INDOT contract R-43811-A bid tabulation
SMALL STRUCTURE REPLACEMENT. Let by Indiana DOT on November 13, 2025, Jay, Fort Wayne. 7 bids received; low bid $392,730 by Calumet Civil Contractors Inc.
- Owner
- Indiana DOT
- Letting
- 13 NOV 2025
- Pay items
- 51
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Calumet Civil Contractors Inc | $392,730 | Low |
| 2 | 3D Company Inc | $425,240 | +8.0% |
| 3 | Morphey Construction Inc. | $439,000 | +12% |
| 4 | Brooks Construction Company Inc | $473,453 | +21% |
| 5 | Milestone Contractors LP | $551,913 | +41% |
| 6 | Yarberry Companies Inc | $576,177 | +47% |
| 7 | Indiana Earthworks, LLC | $606,400 | +54% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Calumet Civil Contractors Inc | 2. 3D Company Inc | 3. Morphey Construction Inc. | 4. Brooks Construction Company Inc | 5. Milestone Contractors LP | 6. Yarberry Companies Inc |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $4,000.00 | $7,805.00 | $4,000.00 | $15,000 | $10,000 | $20,000 |
| 0002 | Inspection hole, deeper than 3 FT (107-09358) | EACH | 4 | $250.00 | $910.00 | $400.00 | $1,000.00 | $1,000.00 | $900.00 |
| 0003 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, HMA (109-08440) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Payment adjustment, PG asphalt binder (109-09489) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0010 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0011 | Mobilization and demobilization (110-01001) | LS | 1 | $11,558 | $31,450 | $21,950 | $23,000 | $27,596 | $27,000 |
| 0012 | Clearing right-of-way (201-52370) | LS | 1 | $5,000.00 | $13,410 | $17,560 | $18,500 | $22,077 | $30,000 |
| 0013 | Pipe, remove (202-96133) | LFT | 81 | $75.00 | $48.62 | $70.00 | $80.00 | $300.00 | $200.00 |
| 0014 | Excavation, common (203-02000) | CYS | 462 | $92.00 | $52.42 | $75.00 | $75.00 | $175.00 | $100.00 |
| 0015 | Excavation, waterway (203-51223) | CYS | 60 | $95.00 | $155.87 | $125.00 | $125.00 | $135.00 | $100.00 |
| 0016 | Temporary turbidity curtain (205-09387) | LFT | 75 | $45.00 | $65.62 | $150.00 | $35.00 | $55.00 | $75.00 |
| 0017 | Stormwater management budget (205-12108) | DOL | 92,078 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0018 | Stormwater management implementation (205-12616) | LS | 1 | $29,200 | $6,770.00 | $500.00 | $25,000 | $1,500.00 | $25,000 |
| 0019 | Subgrade treatment, type IC (207-09935) | SYS | 72 | $80.00 | $72.60 | $60.00 | $40.00 | $60.00 | $70.00 |
| 0020 | Structure backfill, type 2 (211-09265) | CYS | 95 | $102.00 | $55.60 | $60.00 | $70.00 | $170.00 | $115.00 |
| 0021 | Structure backfill, type 3 (211-09266) | CYS | 13 | $102.00 | $56.90 | $70.00 | $115.00 | $450.00 | $175.00 |
| 0022 | Geotextile for pavement, type 2A (214-12238) | SYS | 94 | $13.00 | $12.33 | $7.00 | $6.25 | $15.00 | $25.00 |
| 0023 | Geotextile for pavement, type 2B (214-12239) | SYS | 72 | $24.00 | $19.70 | $7.00 | $5.25 | $22.00 | $25.00 |
| 0024 | Compacted aggregate, no. 53 (303-01180) | TON | 122 | $70.00 | $44.52 | $55.00 | $48.00 | $70.00 | $65.00 |
| 0025 | Milling, asphalt, 1 1/2 in. (306-08034) | SYS | 320 | $22.00 | $18.70 | $22.00 | $8.00 | $13.25 | $25.00 |
| 0027 | QC/QA-HMA, 3, 58H, intermediate, 19.0 MM (401-000041) | TON | 10 | $534.00 | $183.25 | $150.00 | $155.00 | $150.00 | $250.00 |
| 0028 | QC/QA-HMA, 3, 58H, base, 25.0 MM (401-000050) | TON | 32 | $234.00 | $170.70 | $150.00 | $150.00 | $150.00 | $200.00 |
| 0029 | Joint adhesive (401-11526) | LFT | 120 | $3.00 | $1.95 | $1.75 | $1.75 | $1.75 | $10.00 |
| 0030 | Asphalt for tack coat (406-05520) | TON | 1 | $1,425.00 | $550.00 | $500.00 | $500.00 | $500.00 | $1,500.00 |
| 0031 | Temporary fence (603-97461) | LFT | 120 | $61.00 | $34.46 | $60.50 | $6.50 | $20.00 | $67.00 |
| 0032 | Riprap, class 1 (616-05688) | TON | 90 | $110.00 | $134.66 | $195.00 | $105.00 | $220.00 | $300.00 |
| 0033 | Riprap, revetment (616-06405) | TON | 190 | $100.00 | $127.45 | $185.00 | $300.00 | $97.00 | $200.00 |
| 0034 | Geotextile for riprap, type 1A (616-12246) | SYS | 292 | $6.00 | $4.80 | $5.00 | $7.00 | $4.50 | $25.00 |
| 0035 | Geotextile for riprap, type 2A (616-12248) | SYS | 165 | $6.50 | $7.91 | $5.00 | $5.00 | $8.00 | $25.00 |
| 0036 | Mobilization and demobilization for seeding (621-01004) | EACH | 3 | $725.00 | $560.00 | $725.00 | $800.00 | $800.00 | $750.00 |
| 0037 | Mulched seeding, type R (621-06559) | SYS | 2,773 | $7.00 | $2.99 | $8.00 | $3.25 | $3.25 | $2.00 |
| 0038 | Pipe, type 1, circular, diameter 60 in. (715-05133) | LFT | 75 | $485.00 | $568.25 | $800.00 | $450.00 | $700.00 | $573.00 |
| 0039 | Concrete anchor, diameter 60 in. (715-05841) | EACH | 2 | $3,326.00 | $8,310.00 | $11,000 | $4,000.00 | $6,700.00 | $9,500.00 |
| 0040 | Construction sign, type C (801-03290) | EACH | 2 | $150.00 | $165.00 | $150.00 | $246.00 | $150.00 | $200.00 |
| 0041 | Road closure sign assembly (801-04308) | EACH | 4 | $150.00 | $165.00 | $150.00 | $308.00 | $150.00 | $200.00 |
| 0042 | Detour route marker assembly (801-06625) | EACH | 36 | $75.00 | $83.00 | $75.00 | $167.00 | $75.00 | $100.00 |
| 0043 | Construction sign, type A (801-06640) | EACH | 19 | $150.00 | $165.00 | $150.00 | $231.00 | $150.00 | $175.00 |
| 0044 | Construction sign, type B (801-06645) | EACH | 3 | $75.00 | $83.00 | $75.00 | $109.00 | $75.00 | $100.00 |
| 0045 | Maintaining traffic (801-06775) | LS | 1 | $10,000 | $40,100 | $13,038 | $64,976 | $22,860 | $45,000 |
| 0046 | Barricade, type III-A (801-07118) | LFT | 80 | $12.00 | $13.20 | $12.00 | $16.56 | $12.00 | $15.00 |
| 0047 | Barricade, type III-B (801-07119) | LFT | 40 | $12.00 | $13.20 | $12.00 | $16.56 | $12.00 | $15.00 |
| 0048 | Portable changeable message sign (801-11642) | EACH | 2 | $2,000.00 | $2,200.00 | $2,000.00 | $2,960.00 | $3,000.00 | $2,300.00 |
| 0049 | Line, thermoplastic, solid, white, 6 in. (808-75043) | LFT | 240 | $4.00 | $4.40 | $4.00 | $2.40 | $4.00 | $7.00 |
| 0050 | Line, thermoplastic, broken, yellow, 6 in. (808-96078) | LFT | 120 | $4.00 | $4.40 | $4.00 | $2.40 | $4.00 | $7.00 |
| 0051 | Pump around (205-11626) | EACH | 1 | $7,000.00 | $22,125 | $10,000 | $3,500.00 | $65,000 | $30,000 |
| 0052 | QC/QA-HMA, 3, 58H, surface, 9.5 MM (401-000005) | TON | 27 | $300.00 | $177.26 | $155.00 | $155.00 | $155.00 | $295.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of November 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.