75 | $42.75 | $42.75 |
| 0073 | HMA for sidewalk (604-05528) | TON | 7,041 | $124.00 | $128.09 | $130.00 |
| 0074 | Sidewalk, concrete (604-06070) | SYS | 3,564 | $63.50 | $80.99 | $80.00 |
| 0075 | Pavers , grass (604-07569) | SYS | 190 | $198.00 | $163.24 | $139.63 |
| 0076 | Curb ramp, concrete (604-08086) | SYS | 2,000 | $226.00 | $233.52 | $164.00 |
| 0077 | Detectable warning surfaces (604-12083) | SYS | 422 | $309.00 | $399.92 | $303.00 |
| 0078 | Hand rail, steel (604-92237) | LFT | 161.10 | $422.00 | $422.00 | $422.00 |
| 0079 | Curb, concrete (605-06120) | LFT | 47,470 | $23.50 | $29.79 | $21.00 |
| 0080 | Curb, concrete, type B (605-06121) | LFT | 1,723 | $20.75 | $61.52 | $109.00 |
| 0081 | Curb and gutter, concrete (605-06140) | LFT | 52,012 | $32.75 | $37.51 | $29.00 |
| 0082 | Center curb, concrete, type B (605-06245) | SYS | 366 | $255.00 | $219.24 | $197.00 |
| 0083 | Center curb, concrete, type D (605-06255) | SYS | 2,713 | $155.00 | $159.39 | $125.00 |
| 0084 | Curb and gutter, rolled curb (605-97937) | LFT | 199 | $79.00 | $73.19 | $120.00 |
| 0085 | Reinforced concrete bridge approach, 10 in. (609-06257) | SYS | 109 | $246.00 | $364.18 | $230.50 |
| 0086 | HMA for approaches, type C (610-07488) | TON | 5,650 | $163.00 | $143.76 | $150.00 |
| 0087 | PCCP for approaches, 6 in. (610-08446) | SYS | 845 | $99.00 | $83.07 | $101.00 |
| 0088 | PCCP for approaches, 9 in. (610-09108) | SYS | 10,067 | $101.00 | $112.04 | $80.00 |
| 0089 | Right-of-way marker (615-06490) | EACH | 214 | $200.00 | $200.00 | $200.00 |
| 0090 | Monument, type B (615-06505) | EACH | 5 | $875.00 | $879.00 | $875.00 |
| 0091 | Monument, type C (615-06510) | EACH | 22 | $400.00 | $400.00 | $400.00 |
| 0092 | Monument, type D (615-06515) | EACH | 1 | $175.00 | $175.00 | $175.00 |
| 0093 | Monument, section corner (615-06527) | EACH | 1 | $550.00 | $550.00 | $550.00 |
| 0094 | Riprap, class 2 (616-05689) | TON | 916 | $91.00 | $117.35 | $155.00 |
| 0095 | Riprap, revetment (616-06405) | TON | 1,619 | $95.00 | $116.09 | $82.73 |
| 0096 | Geotextile for riprap, type 1A (616-12246) | SYS | 4,305 | $9.85 | $3.53 | $10.00 |
| 0097 | Mobilization and demobilization for seeding (621-01004) | EACH | 5 | $500.00 | $500.00 | $500.00 |
| 0098 | Fertilizer , for permanent seeding (621-06545) | TON | 19 | $600.00 | $600.00 | $600.00 |
| 0099 | Seed mixture, type U (621-06554) | LBS | 9,315 | $4.15 | $4.15 | $4.15 |
| 0100 | Mulching material (621-06565) | TON | 95 | $510.00 | $510.00 | $510.00 |
| 0101 | Water (621-06567) | KGAL | 9 | $1.00 | $1.00 | $1.00 |
| 0102 | Sodding, nursery (621-06575) | SYS | 2,076 | $10.09 | $4.00 | $4.00 |
| 0103 | Seed mixture, floodplain (621-12612) | LBS | 294 | $37.50 | $37.50 | $37.50 |
| 0104 | Sign, "DO not spray" (621-52448) | EACH | 47 | $96.00 | $96.00 | $96.00 |
| 0105 | Plant, deciduous shrub, 18 in. to 24 in. (622-05639) | EACH | 46 | $55.00 | $55.00 | $55.00 |
| 0106 | Plant, deciduous tree, single stem, 1.25 in. or under (622-05648) | EACH | 47 | $315.00 | $315.00 | $315.00 |
| 0107 | Plant, deciduous tree, single stem, 1.25 in. to 2 in. (622-05649) | EACH | 182 | $315.00 | $315.00 | $315.00 |
| 0108 | Computer system equipment (628-11976) | EACH | 5 | $1,300.00 | $1,131.44 | $1.00 |
| 0109 | Field office, type E (628-12684) | MOS | 51 | $9,300.00 | $3,846.90 | $6,950.00 |
| 0110 | Grates, basins, and fittings, cast iron (702-12076) | EACH | 7 | $6,200.00 | $3,381.43 | $2,500.00 |
| 0111 | Concrete, B, footings (702-51015) | CYS | 122 | $1,800.00 | $241.19 | $650.00 |
| 0112 | Field drilled hole in concrete (702-51863) | EACH | 665 | $11.50 | $29.15 | $19.00 |
| 0113 | Reinforcing bars, epoxy coated (703-06029) | LBS | 49,098 | $1.80 | $1.54 | $1.75 |
| 0114 | Threaded tie bar assembly, epoxy coated (703-97936) | EACH | 18 | $59.00 | $108.14 | $57.00 |
| 0115 | Concrete, C, superstructure (704-51002) | CYS | 189 | $2,900.00 | $1,573.42 | $1,450.00 |
| 0116 | Concrete bridge railing transition, type TPS-1 (706-06353) | EACH | 4 | $10,200 | $5,353.28 | $7,020.00 |
| 0117 | Railing, concrete type PS-1 (706-09961) | LFT | 288.10 | $175.00 | $169.38 | $156.00 |
| 0118 | Railing, steel type PS-1 (706-11418) | LFT | 305.20 | $118.00 | $118.00 | $118.00 |
| 0119 | Surface seal (709-51821) | LS | 1 | $500.00 | $1.00 | $11,814 |
| 0120 | Masonry column , gateway monument (710-11640) | EACH | 2 | $125,000 | $104,214 | $11,781 |
| 0121 | Structure extension, reinforced concrete, box sections, 3 FT X 2 FT (714-11133) | LFT | 44 | $890.00 | $946.18 | $958.39 |
| 0122 | Structure extension, reinforced concrete, box sections, 4 FT X 3 FT (714-12575) | LFT | 40 | $1,500.00 | $1,328.73 | $1,378.13 |
| 0123 | Pipe, type 2, circular, diameter 36 in. (715-05024) | LFT | 209 | $166.00 | $163.00 | $221.00 |
| 0124 | Pipe, type 1, circular, diameter 15 in. (715-05119) | LFT | 57 | $83.50 | $102.35 | $103.68 |
| 0125 | Pipe, type 1, circular, diameter 18 in. (715-05121) | LFT | 117 | $67.00 | $89.16 | $135.07 |
| 0126 | Pipe, type 1, circular, diameter 24 in. (715-05123) | LFT | 144 | $98.50 | $126.97 | $147.85 |
| 0127 | Pipe, type 2, circular, diameter 8 in. (715-05147) | LFT | 47 | $56.00 | $92.83 | $83.46 |
| 0128 | Pipe, type 2, circular, diameter 10 in. (715-05148) | LFT | 4 | $249.00 | $300.31 | $179.44 |
| 0129 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 12,264 | $55.50 | $77.18 | $93.66 |
| 0130 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 5,442 | $63.00 | $78.97 | $92.81 |
| 0131 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 4,382 | $70.00 | $94.58 | $96.88 |
| 0132 | Pipe, type 2, circular, diameter 21 in. (715-05153) | LFT | 4,895 | $84.50 | $109.19 | $126.05 |
| 0133 | Pipe, type 2, circular, diameter 24 in. (715-05154) | LFT | 4,856 | $95.00 | $113.60 | $119.69 |
| 0134 | Pipe, type 2, circular, diameter 30 in. (715-05156) | LFT | 5,681 | $120.00 | $151.21 | $152.14 |
| 0135 | Pipe, type 2, circular, diameter 33 in. (715-05157) | LFT | 1,005 | $182.00 | $148.04 | $274.26 |
| 0136 | Pipe, type 2, circular, diameter 42 in. (715-05159) | LFT | 217 | $245.00 | $249.52 | $233.28 |
| 0137 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 71 | $67.00 | $56.83 | $92.62 |
| 0138 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 253 | $63.50 | $77.13 | $100.43 |
| 0139 | Pipe, type 3, circular, diameter 24 in. (715-05173) | LFT | 50 | $105.00 | $117.82 | $152.15 |
| 0140 | Pipe, end bent drain, diameter 6 in. (715-05407) | LFT | 50 | $69.50 | $99.29 | $30.00 |
| 0141 | Pipe, type 2, circular, diameter 4 in. (715-08627) | LFT | 22 | $78.00 | $48.99 | $47.81 |
| 0142 | Video inspection for pipe (715-09064) | LFT | 27,868 | $1.25 | $1.25 | $1.33 |
| 0143 | Pipe end section, diameter 12 in. (715-46000) | EACH | 96 | $1,000.00 | $1,196.29 | $1,722.81 |
| 0144 | Pipe end section, diameter 15 in. (715-46005) | EACH | 31 | $1,100.00 | $1,165.26 | $1,823.60 |
| 0145 | Pipe end section, diameter 18 in. (715-46010) | EACH | 7 | $1,100.00 | $1,202.66 | $1,818.65 |
| 0146 | Pipe end section, diameter 21 in. (715-46015) | EACH | 3 | $1,100.00 | $867.49 | $2,285.42 |
| 0147 | Pipe end section, diameter 24 in. (715-46020) | EACH | 6 | $1,700.00 | $1,318.81 | $2,342.11 |
| 0148 | Pipe end section, diameter 30 in. (715-46030) | EACH | 2 | $1,900.00 | $1,831.15 | $3,124.36 |
| 0149 | Pipe end section, diameter 33 in. (715-46035) | EACH | 1 | $2,700.00 | $2,668.40 | $3,926.89 |
| 0150 | Geotextile for underdrains, type 1B (718-12306) | SYS | 41 | $7.65 | $14.85 | $26.33 |
| 0151 | Manhole , D15 (720-03194) | EACH | 16 | $9,500.00 | $10,562 | $17,017 |
| 0152 | Manhole , D5 (720-03194) | EACH | 6 | $9,700.00 | $10,751 | $15,838 |
| 0153 | Manhole, type C15 (720-03757) | EACH | 13 | $4,800.00 | $5,949.80 | $8,934.95 |
| 0154 | Manhole, type C5 (720-08659) | EACH | 2 | $5,900.00 | $5,096.27 | $7,151.70 |
| 0155 | Casting, manhole, adjust to grade , sanitary (720-12798) | EACH | 11 | $1,300.00 | $1,295.40 | $2,594.40 |
| 0156 | Casting, manhole, adjust to grade , storm (720-12798) | EACH | 4 | $1,300.00 | $955.97 | $2,561.91 |
| 0157 | Casting, type 4, furnish and adjust to grade (720-44025) | EACH | 1 | $2,300.00 | $1,318.02 | $3,250.06 |
| 0158 | Inlet, type E7 (720-45030) | EACH | 35 | $3,600.00 | $2,862.08 | $4,170.72 |
| 0159 | Inlet, type F7 (720-45035) | EACH | 46 | $3,700.00 | $3,391.42 | $4,584.48 |
| 0160 | Inlet, type HA5 (720-45042) | EACH | 59 | $4,800.00 | $4,114.44 | $4,847.66 |
| 0161 | Inlet, type P12A (720-45070) | EACH | 1 | $5,500.00 | $4,319.86 | $5,720.70 |
| 0162 | Pipe catch basin, 18 in. (720-45270) | EACH | 2 | $6,100.00 | $4,101.06 | $3,702.43 |
| 0163 | Manhole, type C4 (720-45410) | EACH | 87 | $5,000.00 | $5,208.10 | $7,869.97 |
| 0164 | Manhole, type D4 (720-45415) | EACH | 33 | $7,500.00 | $9,849.10 | $14,652 |
| 0165 | Manhole, type E4 (720-45416) | EACH | 1 | $7,900.00 | $10,468 | $16,343 |
| 0166 | Structure, manhole, reconstructed (720-45605) | LFT | 82 | $1,200.00 | $951.80 | $1,122.80 |
| 0167 | Manhole, type C7 (720-94432) | EACH | 19 | $5,200.00 | $5,180.91 | $6,264.96 |
| 0168 | Inlet, type B15 (720-98174) | EACH | 205 | $4,300.00 | $4,208.95 | $4,985.82 |
| 0169 | Inlet, type C15 (720-98555) | EACH | 125 | $4,400.00 | $4,480.27 | $4,991.33 |
| 0170 | Structure, reinforced concrete, three-sided (723-12868) | LFT | 148 | $11,100 | $12,899 | $6,400.00 |
| 0171 | Construction sign, type C (801-03290) | EACH | 9 | $507.00 | $507.00 | $507.00 |
| 0172 | Construction sign, type D (801-03291) | EACH | 17 | $154.00 | $154.00 | $154.00 |
| 0173 | Road closure sign assembly (801-04308) | EACH | 10 | $308.00 | $308.00 | $308.00 |
| 0174 | Temporary pavement marking, removable, 4 in. (801-06207) | LFT | 225,641 | $1.10 | $1.10 | $1.10 |
| 0175 | Temporary pavement message marking, removable, lane indication arrow (801-06211) | EACH | 123 | $171.00 | $171.00 | $171.00 |
| 0176 | Temporary transverse pavement marking, removable, 6 in. (801-06217) | LFT | 5,808 | $2.68 | $2.68 | $2.68 |
| 0177 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 859 | $6.71 | $6.71 | $6.71 |
| 0178 | Temporary pavement marking, removable, 8 in. (801-06469) | LFT | 10,351 | $2.57 | $2.57 | $2.57 |
| 0179 | Detour route marker assembly (801-06625) | EACH | 28 | $148.00 | $148.00 | $148.00 |
| 0180 | Construction sign, type A (801-06640) | EACH | 62 | $559.00 | $559.00 | $559.00 |
| 0181 | Construction sign, type B (801-06645) | EACH | 102 | $267.00 | $267.00 | $267.00 |
| 0182 | Flashing arrow sign (801-06710) | DAY | 2,160 | $10.00 | $10.00 | $10.00 |
| 0183 | Maintaining traffic (801-06775) | LS | 1 | $4,000,000 | $1,086,477 | $7,010,538 |
| 0184 | Barricade, type III-A (801-07118) | LFT | 1,653 | $34.00 | $34.00 | $34.00 |
| 0185 | Barricade, type III-B (801-07119) | LFT | 288 | $37.00 | $37.00 | $37.00 |
| 0186 | Temporary crossover drainage pipe (801-07606) | LFT | 225 | $235.00 | $95.11 | $131.64 |
| 0187 | Portable changeable message sign (801-11642) | EACH | 2 | $21,515 | $21,515 | $21,515 |
| 0188 | Temporary curb ramp (801-11990) | EACH | 2 | $7,500.00 | $3,672.85 | $7,349.30 |
| 0189 | Temporary pedestrian channelizer (801-12862) | LFT | 211 | $50.00 | $48.10 | $164.33 |
| 0190 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 15 | $826.00 | $826.00 | $826.00 |
| 0191 | Temporary crossover, type B (801-52817) | EACH | 2 | $112,500 | $41,654 | $50,000 |
| 0192 | Signal head relocate (801-94295) | EACH | 4 | $992.00 | $992.00 | $992.00 |
| 0193 | Bollard (802-03896) | EACH | 299 | $3,375.00 | $3,375.00 | $3,375.00 |
| 0194 | Sign, sheet, remove (802-04089) | EACH | 58 | $215.00 | $215.00 | $215.00 |
| 0195 | Sign post, square, type 1, reinforced anchor base (802-05701) | LFT | 7,085 | $33.80 | $33.80 | $33.80 |
| 0196 | Sign post, square, type 2, reinforced anchor base (802-05702) | LFT | 282 | $31.50 | $31.50 | $31.50 |
| 0197 | Sign post, square, type 3, reinforced anchor base (802-05703) | LFT | 234 | $47.80 | $47.80 | $47.80 |
| 0198 | Sign, panel, with legend (802-07057) | SFT | 191 | $51.70 | $51.70 | $51.70 |
| 0199 | Sign, sheet, and supports, remove (802-07059) | EACH | 287 | $83.80 | $83.80 | $83.80 |
| 0200 | Sign, sheet, relocate (802-07060) | EACH | 65 | $629.00 | $629.00 | $629.00 |
| 0201 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 4,139 | $33.70 | $33.70 | $33.70 |
| 0202 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 3,138 | $32.90 | $32.90 | $32.90 |
| 0203 | Sign, sheet, with legend, 0.125 in. thickness (802-09842) | SFT | 946 | $43.90 | $43.90 | $43.90 |
| 0204 | Wide flange sign post support foundation, type A (802-12222) | EACH | 12 | $1,932.00 | $1,932.00 | $1,932.00 |
| 0205 | Structural steel, breakaway (802-76095) | LBS | 1,688 | $13.80 | $13.80 | $13.80 |
| 0206 | Traffic signal equipment, remove (805-01300) | EACH | 11 | $5,928.00 | $5,928.00 | $5,928.00 |
| 0207 | Signal pole foundation, 36 in. X 144 in. (805-01815) | EACH | 95 | $3,863.00 | $3,863.00 | $3,863.00 |
| 0208 | Traffic signal head, realign (805-01828) | EACH | 11 | $992.00 | $992.00 | $992.00 |
| 0209 | Handhole, signal, type 1 (805-01842) | EACH | 6 | $1,788.00 | $1,788.00 | $1,788.00 |
| 0210 | Handhole, signal, adjust to grade (805-01843) | EACH | 17 | $631.00 | $631.00 | $631.00 |
| 0211 | Transportation of salvageable signal equipment (805-02087) | LS | 1 | $5,408.00 | $5,408.00 | $5,408.00 |
| 0212 | Pedestrian signal head, countdown, 18 in. (805-02150) | EACH | 68 | $727.00 | $727.00 | $727.00 |
| 0213 | Controller and cabinet, type P1 (805-02445) | EACH | 20 | $19,756 | $19,756 | $19,756 |
| 0214 | Signal pole foundation, 24 in. X 24 in. X 36 in. (805-02645) | EACH | 57 | $1,425.00 | $1,425.00 | $1,425.00 |
| 0215 | Emergency vehicle confirmation light kit (805-03980) | EACH | 31 | $716.00 | $716.00 | $716.00 |
| 0216 | Emergency vehicle confirmation light kit , relocate (805-03980) | EACH | 18 | $1,091.00 | $1,091.00 | $1,091.00 |
| 0217 | Phase selectors (805-03983) | EACH | 17 | $4,222.00 | $4,222.00 | $4,222.00 |
| 0218 | Phase selectors , relocate (805-03983) | EACH | 9 | $343.00 | $343.00 | $343.00 |
| 0219 | Cellular modem kit (805-08244) | EACH | 27 | $2,160.00 | $2,160.00 | $2,160.00 |
| 0220 | Signal cantilever structure, single arm 30 FT (805-11376) | EACH | 1 | $17,115 | $17,115 | $17,115 |
| 0221 | Signal cantilever structure, single arm 40 FT (805-11378) | EACH | 1 | $24,078 | $24,078 | $24,078 |
| 0222 | Signal cantilever structure, single arm 45 FT (805-11379) | EACH | 1 | $26,576 | $26,576 | $26,576 |
| 0223 | Signal cantilever structure, drilled shaft foundation, type A (805-11383) | EACH | 1 | $4,061.00 | $4,061.00 | $4,061.00 |
| 0224 | Signal cantilever structure, drilled shaft foundation, type B (805-11384) | EACH | 2 | $7,211.00 | $7,211.00 | $7,211.00 |
| 0225 | Handhole, signal, type 2 (805-11744) | EACH | 143 | $1,477.00 | $1,477.00 | $1,744.00 |
| 0226 | GPS mast mount radio unit (805-11759) | EACH | 18 | $7,387.00 | $7,387.00 | $7,387.00 |
| 0227 | GPS mast mount radio unit , relocate (805-11759) | EACH | 9 | $955.00 | $955.00 | $955.00 |
| 0228 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 30,879 | $32.50 | $32.50 | $32.50 |
| 0229 | Pedestrian push button, APS (805-11817) | EACH | 64 | $1,086.00 | $1,086.00 | $1,086.00 |
| 0230 | Traffic signal head, no. 3 (805-78205) | EACH | 219 | $907.00 | $907.00 | $907.00 |
| 0231 | Pedestrian push button, non-APS (805-78370) | EACH | 4 | $457.00 | $457.00 | $457.00 |
| 0232 | Signal pole, pedestal, 9 FT (805-78412) | EACH | 57 | $1,281.00 | $1,281.00 | $1,281.00 |
| 0233 | Span, catenary, and tether (805-78415) | EACH | 82 | $4,601.00 | $4,601.00 | $4,601.00 |
| 0234 | Disconnect hanger (805-78420) | EACH | 87 | $612.00 | $612.00 | $612.00 |
| 0235 | Signal service (805-78445) | EACH | 25 | $2,306.00 | $2,306.00 | $2,306.00 |
| 0236 | Signal cable, service, copper, 3C/8 gauge (805-78467) | LFT | 2,191 | $4.80 | $4.80 | $4.80 |
| 0237 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 77,800 | $0.22 | $0.22 | $0.22 |
| 0238 | Signal cable, control, copper, 3C/14 gauge (805-78480) | LFT | 35,572 | $4.10 | $4.10 | $4.10 |
| 0239 | Signal cable, control, copper, 5C/14 gauge (805-78485) | LFT | 4,180 | $4.40 | $4.40 | $4.40 |
| 0240 | Signal cable, control, copper, 9C/14 gauge (805-78495) | LFT | 20,814 | $5.90 | $5.90 | $5.90 |
| 0241 | Signal cable, detector lead-in, copper, 2C/16 gauge (805-78510) | LFT | 51,943 | $2.50 | $2.50 | $2.50 |
| 0242 | Signal detector housing (805-78785) | EACH | 222 | $2,596.00 | $2,596.00 | $2,596.00 |
| 0243 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 26,700 | $16.30 | $16.30 | $16.30 |
| 0244 | Controller cabinet foundation, type P1 (805-78925) | EACH | 20 | $2,778.00 | $2,778.00 | $2,778.00 |
| 0245 | Signal pole, steel strain, 30 FT (805-81032) | EACH | 95 | $8,318.00 | $8,318.00 | $8,318.00 |
| 0246 | Signal pole, steel strain, 36 FT (805-81060) | EACH | 1 | $10,125 | $10,125 | $10,125 |
| 0247 | Handhole, lighting (807-02191) | EACH | 55 | $1,366.00 | $1,366.00 | $1,366.00 |
| 0248 | Service point, II, modified (807-02194) | EACH | 27 | $10,173 | $10,173 | $10,173 |
| 0249 | Lighting foundation , concrete with ground, 24 in. dia. X 48 in. (807-04653) | EACH | 299 | $1,106.00 | $1,106.00 | $1,106.00 |
| 0250 | Lighting foundation , concrete with ground, 24 in. dia. X 72 in. (807-04653) | EACH | 112 | $1,461.00 | $1,461.00 | $1,461.00 |
| 0251 | Conduit, steel, galvanized, 2 in. (807-06592) | LFT | 14,303 | $43.20 | $43.20 | $43.20 |
| 0252 | Luminaire, high lumen roadway (807-12199) | EACH | 112 | $474.00 | $474.00 | $474.00 |
| 0253 | Light pole, 40 FT E.M.H., 20 FT mast arm, anchor base (807-12663) | EACH | 112 | $3,921.00 | $3,921.00 | $3,921.00 |
| 0254 | Wire, no. 4 copper, in plastic duct, 4 1/C (807-97237) | LFT | 71,019 | $19.50 | $19.50 | $19.50 |
| 0255 | Transverse marking, thermoplastic, crosswalk line, white, 24 in. (808-03439) | LFT | 1,940 | $7.66 | $7.66 | $7.66 |
| 0256 | Pavement message marking, remove (808-05866) | SYS | 69 | $36.00 | $36.00 | $36.00 |
| 0257 | Transverse marking, remove (808-06368) | LFT | 34 | $3.81 | $3.81 | $3.81 |
| 0258 | Line, remove (808-06716) | LFT | 37,219 | $0.45 | $0.45 | $0.45 |
| 0259 | Retro-reflectivity testing (808-09381) | LS | 1 | $22,580 | $22,580 | $22,580 |
| 0260 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 39,202 | $1.00 | $1.00 | $1.00 |
| 0262 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 61,313 | $1.00 | $1.00 | $1.00 |
| 0263 | Pavement message marking, multi- component, lane indication arrow (808-10077) | EACH | 1 | $225.00 | $225.00 | $225.00 |
| 0264 | Line, thermoplastic, dotted, white, 6 in. (808-11650) | LFT | 776 | $1.75 | $1.75 | $1.75 |
| 0265 | Grooving for pavement markings (808-12032) | LFT | 117,499 | $0.61 | $0.61 | $0.61 |
| 0266 | Transverse marking, thermoplastic, yield line, white, 36 in. (808-12148) | LFT | 217 | $17.85 | $17.85 | $17.85 |
| 0267 | Line, thermoplastic, dotted, yellow, 6 in. (808-12849) | LFT | 76 | $1.85 | $1.85 | $1.85 |
| 0268 | Line, thermoplastic, solid, yellow, 10 in. (808-12858) | LFT | 1,089 | $2.20 | $2.20 | $2.20 |
| 0270 | Line, preformed plastic, broken, white, 6 in. (808-75055) | LFT | 16,444 | $5.65 | $5.65 | $5.65 |
| 0273 | Transverse marking, thermoplastic, crosshatch line, white, 12 in. (808-75260) | LFT | 547 | $3.83 | $3.83 | $3.83 |
| 0274 | Transverse marking, thermoplastic, crosshatch line, yellow, 12 in. (808-75278) | LFT | 1,865 | $3.83 | $3.83 | $3.83 |
| 0275 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 3,080 | $7.66 | $7.66 | $7.66 |
| 0276 | Transverse marking, thermoplastic, crosswalk line, white, 6 in. (808-75300) | LFT | 6,309 | $1.92 | $1.92 | $1.92 |
| 0277 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 290 | $181.00 | $181.00 | $181.00 |
| 0279 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 599 | $50.00 | $11.80 | $56.19 |
| 0280 | Snowplowable raised pavement marker (808-75998) | EACH | 941 | $40.00 | $40.00 | $40.00 |
| 0281 | Roadway weather information system , relocate emergency weather signal pole (809-08372) | EACH | 1 | $12,490 | $12,490 | $12,490 |
| 0282 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 143,204 | $2.68 | $2.68 | $1.69 |
| 0283 | Fence, chain link, reset (603-06065) | LFT | 472 | $38.00 | $38.00 | $38.00 |
| 0284 | Line, thermoplastic, dotted, white, 10 in. (808-12850) | LFT | 324 | $5.37 | $5.37 | $5.37 |
| 0285 | Line, thermoplastic, solid, white, 10 in. (808-12953) | LFT | 1,545 | $2.19 | $2.19 | $2.19 |
| 0286 | Pipe installation, trenchless, 18 in. (716-07632) | LFT | 183 | $1,700.00 | $825.15 | $723.62 |
| 0287 | Milling, asphalt , 1.5 in. - 3.5 in. (306-08159) | SYS | 192,373 | $3.45 | $3.01 | $1.90 |
| 0288 | Temporary traffic barrier, type 2 (801-08401) | LFT | 1,000 | $36.00 | $44.41 | $70.31 |
| 0289 | Loop detector delay amplifier, counting, no. 2 channel (805-09539) | EACH | 68 | $361.00 | $361.00 | $361.00 |
| 0290 | Loop detector delay amplifier, noncounting 2 channel (805-92504) | EACH | 34 | $292.00 | $292.00 | $292.00 |
| 0291 | Temporary traffic barrier, anchored, type 2 (801-08508) | LFT | 1,000 | $35.45 | $59.02 | $83.56 |
| 0292 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 1 | $19,075 | $12,175 | $9,875.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of January 22, 2025. Compiled by Mirage Metrics.