INDOT contract R-43902-A bid tabulation
SMALL STRUCTURE PIPE LINING. Let by Indiana DOT on November 13, 2025, Fulton, LaPorte. 7 bids received; low bid $1,019,825 by Rieth-Riley Construction Co., Inc..
- Owner
- Indiana DOT
- Letting
- 13 NOV 2025
- Pay items
- 52
- Data through
- 05 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rieth-Riley Construction Co., Inc. | $1,019,825 | Low |
| 2 | Morphey Construction Inc. | $1,043,000 | +2.0% |
| 3 | E & B Paving LLC | $1,116,494 | +9.0% |
| 4 | Temple & Temple Excavating & Paving Inc | $1,144,320 | +12% |
| 5 | Yarberry Companies Inc | $1,188,823 | +17% |
| 6 | Milestone Contractors LP | $1,194,750 | +17% |
| 7 | F H Paschen S N Nielsen & Associates LLC | $1,322,000 | +30% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rieth-Riley Construction Co., Inc. | 2. Morphey Construction Inc. | 3. E & B Paving LLC | 4. Temple & Temple Excavating & Paving Inc | 5. Yarberry Companies Inc | 6. Milestone Contractors LP |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Construction engineering (105-06845) | LS | 1 | $4,494.00 | $5,000.00 | $10,000 | $9,000.00 | $15,000 | $56,700 |
| 0002 | Liquidated damages (109-08359) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0003 | Contract liens (109-08360) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0004 | Quality adjustments, temporary traffic control devices (109-08443) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0005 | Quality adjustments, failed materials (109-08444) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0006 | Project estimate adjustment (109-08463) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Quality adjustments, failure to maintain temporary erosion and sediment control measures (109-11362) | DOL | 1 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0008 | Mobilization and demobilization (110-01001) | LS | 1 | $83,075 | $52,150 | $55,825 | $79,182 | $60,000 | $59,389 |
| 0009 | Clearing right-of-way (201-52370) | LS | 1 | $9,994.00 | $20,860 | $15,000 | $19,000 | $25,000 | $84,090 |
| 0010 | Concrete, remove (202-93615) | SYS | 1 | $1,442.00 | $50.00 | $1,000.00 | $2,775.00 | $500.00 | $1,200.00 |
| 0011 | Fence, farm field, remove (202-99187) | LFT | 100 | $20.00 | $3.00 | $12.00 | $15.00 | $30.00 | $12.00 |
| 0012 | Excavation, common (203-02000) | CYS | 18 | $500.00 | $150.00 | $300.00 | $120.00 | $200.00 | $230.00 |
| 0013 | Excavation, unclassified (203-02020) | CYS | 8 | $215.00 | $250.00 | $450.00 | $300.00 | $200.00 | $320.00 |
| 0014 | Borrow (203-02070) | CYS | 4 | $600.00 | $150.00 | $500.00 | $580.00 | $150.00 | $709.00 |
| 0015 | Pump around (205-11626) | EACH | 3 | $10,000 | $5,000.00 | $5,000.00 | $20,000 | $10,000 | $1.00 |
| 0016 | Stormwater management budget (205-12108) | DOL | 24,845 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0017 | Stormwater management implementation (205-12616) | LS | 1 | $5,000.00 | $500.00 | $30,000 | $20,000 | $35,000 | $16,500 |
| 0018 | Structure backfill, type 2 (211-09265) | CYS | 34 | $430.00 | $70.00 | $200.00 | $75.00 | $90.00 | $270.00 |
| 0019 | Compacted aggregate, no. 5 (301-12232) | CYS | 8 | $400.00 | $175.00 | $200.00 | $80.00 | $200.00 | $386.00 |
| 0020 | Compacted aggregate, no. 73 (303-07449) | TON | 27 | $150.00 | $105.00 | $170.00 | $75.00 | $90.00 | $300.00 |
| 0021 | Fence, farm field, 47 in. (603-06040) | LFT | 100 | $36.00 | $83.00 | $83.00 | $90.00 | $40.00 | $36.00 |
| 0022 | Riprap, class 2 (616-05689) | TON | 165 | $203.00 | $200.00 | $250.00 | $150.00 | $250.00 | $322.00 |
| 0023 | Riprap, revetment (616-06405) | TON | 30 | $253.00 | $135.00 | $155.00 | $80.00 | $200.00 | $300.00 |
| 0024 | Geotextile for riprap, type 2B (616-12249) | SYS | 310 | $8.00 | $4.00 | $12.00 | $12.00 | $25.00 | $20.00 |
| 0025 | Mobilization and demobilization for seeding (621-01004) | EACH | 5 | $500.00 | $425.00 | $425.00 | $500.00 | $700.00 | $425.00 |
| 0026 | Mulched seeding, type R (621-06559) | SYS | 5,109 | $1.25 | $7.00 | $3.22 | $5.00 | $2.00 | $3.22 |
| 0027 | Field office, type C (628-09403) | MOS | 6 | $2,000.00 | $3,000.00 | $4,400.00 | $4,600.00 | $3,000.00 | $2,500.00 |
| 0028 | Temporary shoring (702-04325) | LS | 1 | $12,245 | $85,000 | $65,000 | $6,500.00 | $30,000 | $21,000 |
| 0029 | Concrete, A, substructure (702-51005) | CYS | 8 | $4,500.00 | $3,100.00 | $5,500.00 | $4,175.00 | $4,500.00 | $4,110.00 |
| 0030 | Concrete, B, footings (702-51015) | CYS | 13 | $900.00 | $1,400.00 | $2,500.00 | $1,090.00 | $750.00 | $1,085.00 |
| 0031 | Reinforcing bars (703-06028) | LBS | 2,124 | $4.00 | $5.00 | $3.00 | $3.00 | $7.00 | $3.50 |
| 0032 | Stud shear connectors (711-96800) | EACH | 19 | $100.00 | $20.00 | $94.00 | $52.00 | $150.00 | $110.00 |
| 0033 | Concrete anchor, diameter 48 in. (715-06004) | EACH | 2 | $8,000.00 | $10,000 | $9,500.00 | $4,500.00 | $7,000.00 | $12,700 |
| 0034 | Pipe extension, circular, diameter 8 in. , corrugated plastic pipe (715-06051) | LFT | 5 | $50.00 | $225.00 | $300.00 | $180.00 | $70.00 | $297.00 |
| 0035 | Concrete anchor, min. area 8.9 SFT (715-06501) | EACH | 2 | $8,000.00 | $10,000 | $9,000.00 | $4,500.00 | $10,000 | $12,700 |
| 0036 | Pipe extension, circular, diameter 4 in. , corrugated plastic pipe (715-06561) | LFT | 5 | $50.00 | $215.00 | $300.00 | $180.00 | $70.00 | $280.00 |
| 0037 | Pipe extension, circular, diameter 6 in. , corrugated plastic pipe (715-06566) | LFT | 5 | $50.00 | $220.00 | $300.00 | $180.00 | $70.00 | $280.00 |
| 0038 | Pipe liner, cured-in- place, 48 in. (725-08296) | LFT | 223 | $650.00 | $665.00 | $580.21 | $813.00 | $812.00 | $590.00 |
| 0039 | Pipe liner, cured-in- place, 72 in. (725-10203) | LFT | 86 | $1,850.00 | $1,825.00 | $1,644.51 | $2,100.00 | $2,323.00 | $1,655.00 |
| 0040 | Liner pipe, thermoplastic, deformed, 4.7-5.0 SFT (725-11013) | LFT | 216 | $875.00 | $650.00 | $850.00 | $790.00 | $656.00 | $930.76 |
| 0041 | Road closure sign assembly (801-04308) | EACH | 2 | $325.00 | $325.00 | $325.00 | $176.00 | $175.00 | $325.00 |
| 0042 | Temporary transverse pavement marking, removable, 24 in. (801-06218) | LFT | 24 | $12.00 | $12.00 | $23.92 | $12.00 | $12.00 | $12.00 |
| 0043 | Construction sign, type A (801-06640) | EACH | 74 | $170.00 | $170.00 | $170.00 | $205.00 | $225.00 | $170.00 |
| 0044 | Flashing arrow sign (801-06710) | DAY | 40 | $15.00 | $15.00 | $15.00 | $29.00 | $40.00 | $15.00 |
| 0045 | Maintaining traffic (801-06775) | LS | 1 | $25,000 | $16,680 | $41,301 | $14,000 | $55,000 | $12,000 |
| 0046 | Energy absorbing terminal, CZ, TL-3 (801-07024) | EACH | 6 | $2,000.00 | $4,600.00 | $4,600.00 | $5,400.00 | $8,300.00 | $7,500.00 |
| 0047 | Barricade, type III-B (801-07119) | LFT | 132 | $16.00 | $16.00 | $16.00 | $14.00 | $15.00 | $16.00 |
| 0048 | Temporary traffic barrier, type 2 (801-08401) | LFT | 2,064 | $35.00 | $41.00 | $34.00 | $45.00 | $38.00 | $48.00 |
| 0049 | Portable signal (801-12081) | LS | 1 | $5,000.00 | $6,500.00 | $6,000.00 | $13,500 | $6,600.00 | $6,000.00 |
| 0050 | Driveway assistance device (801-12482) | EACH | 1 | $1,500.00 | $2,500.00 | $1,750.00 | $5,725.00 | $1,925.00 | $1,750.00 |
| 0051 | Temporary worksite speed limit sign assembly, intermittent (801-12930) | EACH | 16 | $1,213.00 | $1,213.00 | $1,213.00 | $1,175.00 | $1,100.00 | $1,213.00 |
| 0052 | Temporary pavement marking, removable, 6 in. (801-06209) | LFT | 4,805 | $1.75 | $1.75 | $1.75 | $2.00 | $2.20 | $1.75 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from INDOT's tabulation for this contract. INDOT Unit Tab Results (AASHTOWare Tabulation of Bids PDFs), one per letting, January 2022 to November 2026. Bids that did not match their published total, mostly large contracts with alternate sets, are left out.
Every contract let that day: INDOT letting of November 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.