INDOT contract R-43285-A bid tabulation
HMA OVERLAY, INTERSECTION IMPROVE AND SMALL STR REPLACEMENT. Let by Indiana DOT on July 9, 2025, Wabash, Fort Wayne. 4 bids received; low bid $11,017,882 by Brooks Construction Company Inc.
- Owner
- Indiana DOT
- Letting
- 09 JUL 2025
- Pay items
- 208
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Brooks Construction Company Inc | $11,017,882 | Low |
| 2 | E & B Paving LLC | $11,741,675 | +7.0% |
| 3 | Phend & Brown Inc | $12,325,349 | +12% |
| 4 | Bunn Excavating Inc | $12,713,885 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Brooks Construction Company Inc | 2. E & B Paving LLC | 3. Phend & Brown Inc | 4. Bunn Excavating Inc |
|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $75,000 | $100,000 | $150,000 | $76,743 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 2 | $1,000.00 | $554.86 | $1.00 | $823.50 |
| 0003 | Inspection hole, 3 FT deep or less (107-09367) | EACH | 2 | $800.00 | $374.65 | $1.00 | $632.52 |
| 0004 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, pavement traffic markings (109-09377) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0012 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0013 | Mobilization and demobilization (110-01001) | LS | 1 | $540,000 | $585,000 | $600,000 | $354,483 |
| 0014 | Clearing right-of-way (201-52370) | LS | 1 | $55,000 | $42,874 | $75,000 | $45,435 |
| 0015 | Pavement removal (202-02240) | SYS | 1,026 | $30.00 | $18.21 | $30.00 | $24.14 |
| 0016 | Headwall, remove (202-02271) | EACH | 5 | $441.00 | $659.27 | $659.27 | $698.66 |
| 0017 | Catch basin, remove (202-02928) | EACH | 1 | $503.00 | $542.61 | $542.61 | $575.03 |
| 0018 | Delineator post, remove (202-04435) | EACH | 32 | $48.00 | $50.00 | $25.30 | $58.87 |
| 0019 | Handhole, remove (202-86946) | EACH | 2 | $750.00 | $750.00 | $1,000.00 | $883.08 |
| 0020 | Detector housing, remove (202-90277) | EACH | 27 | $300.00 | $300.00 | $400.00 | $353.23 |
| 0021 | Inlet, remove (202-91385) | EACH | 5 | $500.00 | $542.61 | $542.60 | $575.03 |
| 0022 | Pipe, remove (202-96133) | LFT | 369 | $50.00 | $23.83 | $23.83 | $25.25 |
| 0023 | Excavation, common (203-02000) | CYS | 5,885 | $51.00 | $55.78 | $55.78 | $59.11 |
| 0024 | Borrow (203-02070) | CYS | 557 | $30.00 | $33.89 | $33.89 | $35.92 |
| 0025 | Linear grading (203-08607) | LFT | 295 | $16.00 | $25.17 | $25.17 | $26.67 |
| 0026 | Linear grading , shoulder clipping (203-08607) | LFT | 7,405 | $10.00 | $7.85 | $25.17 | $26.67 |
| 0027 | Pump around (205-11626) | EACH | 2 | $12,693 | $25,000 | $8,459.96 | $8,965.43 |
| 0028 | Stormwater management budget (205-12108) | DOL | 47,812.93 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0029 | Stormwater management implementation (205-12616) | LS | 1 | $28,800 | $25,000 | $15,000 | $236,585 |
| 0030 | SWQCP preparation (205-12618) | LS | 1 | $2,600.00 | $2,600.00 | $3,600.00 | $4,777.58 |
| 0031 | Subgrade treatment, type IC (207-09935) | SYS | 18,258 | $37.00 | $28.95 | $29.10 | $30.83 |
| 0032 | Structure backfill, type 1 (211-09264) | CYS | 43 | $85.00 | $67.13 | $67.13 | $71.14 |
| 0033 | Structure backfill, type 2 (211-09265) | CYS | 314 | $77.00 | $64.56 | $64.56 | $68.42 |
| 0034 | Structure backfill, type 4 (211-09267) | CYS | 18 | $420.00 | $284.54 | $284.54 | $301.54 |
| 0035 | Structure backfill, type 5 (211-09268) | CYS | 126 | $380.00 | $205.18 | $205.18 | $217.44 |
| 0036 | Geogrid, type IB (214-11796) | SYS | 4,519 | $4.00 | $3.44 | $3.50 | $3.56 |
| 0037 | Geotextile for pavement, type 2A (214-12238) | SYS | 687 | $4.00 | $3.96 | $3.96 | $4.19 |
| 0038 | Compacted aggregate, no. 5 (301-12232) | CYS | 229 | $87.00 | $83.80 | $83.80 | $88.81 |
| 0039 | Compacted aggregate, no. 53 (301-12234) | CYS | 4,523 | $58.00 | $54.33 | $54.33 | $57.57 |
| 0040 | Subbase for PCCP (302-06464) | CYS | 45 | $136.00 | $57.59 | $57.59 | $61.03 |
| 0041 | Compacted aggregate, no. 53 (303-01180) | TON | 1,652 | $44.00 | $29.48 | $27.16 | $28.79 |
| 0042 | Compacted aggregate, no. 73 (303-07449) | TON | 755 | $46.00 | $70.41 | $27.16 | $28.79 |
| 0043 | HMA patching, full depth, type D (304-12627) | TON | 222 | $200.00 | $400.00 | $355.00 | $470.98 |
| 0044 | HMA patching, partial depth, type D (304-12628) | TON | 961 | $174.00 | $195.00 | $215.00 | $206.05 |
| 0045 | Milling, asphalt, 2 in. (306-08036) | SYS | 245,572 | $1.30 | $4.35 | $1.33 | $2.01 |
| 0046 | Milling, asphalt, 4 in. (306-08038) | SYS | 1,092 | $9.00 | $7.78 | $6.50 | $4.42 |
| 0047 | Milling, approach (306-08432) | SYS | 11,648 | $6.00 | $4.00 | $5.20 | $1.69 |
| 0048 | QC/QA-HMA, 2, 58S, surface, 9.5 MM (401-000001) | TON | 6,001 | $79.00 | $100.00 | $93.00 | $90.66 |
| 0049 | QC/QA-HMA, 4, 58H, surface, 9.5 MM (401-000006) | TON | 2,371 | $102.00 | $65.00 | $93.00 | $106.22 |
| 0050 | QC/QA-HMA, 4, 58E, surface, 9.5 MM (401-000009) | TON | 20,024 | $90.00 | $100.00 | $108.00 | $118.02 |
| 0051 | QC/QA-HMA, 4, 58H, intermediate, 19.0 MM (401-000042) | TON | 978 | $106.00 | $90.00 | $100.00 | $106.22 |
| 0052 | QC/QA-HMA, 4, 58E, intermediate, 19.0 MM (401-000045) | TON | 568 | $113.00 | $120.00 | $127.00 | $141.62 |
| 0053 | QC/QA-HMA, 4, 58S, base, 25.0 MM (401-000048) | TON | 4,441 | $97.00 | $75.00 | $100.00 | $88.51 |
| 0054 | Joint adhesive, intermediate (401-10259) | LFT | 12,155 | $0.10 | $0.30 | $1.00 | $0.37 |
| 0055 | Inertial profiler, HMA (401-12169) | LS | 1 | $15,000 | $8,000.00 | $10,500 | $9,441.52 |
| 0056 | Void reducing asphalt membrane for HMA (401-12439) | LFT | 137,772 | $2.70 | $3.00 | $2.50 | $3.54 |
| 0057 | HMA spray paver emulsion (401-12664) | TON | 154 | $738.00 | $800.00 | $750.00 | $944.15 |
| 0058 | HMA for temporary pavement, type D (402-10087) | TON | 2,295 | $100.00 | $125.00 | $101.00 | $184.07 |
| 0059 | Asphalt for tack coat (406-05520) | TON | 38 | $700.00 | $600.00 | $700.00 | $708.11 |
| 0060 | Guardrail, reset (601-06035) | LFT | 250 | $70.00 | $60.00 | $70.00 | $69.63 |
| 0061 | Fence, farm field, reset (603-06060) | LFT | 100 | $81.00 | $109.00 | $81.00 | $61.37 |
| 0062 | Curb and gutter, concrete (605-06140) | LFT | 30 | $80.00 | $88.97 | $130.00 | $109.20 |
| 0063 | Curb and gutter, concrete, type B , modified (605-06145) | LFT | 235 | $55.00 | $63.89 | $65.00 | $78.39 |
| 0064 | Center curb, concrete, type B (605-06245) | SYS | 177 | $90.00 | $57.29 | $160.00 | $70.28 |
| 0065 | Milled HMA corrugations, conventional (606-12399) | LFT | 81,049 | $0.45 | $0.65 | $0.30 | $0.99 |
| 0066 | HMA for approaches, type B (610-07487) | TON | 170 | $130.00 | $150.00 | $132.00 | $177.03 |
| 0067 | HMA for approaches, type D (610-07788) | TON | 1,112 | $130.00 | $125.00 | $155.00 | $147.52 |
| 0068 | Riprap, class 1 (616-05688) | TON | 93 | $170.00 | $206.71 | $206.71 | $219.58 |
| 0069 | Riprap, class 2 (616-05689) | TON | 48 | $172.00 | $211.67 | $211.67 | $224.84 |
| 0070 | Riprap, revetment (616-06405) | TON | 60 | $125.00 | $78.56 | $78.56 | $83.45 |
| 0071 | Riprap, uniform (616-06451) | TON | 20 | $120.00 | $69.60 | $69.60 | $73.93 |
| 0072 | Geotextile for riprap, type 1A (616-12246) | SYS | 43 | $4.00 | $13.39 | $13.39 | $14.23 |
| 0073 | Geotextile for riprap, type 2A (616-12248) | SYS | 323 | $4.00 | $4.07 | $4.07 | $4.32 |
| 0074 | Mobilization and demobilization for seeding (621-01004) | EACH | 18 | $450.00 | $500.00 | $450.00 | $590.09 |
| 0075 | Erosion control blanket (621-02770) | SYS | 1,387 | $5.30 | $2.40 | $5.30 | $2.83 |
| 0076 | Fertilizer, for permanent seeding , for permanent seeding (621-06545) | TON | 2 | $1,540.00 | $1,450.00 | $1,540.00 | $1,711.28 |
| 0077 | Seed mixture, type R (621-06553) | LBS | 564 | $13.25 | $8.00 | $13.25 | $9.44 |
| 0078 | Mulched seeding, type R (621-06559) | SYS | 11,074 | $3.75 | $2.25 | $3.75 | $2.66 |
| 0079 | Mulching material (621-06565) | TON | 3 | $2,075.00 | $1,000.00 | $2,075.00 | $1,180.19 |
| 0080 | Field office, type D (628-12683) | MOS | 18 | $4,500.00 | $4,500.00 | $5,556.21 | $6,846.85 |
| 0081 | Temporary shoring (702-04325) | LS | 1 | $75,000 | $36,058 | $36,058 | $38,302 |
| 0082 | Grated box end section, type I, 2:1, diameter 21 in. (715-000152) | EACH | 1 | $10,000 | $3,234.87 | $3,234.87 | $3,436.15 |
| 0083 | Grated box end section, type I, 4:1, diameter 21 in. (715-000153) | EACH | 1 | $15,000 | $4,684.81 | $4,684.81 | $4,976.31 |
| 0084 | Grated box end section, type I, 2:1, diameter 27 in. (715-000154) | EACH | 2 | $11,000 | $3,447.09 | $3,447.09 | $3,661.58 |
| 0085 | Safety metal end section, 4:1, diameter 36 in. (715-02397) | EACH | 2 | $8,000.00 | $7,770.21 | $7,770.21 | $8,253.69 |
| 0086 | Safety metal end section, 4:1, diameter 42 in. (715-02399) | EACH | 1 | $12,000 | $9,751.04 | $9,751.04 | $10,358 |
| 0087 | Safety metal end section, 4:1, diameter 48 in. (715-02407) | EACH | 1 | $12,000 | $12,139 | $12,139 | $12,894 |
| 0088 | Safety metal end section, 6:1, diameter 15 in. (715-02628) | EACH | 1 | $1,800.00 | $1,106.80 | $1,106.80 | $1,175.67 |
| 0089 | Safety metal end section, 6:1, diameter 18 in. (715-02629) | EACH | 1 | $2,400.00 | $2,224.46 | $2,224.46 | $2,362.86 |
| 0090 | Pipe, type 1, circular, diameter 36 in. (715-05019) | LFT | 141 | $247.00 | $127.92 | $127.92 | $135.88 |
| 0091 | Pipe, type 4, circular, diameter 6 in. (715-05048) | LFT | 8 | $55.00 | $53.91 | $53.91 | $57.26 |
| 0092 | Pipe, underdrain outlet, diameter 6 in. (715-05053) | LFT | 104 | $37.00 | $61.43 | $61.43 | $65.26 |
| 0093 | Pipe, type 1, circular, diameter 18 in. (715-05121) | LFT | 60 | $102.00 | $88.01 | $88.01 | $93.49 |
| 0094 | Pipe, type 1, circular, diameter 21 in. (715-05122) | LFT | 45 | $135.00 | $96.98 | $96.98 | $103.01 |
| 0095 | Pipe, type 1, circular, diameter 27 in. (715-05124) | LFT | 143 | $213.00 | $119.98 | $119.98 | $127.44 |
| 0096 | Pipe, type 1, circular, diameter 42 in. (715-05127) | LFT | 15 | $661.00 | $208.30 | $208.30 | $221.26 |
| 0097 | Pipe, type 2, circular, diameter 12 in. (715-05149) | LFT | 458 | $99.00 | $71.79 | $71.79 | $76.26 |
| 0098 | Pipe, type 2, circular, diameter 15 in. (715-05151) | LFT | 295 | $104.00 | $79.12 | $79.12 | $84.05 |
| 0099 | Pipe, type 2, circular, diameter 18 in. (715-05152) | LFT | 58 | $240.00 | $89.32 | $89.32 | $94.88 |
| 0100 | Pipe extension, circular, diameter 15 in. , CLV-82584 (715-05595) | LFT | 13 | $148.00 | $93.05 | $93.05 | $98.84 |
| 0101 | Concrete anchor, diameter 42 in. (715-05842) | EACH | 2 | $5,530.00 | $2,843.53 | $2,843.53 | $8,261.33 |
| 0102 | Safety metal end section, 6:1, diameter 42 in. (715-06077) | EACH | 1 | $12,961 | $13,214 | $13,214 | $14,036 |
| 0103 | HMA for structure installation, type D (715-08307) | TON | 303 | $180.00 | $242.85 | $300.00 | $294.33 |
| 0104 | Video inspection for pipe (715-09064) | LFT | 2,320 | $1.45 | $1.45 | $1.45 | $1.71 |
| 0105 | Grated box end section, type I, 2:1, diameter 48 in. (715-26779) | EACH | 1 | $26,000 | $6,691.96 | $6,691.96 | $7,108.35 |
| 0106 | Pipe end section, diameter 12 in. (715-46000) | EACH | 2 | $890.00 | $1,029.38 | $1,029.38 | $1,093.43 |
| 0107 | Pipe end section, diameter 15 in. (715-46005) | EACH | 4 | $1,000.00 | $1,100.15 | $1,100.15 | $1,168.61 |
| 0108 | Pipe end section, diameter 18 in. (715-46010) | EACH | 4 | $1,100.00 | $1,204.57 | $1,204.57 | $1,279.52 |
| 0109 | Grated box end section, type I, 3:1, diameter 15 in. (715-97404) | EACH | 1 | $9,650.00 | $2,661.85 | $2,661.85 | $2,827.47 |
| 0110 | Pipe installation, trenchless, 12 in. (716-07630) | LFT | 70 | $665.00 | $959.54 | $1,500.00 | $855.41 |
| 0111 | Pipe installation, trenchless, 18 in. (716-07632) | LFT | 250 | $675.00 | $757.48 | $1,300.00 | $842.30 |
| 0112 | Pipe installation, trenchless, 42 in. (716-07636) | LFT | 401 | $920.00 | $985.52 | $1,580.00 | $1,509.03 |
| 0113 | Pipe installation, trenchless, 48 in. (716-07637) | LFT | 154 | $1,275.00 | $1,445.61 | $2,100.00 | $1,887.29 |
| 0114 | Outlet protector, type 3 (718-06531) | EACH | 1 | $1,900.00 | $716.26 | $716.26 | $760.82 |
| 0115 | Casting, type 10, furnish and adjust to grade (720-44055) | EACH | 1 | $1,400.00 | $1,299.82 | $1,299.82 | $1,380.70 |
| 0116 | Inlet, type N12 (720-45065) | EACH | 3 | $6,500.00 | $4,900.69 | $4,900.69 | $5,205.62 |
| 0117 | Inlet, type N12, modified (720-45066) | EACH | 4 | $7,200.00 | $5,072.91 | $5,072.91 | $5,388.56 |
| 0118 | Inlet, type P12A (720-45070) | EACH | 5 | $4,900.00 | $4,911.87 | $4,911.87 | $5,217.50 |
| 0119 | Inlet, type R13 (720-45075) | EACH | 2 | $4,100.00 | $4,249.72 | $4,249.72 | $4,514.15 |
| 0120 | Manhole, type C4 (720-45410) | EACH | 1 | $4,300.00 | $3,769.03 | $3,769.03 | $4,003.54 |
| 0121 | Inlet, type P12A, modified (720-95310) | EACH | 1 | $5,400.00 | $5,084.07 | $5,084.07 | $5,400.41 |
| 0122 | Inlet, type A4 , modified (720-97896) | EACH | 1 | $3,400.00 | $2,730.19 | $2,730.19 | $2,900.07 |
| 0123 | Pipe liner, cured-in- place, 12 in. (725-11275) | LFT | 76 | $215.60 | $236.60 | $725.00 | $301.75 |
| 0124 | Pipe liner, cured-in- place, 18 in. (725-12453) | LFT | 141 | $284.17 | $425.17 | $825.00 | $360.87 |
| 0125 | Temporary pavement message marking, lane indication arrow (801-01504) | EACH | 34 | $250.00 | $120.00 | $120.00 | $213.61 |
| 0126 | Temporary pavement marking, 6 in. (801-06206) | LFT | 138,012 | $0.30 | $0.10 | $0.37 | $0.40 |
| 0127 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 193,551 | $1.68 | $0.10 | $1.60 | $1.98 |
| 0128 | Temporary pavement message marking, removable, lane indication arrow (801-06211) | EACH | 34 | $125.00 | $150.00 | $150.00 | $226.60 |
| 0129 | Temporary transverse pavement marking, 24 in. (801-06216) | LFT | 637 | $20.00 | $10.00 | $10.00 | $14.02 |
| 0130 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 637 | $25.00 | $10.00 | $14.00 | $15.60 |
| 0131 | Construction sign, type A (801-06640) | EACH | 96 | $250.00 | $180.00 | $180.00 | $272.62 |
| 0132 | Construction sign, type B (801-06645) | EACH | 5 | $150.00 | $100.00 | $100.00 | $140.44 |
| 0133 | Flashing arrow sign (801-06710) | DAY | 800 | $20.00 | $15.00 | $15.00 | $18.88 |
| 0134 | Maintaining traffic (801-06775) | LS | 1 | $378,963 | $694,200 | $575,000 | $91,237 |
| 0135 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 7 | $4,850.00 | $5,560.00 | $8,869.00 | $10,467 |
| 0136 | Barricade, type III-A (801-07118) | LFT | 216 | $20.00 | $17.00 | $17.00 | $19.90 |
| 0137 | Temporary traffic barrier, type 2 (801-08401) | LFT | 3,684 | $35.00 | $20.00 | $48.00 | $56.65 |
| 0138 | Portable changeable message sign (801-11642) | EACH | 2 | $6,500.00 | $5,013.00 | $5,013.00 | $6,938.34 |
| 0139 | Truck mounted attenuator (801-12042) | DAY | 600 | $250.00 | $320.00 | $150.00 | $431.95 |
| 0140 | Temporary speed feedback assembly (801-12832) | EACH | 4 | $4,000.00 | $7,500.00 | $7,500.00 | $3,526.41 |
| 0141 | Temporary worksite speed limit sign assembly, continuous (801-12883) | EACH | 16 | $400.00 | $400.00 | $400.00 | $1,325.35 |
| 0142 | Construction signs mobile (801-92448) | DAY | 500 | $1.00 | $2.50 | $8.00 | $39.44 |
| 0143 | Sign post, square, type 1, unreinforced anchor base (802-05704) | LFT | 282 | $18.75 | $18.75 | $30.00 | $22.13 |
| 0144 | Sign post, square, type 2, unreinforced anchor base (802-05705) | LFT | 89 | $18.50 | $18.50 | $29.00 | $21.83 |
| 0145 | Sign, panel, with legend (802-07057) | SFT | 692 | $45.00 | $45.00 | $45.00 | $53.11 |
| 0146 | Sign, sheet, and supports, remove (802-07059) | EACH | 20 | $110.00 | $110.00 | $150.00 | $129.82 |
| 0147 | Sign, sheet, relocate (802-07060) | EACH | 8 | $125.00 | $125.00 | $200.00 | $147.52 |
| 0148 | Sign, sheet, with legend, 0.080 in. thickness (802-09838) | SFT | 91.50 | $18.00 | $18.00 | $30.00 | $21.24 |
| 0149 | Sign, sheet, with legend, 0.100 in. thickness (802-09840) | SFT | 277.50 | $21.00 | $21.00 | $32.00 | $24.78 |
| 0150 | Sign, sheet, with legend, 0.125 in. thickness (802-09842) | SFT | 16 | $30.00 | $30.00 | $34.00 | $35.41 |
| 0151 | Wide flange sign post support foundation, type A (802-12222) | EACH | 4 | $3,000.00 | $3,000.00 | $2,800.00 | $3,540.57 |
| 0152 | Wide flange sign post support foundation, type B (802-12223) | EACH | 10 | $3,500.00 | $3,500.00 | $3,100.00 | $4,130.66 |
| 0153 | Structural steel, breakaway (802-76095) | LBS | 4,407 | $9.00 | $9.00 | $6.00 | $10.62 |
| 0154 | Sign, ground mounted, reset (802-91122) | EACH | 12 | $275.00 | $275.00 | $300.00 | $324.55 |
| 0155 | Delineator post, flexible, type I (804-11920) | EACH | 71 | $160.00 | $125.00 | $160.00 | $147.52 |
| 0156 | Miscellaneous equipment for traffic signals (805-01579) | LS | 1 | $38,000 | $38,000 | $2,500.00 | $44,847 |
| 0157 | Traffic signal head, realign (805-01828) | EACH | 2 | $1,500.00 | $1,500.00 | $700.00 | $1,770.29 |
| 0158 | Handhole, signal, type 1 , modified (805-01842) | EACH | 4 | $3,750.00 | $3,750.00 | $4,000.00 | $4,425.71 |
| 0159 | Conduit, HDPE, 2 in. schedule 80 (805-11815) | LFT | 537 | $12.00 | $12.00 | $36.00 | $14.16 |
| 0160 | Traffic signal head, no. 4 (805-78225) | EACH | 2 | $1,500.00 | $1,500.00 | $1,400.00 | $1,770.29 |
| 0161 | Signal cable, roadway loop, copper, 1C/14 gauge (805-78470) | LFT | 12,354 | $0.65 | $0.65 | $2.00 | $0.77 |
| 0162 | Signal cable, control, copper, 7C/14 gauge (805-78490) | LFT | 440 | $8.00 | $8.00 | $5.50 | $9.44 |
| 0163 | Signal cable, control, copper, 9C/14 gauge (805-78495) | LFT | 314 | $9.00 | $9.00 | $6.00 | $10.62 |
| 0164 | Signal cable, detector lead-in, copper, 2C/16 gauge (805-78510) | LFT | 1,517 | $4.00 | $4.00 | $2.00 | $4.72 |
| 0165 | Signal detector housing (805-78785) | EACH | 27 | $1,500.00 | $1,500.00 | $2,200.00 | $1,770.28 |
| 0166 | Saw cut for roadway loop detector and sealant (805-78795) | LFT | 4,433 | $12.00 | $12.00 | $14.00 | $14.16 |
| 0167 | Loop detector delay amplifier, noncounting 2 channel (805-92504) | EACH | 1 | $375.00 | $375.00 | $600.00 | $442.57 |
| 0168 | Handhole, lighting (807-02191) | EACH | 3 | $1,500.00 | $1,500.00 | $1,500.00 | $1,770.28 |
| 0169 | Lighting foundation, concrete, with grounding, 24 in. X 24 in. X 96 in. (807-03758) | EACH | 10 | $2,500.00 | $2,500.00 | $3,500.00 | $2,950.47 |
| 0170 | Luminaire, low lumen roadway (807-12202) | EACH | 10 | $1,500.00 | $1,500.00 | $600.00 | $1,770.28 |
| 0171 | Light pole, 40 FT E.M.H., 15 FT mast arm, breakaway base (807-85762) | EACH | 10 | $3,500.00 | $3,500.00 | $4,300.00 | $4,130.66 |
| 0172 | Service point, type I (807-86805) | EACH | 1 | $10,000 | $10,000 | $10,500 | $11,802 |
| 0173 | Cable, pole circuit, THWN, no. 10 copper, stranded 1/C (807-86889) | LFT | 1,200 | $2.00 | $2.00 | $1.50 | $2.36 |
| 0174 | Connector kit, unfused (807-86910) | EACH | 10 | $125.00 | $125.00 | $75.00 | $147.52 |
| 0175 | Connector kit, fused (807-86915) | EACH | 10 | $125.00 | $125.00 | $75.00 | $147.52 |
| 0176 | Multiple compression fitting, non- waterproofed (807-86920) | EACH | 15 | $20.00 | $20.00 | $35.00 | $23.60 |
| 0177 | Multiple compression fitting, waterproofed (807-86925) | EACH | 8 | $20.00 | $20.00 | $60.00 | $23.60 |
| 0178 | Insulation link, non- waterproofed (807-86930) | EACH | 20 | $20.00 | $20.00 | $35.00 | $23.60 |
| 0179 | Insulation link, waterproofed (807-86935) | EACH | 20 | $20.00 | $20.00 | $60.00 | $23.60 |
| 0180 | Sign, underpass, and roadway lighting, location identification (807-86950) | EACH | 10 | $100.00 | $100.00 | $100.00 | $118.02 |
| 0181 | Cable-duct marker (807-86955) | EACH | 13 | $750.00 | $750.00 | $400.00 | $885.14 |
| 0182 | Wire, no. 4 copper, in plastic duct, 4 1/C (807-97237) | LFT | 3,352 | $25.00 | $25.00 | $22.00 | $29.50 |
| 0183 | Line, remove (808-06716) | LFT | 135,360 | $0.60 | $0.60 | $0.60 | $0.64 |
| 0184 | Retro-reflectivity testing (808-09381) | LS | 1 | $4,750.00 | $25,000 | $25,000 | $4,130.66 |
| 0185 | Transverse marking, multi-component, crosshatch line, white, 24 in. (808-10038) | LFT | 824 | $20.00 | $14.00 | $14.00 | $16.91 |
| 0186 | Transverse marking, multi-component, crosshatch line, white, 12 in. (808-10047) | LFT | 21 | $10.00 | $10.00 | $10.00 | $11.14 |
| 0187 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 60,438 | $1.10 | $1.00 | $1.00 | $1.01 |
| 0188 | Transverse marking, multi-component, stop line, white, 24 in. (808-10051) | LFT | 637 | $20.00 | $14.00 | $14.00 | $16.91 |
| 0189 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 50,840 | $1.10 | $1.00 | $1.00 | $1.01 |
| 0190 | Pavement message marking, multi- component, lane indication arrow (808-10077) | EACH | 34 | $275.00 | $190.00 | $190.00 | $274.98 |
| 0191 | Transverse marking, thermoplastic, yield line, white, 24 in. (808-10118) | LFT | 48 | $16.48 | $15.00 | $15.00 | $29.35 |
| 0192 | Transverse marking, multi-component, crosshatch line, yellow, 24 in. (808-10119) | LFT | 128 | $20.00 | $13.00 | $13.00 | $16.91 |
| 0193 | Grooving for pavement markings (808-12032) | LFT | 147,525 | $0.60 | $0.58 | $0.58 | $0.76 |
| 0194 | Line, thermoplastic, solid, white, 10 in. (808-12667) | LFT | 364 | $4.55 | $3.00 | $3.00 | $7.60 |
| 0195 | Line, multi-component, solid, white, 10 in. (808-12781) | LFT | 2,968 | $1.90 | $3.00 | $3.00 | $3.91 |
| 0196 | Line, thermoplastic, solid, yellow, 10 in. (808-12858) | LFT | 405 | $4.28 | $3.00 | $3.00 | $7.60 |
| 0197 | Line, multi-component, solid, yellow, 10 in. (808-12859) | LFT | 1,148 | $1.90 | $3.00 | $3.00 | $3.91 |
| 0198 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 10,510 | $0.91 | $1.10 | $1.10 | $1.13 |
| 0199 | Line, preformed plastic, broken, white, 6 in. (808-75055) | LFT | 12,190 | $8.00 | $6.50 | $6.50 | $8.51 |
| 0200 | Line, thermoplastic, solid, yellow, 6 in. (808-75247) | LFT | 7,096 | $0.91 | $1.10 | $1.10 | $1.13 |
| 0201 | Transverse marking, thermoplastic, crosshatch line, white, 24 in. (808-75272) | LFT | 66 | $7.35 | $14.00 | $14.42 | $16.37 |
| 0202 | Transverse marking, thermoplastic, crosshatch line, yellow, 24 in. (808-75290) | LFT | 409 | $7.35 | $14.00 | $14.00 | $16.37 |
| 0203 | Transverse marking, thermoplastic, stop line, white, 24 in. (808-75297) | LFT | 63 | $7.35 | $14.00 | $14.00 | $16.37 |
| 0204 | Pavement message marking, thermoplastic, lane indication arrow (808-75320) | EACH | 19 | $227.00 | $150.00 | $150.00 | $260.82 |
| 0205 | Pavement message marking, thermoplastic, 'only' (808-75325) | EACH | 2 | $197.00 | $250.00 | $250.00 | $304.49 |
| 0206 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 920 | $10.00 | $10.00 | $26.34 | $23.07 |
| 0207 | Snowplowable raised pavement marker (808-75998) | EACH | 932 | $75.00 | $40.00 | $40.00 | $41.07 |
| 0208 | Line, thermoplastic, broken, white, 6 in. (808-96075) | LFT | 1,767 | $1.50 | $1.25 | $1.25 | $2.49 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of July 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.