INDOT contract R-42770-A bid tabulation
SIGHT DISTANCE IMPROVEMENT. Let by Indiana DOT on December 10, 2025, Huntington, Fort Wayne. 7 bids received; low bid $965,518 by Fleming Excavating Inc.
- Owner
- Indiana DOT
- Letting
- 10 DEC 2025
- Pay items
- 51
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Fleming Excavating Inc | $965,518 | Low |
| 2 | Brooks Construction Company Inc | $979,532 | +1.0% |
| 3 | E & B Paving LLC | $988,729 | +2.0% |
| 4 | 3D Company Inc | $989,870 | +3.0% |
| 5 | Morphey Construction Inc. | $1,083,460 | +12% |
| 6 | Deichman Excavating Co | $1,096,215 | +14% |
| 7 | Phend & Brown Inc | $1,419,027 | +47% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fleming Excavating Inc | 2. Brooks Construction Company Inc | 3. E & B Paving LLC | 4. 3D Company Inc | 5. Morphey Construction Inc. | 6. Deichman Excavating Co |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $25,300 | $19,000 | $14,800 | $11,150 | $13,300 | $22,900 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $52,296 | $48,500 | $49,430 | $51,365 | $50,000 | $108,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $16,800 | $4,000.00 | $14,105 | $6,405.00 | $10,000 | $5,000.00 |
| 0011 | Pipe, remove (202-96133) | LFT | 61 | $20.00 | $27.00 | $19.30 | $19.28 | $10.00 | $30.00 |
| 0012 | Excavation, common (203-02000) | CYS | 2,152 | $49.24 | $31.00 | $54.70 | $53.68 | $32.00 | $42.60 |
| 0013 | Borrow (203-02070) | CYS | 6,174 | $15.50 | $27.00 | $14.50 | $12.96 | $31.00 | $32.00 |
| 0014 | Stormwater management budget (205-12108) | DOL | 30,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0015 | Stormwater management implementation (205-12616) | LS | 1 | $28,031 | $500.00 | $14,133 | $25,370 | $750.00 | $15,750 |
| 0016 | SWQCP preparation (205-12618) | LS | 1 | $3,450.00 | $3,200.00 | $9,000.00 | $3,165.00 | $3,000.00 | $3,200.00 |
| 0017 | Subgrade treatment, type II (207-08264) | SYS | 314 | $10.82 | $18.25 | $20.00 | $16.20 | $25.00 | $26.00 |
| 0018 | Subgrade treatment, type IC (207-09935) | SYS | 7,572 | $20.56 | $20.00 | $24.75 | $21.67 | $30.00 | $20.00 |
| 0019 | Structure backfill, type 2 (211-09265) | CYS | 20 | $45.58 | $100.00 | $71.50 | $71.50 | $110.00 | $80.00 |
| 0020 | Compacted aggregate, no. 53 (301-12234) | CYS | 53 | $25.79 | $72.00 | $123.00 | $90.00 | $85.00 | $85.00 |
| 0021 | Compacted aggregate, no. 53 (303-01180) | TON | 255 | $37.79 | $46.00 | $67.00 | $56.00 | $70.00 | $39.50 |
| 0022 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 548 | $90.72 | $96.00 | $84.00 | $93.00 | $84.00 | $84.00 |
| 0023 | QC/QA-HMA, 2, 58S, intermediate, 19.0 MM (401-000037) | TON | 1,347 | $84.24 | $75.00 | $78.00 | $86.00 | $78.00 | $78.00 |
| 0024 | QC/QA-HMA, 2, 58S, base, 25.0 MM (401-000046) | TON | 1,952 | $70.20 | $69.00 | $65.00 | $72.00 | $65.00 | $65.00 |
| 0025 | Joint adhesive (401-11526) | LFT | 2,241 | $1.28 | $0.50 | $1.11 | $1.22 | $1.11 | $1.11 |
| 0026 | Asphalt for tack coat (406-05520) | TON | 5 | $690.00 | $800.00 | $600.00 | $660.00 | $600.00 | $600.00 |
| 0027 | HMA for approaches, type B (610-07487) | TON | 101 | $181.50 | $145.00 | $165.00 | $184.00 | $260.00 | $165.00 |
| 0028 | Mailbox assembly, reset, single (611-08232) | EACH | 4 | $300.00 | $475.00 | $355.00 | $525.00 | $475.00 | $355.00 |
| 0029 | Monument, section corner (615-06527) | EACH | 2 | $1,320.00 | $800.00 | $1,600.00 | $880.00 | $800.00 | $1,600.00 |
| 0030 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $488.75 | $425.00 | $425.00 | $470.00 | $425.00 | $425.00 |
| 0031 | Mulched seeding, type R (621-06559) | SYS | 6,187 | $1.04 | $0.90 | $0.90 | $1.00 | $3.17 | $0.95 |
| 0032 | Sodding (621-06574) | SYS | 863 | $6.10 | $5.30 | $5.30 | $5.83 | $12.00 | $5.57 |
| 0033 | Field office, type D (628-12683) | MOS | 12 | $989.75 | $3,250.00 | $3,250.00 | $3,575.00 | $2,000.00 | $4,250.00 |
| 0034 | Pipe, type 3, circular, diameter 12 in. (715-05168) | LFT | 191 | $49.43 | $60.00 | $74.75 | $74.75 | $70.00 | $60.00 |
| 0035 | Pipe end section, diameter 12 in. (715-46000) | EACH | 8 | $664.00 | $520.00 | $905.00 | $905.00 | $1,750.00 | $675.00 |
| 0036 | Road closure sign assembly (801-04308) | EACH | 8 | $280.50 | $255.00 | $255.00 | $285.00 | $255.00 | $255.00 |
| 0037 | Detour route marker assembly (801-06625) | EACH | 48 | $168.30 | $153.00 | $153.00 | $170.00 | $153.00 | $153.00 |
| 0038 | Construction sign, type A (801-06640) | EACH | 24 | $229.90 | $209.00 | $209.00 | $230.00 | $209.00 | $209.00 |
| 0039 | Maintaining traffic (801-06775) | LS | 1 | $13,677 | $27,834 | $3,500.00 | $6,745.00 | $8,880.84 | $10,000 |
| 0040 | Barricade, type III-A (801-07118) | LFT | 96 | $17.84 | $15.51 | $15.51 | $17.10 | $15.51 | $15.51 |
| 0041 | Barricade, type III-B (801-07119) | LFT | 112 | $17.84 | $15.51 | $15.51 | $17.10 | $15.51 | $15.51 |
| 0042 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 277 | $20.90 | $20.00 | $18.00 | $22.00 | $20.00 | $18.00 |
| 0043 | Sign, sheet, and supports, remove (802-07059) | EACH | 11 | $86.25 | $125.00 | $71.00 | $138.00 | $125.00 | $71.00 |
| 0044 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 77 | $17.25 | $35.00 | $38.00 | $38.50 | $35.00 | $38.00 |
| 0045 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 40 | $23.00 | $40.00 | $30.00 | $44.00 | $40.00 | $30.00 |
| 0046 | Line, thermoplastic, solid, white, 4 in. (808-06703) | LFT | 4,618 | $0.89 | $0.81 | $0.81 | $0.90 | $0.81 | $0.81 |
| 0047 | Grooving for pavement markings (808-12032) | LFT | 7,776 | $1.01 | $0.88 | $0.88 | $1.00 | $0.88 | $0.88 |
| 0048 | Line, thermoplastic, broken, yellow, 4 in. (808-75240) | LFT | 460 | $1.12 | $0.97 | $0.97 | $1.10 | $0.97 | $0.97 |
| 0049 | Line, thermoplastic, solid, yellow, 4 in. (808-75245) | LFT | 2,698 | $0.93 | $0.81 | $0.81 | $0.90 | $0.81 | $0.81 |
| 0050 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 43 | $15.65 | $13.61 | $13.61 | $15.00 | $13.61 | $13.61 |
| 0051 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 2,241 | $4.40 | $7.50 | $4.00 | $4.24 | $4.00 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of December 10, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.