INDOT contract R-43750-A bid tabulation
SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on August 6, 2025, Jennings, Seymour. 8 bids received; low bid $487,694 by 5 Star Company Inc.
- Owner
- Indiana DOT
- Letting
- 06 AUG 2025
- Pay items
- 69
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | 5 Star Company Inc | $487,694 | Low |
| 2 | Olco Inc | $530,454 | +9.0% |
| 3 | Milestone Contractors LP | $540,277 | +11% |
| 4 | Paul H Rohe Company Inc | $552,633 | +13% |
| 5 | Dave Omara Contractor Inc | $616,219 | +26% |
| 6 | Force Construction Co Inc | $621,268 | +27% |
| 7 | Morphey Construction Inc. | $628,000 | +29% |
| 8 | Ragle, Inc. | $720,105 | +48% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. 5 Star Company Inc | 2. Olco Inc | 3. Milestone Contractors LP | 4. Paul H Rohe Company Inc | 5. Dave Omara Contractor Inc | 6. Force Construction Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $11,000 | $16,060 | $10,000 | $5,900.00 | $9,500.00 | $6,307.00 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Mobilization and demobilization (110-01001) | LS | 1 | $32,500 | $19,345 | $27,000 | $23,973 | $29,800 | $36,000 |
| 0010 | Clearing right-of-way (201-52370) | LS | 1 | $12,550 | $11,743 | $44,000 | $19,470 | $36,000 | $19,200 |
| 0011 | Present structure, remove, structure no. CV 007-040-17.45 (202-51330) | LS | 1 | $5,000.00 | $27,071 | $55,000 | $49,275 | $21,000 | $32,540 |
| 0012 | Sign, remove (202-74035) | EACH | 4 | $150.00 | $87.84 | $75.00 | $75.00 | $450.00 | $166.00 |
| 0013 | Pipe, remove (202-96133) | LFT | 39 | $22.00 | $30.40 | $19.65 | $52.00 | $50.00 | $50.00 |
| 0014 | Fence, farm field, remove (202-99187) | LFT | 553 | $10.00 | $4.00 | $4.00 | $5.00 | $10.00 | $4.20 |
| 0015 | Excavation, common (203-02000) | CYS | 765 | $39.00 | $40.89 | $32.00 | $38.00 | $48.00 | $57.00 |
| 0016 | Pump around (205-11626) | EACH | 1 | $7,500.00 | $8,103.18 | $19,100 | $8,520.00 | $14,900 | $13,350 |
| 0017 | Stormwater management budget (205-12108) | DOL | 3,900 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $3,500.00 | $4,007.94 | $2,200.00 | $2,200.00 | $22,000 | $3,755.00 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 300 | $58.00 | $52.13 | $30.40 | $48.00 | $38.00 | $64.00 |
| 0020 | Structure backfill, type 2 (211-09265) | CYS | 215 | $99.00 | $72.15 | $68.40 | $94.00 | $145.00 | $104.00 |
| 0021 | Geotextile for pavement, type 2A (214-12238) | SYS | 195 | $7.00 | $4.64 | $9.40 | $5.00 | $11.00 | $9.10 |
| 0022 | Geotextile for pavement, type 2B (214-12239) | SYS | 300 | $7.00 | $5.29 | $7.85 | $6.00 | $8.00 | $8.70 |
| 0023 | Compacted aggregate, no. 5 (301-12232) | CYS | 35 | $100.00 | $112.06 | $91.60 | $100.00 | $82.00 | $105.00 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 230 | $60.00 | $65.92 | $72.10 | $58.00 | $36.00 | $52.00 |
| 0025 | Widening with HMA, type B (304-07493) | TON | 95 | $200.00 | $194.24 | $138.00 | $200.00 | $150.00 | $225.00 |
| 0026 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 616 | $10.00 | $8.64 | $13.40 | $7.00 | $12.00 | $11.00 |
| 0027 | QC/QA-HMA, 3, 58S, surface, 9.5 MM (401-000002) | TON | 90 | $189.00 | $226.96 | $175.00 | $185.00 | $190.00 | $241.00 |
| 0028 | QC/QA-HMA, 3, 58S, intermediate, 19.0 MM (401-000038) | TON | 38 | $175.00 | $194.39 | $158.00 | $184.00 | $130.00 | $182.00 |
| 0029 | QC/QA-HMA, 3, 58S, base, 25.0 MM (401-000047) | TON | 92 | $160.00 | $175.10 | $139.00 | $165.00 | $109.00 | $175.00 |
| 0030 | Joint adhesive, surface (401-10258) | LFT | 918 | $1.00 | $1.75 | $1.45 | $0.65 | $3.00 | $1.00 |
| 0031 | Joint adhesive, intermediate (401-10259) | LFT | 225 | $1.00 | $1.76 | $3.45 | $1.00 | $11.00 | $1.00 |
| 0032 | Asphalt for tack coat (406-05520) | TON | 1 | $1,500.00 | $1,857.19 | $630.00 | $850.00 | $650.00 | $1,041.00 |
| 0033 | Cracks and joints in asphalt pavement, rout and seal (408-07478) | TON | 1 | $1,750.00 | $3,284.85 | $7,200.00 | $5,500.00 | $10,000 | $1,561.00 |
| 0034 | Guardrail terminal system, W-beam curved, type 1 (601-01700) | EACH | 1 | $3,075.00 | $3,450.00 | $3,450.00 | $2,875.00 | $3,200.00 | $2,992.00 |
| 0035 | Guardrail, remove (601-02241) | LFT | 276 | $6.00 | $4.00 | $4.00 | $5.00 | $7.00 | $5.20 |
| 0036 | Guardrail, MGS W-beam, 6 FT 3 in. spacing (601-12281) | LFT | 188 | $23.00 | $21.00 | $21.00 | $20.00 | $22.00 | $21.00 |
| 0037 | Guardrail, MGS, long span, type 1 (601-12287) | EACH | 2 | $1,780.00 | $1,690.00 | $1,690.00 | $1,650.00 | $1,850.00 | $1,717.00 |
| 0038 | Guardrail height transition, MGS (601-12289) | EACH | 1 | $915.00 | $1,275.00 | $1,275.00 | $862.00 | $975.00 | $897.00 |
| 0039 | Guardrail end treatment, type OS (601-94689) | EACH | 3 | $3,100.00 | $3,475.00 | $3,475.00 | $2,900.00 | $3,200.00 | $3,018.00 |
| 0040 | Fence, farm field, 47 in. (603-06040) | LFT | 509 | $23.60 | $16.00 | $16.00 | $21.00 | $20.00 | $22.00 |
| 0041 | Milled HMA corrugations, sinusoidal (606-12400) | LFT | 918 | $10.00 | $2.62 | $2.00 | $6.50 | $15.00 | $2.10 |
| 0042 | Right-of-way marker (615-06490) | EACH | 9 | $200.00 | $150.00 | $150.00 | $180.00 | $215.00 | $187.00 |
| 0043 | Monument, type B (615-06505) | EACH | 2 | $1,610.00 | $1,250.00 | $1,250.00 | $1,500.00 | $1,600.00 | $1,561.00 |
| 0044 | Riprap, class 1 (616-05688) | TON | 31 | $100.00 | $83.48 | $120.00 | $160.00 | $100.00 | $128.00 |
| 0045 | Riprap, revetment (616-06405) | TON | 302 | $89.00 | $53.77 | $48.00 | $60.00 | $90.00 | $74.00 |
| 0046 | Geotextile for riprap, type 1A (616-12246) | SYS | 433 | $6.00 | $3.31 | $4.70 | $3.00 | $6.00 | $7.10 |
| 0047 | Mobilization and demobilization for seeding (621-01004) | EACH | 1 | $400.00 | $224.01 | $1,500.00 | $1,000.00 | $1,100.00 | $1,561.00 |
| 0048 | Erosion control blanket (621-02770) | SYS | 2,148 | $2.50 | $2.49 | $2.25 | $2.00 | $2.00 | $2.30 |
| 0049 | Seed mixture, native (621-03909) | LBS | 3 | $750.00 | $236.33 | $800.00 | $1,000.00 | $1,130.00 | $833.00 |
| 0050 | Fertilizer, for permanent seeding , for permanent seeding (621-06545) | TON | 1 | $150.00 | $1,811.66 | $10.00 | $50.00 | $110.00 | $10.00 |
| 0051 | Seed mixture, type R (621-06553) | LBS | 81 | $32.50 | $10.64 | $12.00 | $40.00 | $45.00 | $12.00 |
| 0052 | Sodding (621-06574) | SYS | 107 | $35.00 | $16.42 | $40.00 | $40.00 | $45.00 | $42.00 |
| 0053 | Computer system equipment (628-11976) | EACH | 4 | $400.00 | $897.97 | $600.00 | $900.00 | $840.00 | $947.00 |
| 0054 | Field office, type D (628-12683) | MOS | 12 | $1,890.00 | $1,474.53 | $3,000.00 | $3,600.00 | $1,975.00 | $4,455.00 |
| 0055 | Waterproofing membrane type 2 (714-000086) | SFT | 1,410 | $5.00 | $7.05 | $4.54 | $4.40 | $4.00 | $4.40 |
| 0056 | Structure, reinforced concrete, box sections, 8 FT X 6 FT (714-11179) | LFT | 51 | $1,400.00 | $2,351.28 | $1,500.00 | $1,870.00 | $2,462.00 | $1,341.00 |
| 0057 | Pipe, type 3, circular, diameter 15 in. (715-05169) | LFT | 50 | $45.00 | $152.32 | $78.50 | $102.00 | $112.00 | $128.00 |
| 0058 | Road closure sign assembly (801-04308) | EACH | 6 | $185.00 | $389.68 | $345.00 | $390.00 | $225.00 | $359.00 |
| 0059 | Detour route marker assembly (801-06625) | EACH | 45 | $90.00 | $116.57 | $135.55 | $117.00 | $98.00 | $141.00 |
| 0060 | Construction sign, type A (801-06640) | EACH | 16 | $210.00 | $243.69 | $155.55 | $245.00 | $155.00 | $162.00 |
| 0061 | Maintaining traffic (801-06775) | LS | 1 | $21,000 | $12,306 | $10,762 | $9,649.00 | $2,850.00 | $71,500 |
| 0062 | Barricade, type III-A (801-07118) | LFT | 80 | $17.00 | $12.69 | $16.75 | $13.00 | $18.00 | $17.00 |
| 0063 | Barricade, type III-B (801-07119) | LFT | 136 | $17.00 | $12.69 | $16.75 | $13.00 | $19.00 | $17.00 |
| 0064 | Line, multi-component, solid, white, 6 in. (808-10049) | LFT | 612 | $5.25 | $6.52 | $1.00 | $6.55 | $7.00 | $1.00 |
| 0065 | Line, multi-component, solid, yellow, 6 in. (808-10057) | LFT | 306 | $5.25 | $6.52 | $1.00 | $6.55 | $7.00 | $1.00 |
| 0066 | Grooving for pavement markings (808-12032) | LFT | 995 | $2.20 | $5.35 | $1.00 | $5.35 | $6.00 | $1.00 |
| 0067 | Line, multi-component, broken, yellow, 6 in. (808-12841) | LFT | 77 | $5.25 | $6.52 | $1.00 | $6.55 | $7.00 | $1.00 |
| 0068 | Snowplowable raised pavement marker, remove (808-75996) | EACH | 4 | $20.00 | $23.61 | $75.00 | $30.00 | $150.00 | $78.00 |
| 0069 | Pavement removal (202-02240) | SYS | 380 | $15.00 | $30.19 | $35.40 | $26.00 | $26.00 | $24.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of August 6, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.