KYTC contract 25-1037 bid tabulation
BRIDGE WITH GRADE, DRAIN & SURFACE CR-1169. Let by Kentucky Transportation Cabinet on December 11, 2025. 5 bids received; low bid $1,241,796 by Kay & Kay Contracting LLC, -17% against the engineer's estimate of $1,495,925.
- Owner
- Kentucky Transportation Cabinet
- Letting
- 11 DEC 2025
- Pay items
- 75
- Data through
- 22 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kay & Kay Contracting LLC | $1,241,796 | Low | -17% |
| 2 | Jave LLC | $1,245,658 | 0.0% | -17% |
| 3 | Frederick & May Construction Co | $1,418,175 | +14% | -5.0% |
| 4 | Bush & Burchett Inc | $1,430,126 | +15% | -4.0% |
| 5 | Adams Contracting LLC | $1,674,954 | +35% | +12% |
Engineer's estimate: $1,495,925.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kay & Kay Contracting LLC | 2. Jave LLC | 3. Frederick & May Construction Co | 4. Bush & Burchett Inc | 5. Adams Contracting LLC |
|---|---|---|---|---|---|---|---|---|
| 0010 | Electronic delivery MGMT system - agg | LS A A | 1 | $10.00 | $1.03 | $500.00 | $1,000.00 | $2,000.00 |
| 0020 | Dga base | TON A A | 653 | $60.95 | $41.20 | $55.00 | $62.00 | $57.00 |
| 0030 | Traffic bound base | TON A A | 67 | $50.90 | $51.50 | $50.00 | $62.00 | $61.00 |
| 0040 | Crushed aggregate size no 2 | TON A A | 3,726 | $49.65 | $41.20 | $44.00 | $58.00 | $44.00 |
| 0050 | Asphalt seal aggregate | TON A A | 15.40 | $250.00 | $257.50 | $250.00 | $200.00 | $440.00 |
| 0060 | Asphalt seal coat | TON A A | 1.80 | $450.00 | $463.50 | $450.00 | $1,500.00 | $2,200.00 |
| 0070 | CL2 asph base 1.00D PG64-22 | TON A A | 244 | $150.00 | $154.50 | $150.00 | $150.00 | $170.00 |
| 0080 | CL2 asph surf 0.38D PG64-22 | TON A A | 86 | $200.00 | $206.00 | $200.00 | $200.00 | $220.00 |
| 0090 | Asphalt material for tack | TON A A | 0.50 | $10.00 | $10.30 | $10.00 | $10.00 | $1,100.00 |
| 0100 | Delineator for guardrail BI directional white | EACH A A | 21 | $12.99 | $13.38 | $12.99 | $12.99 | $15.00 |
| 0110 | Remove pavement | SQYD A A | 81 | $50.80 | $10.30 | $15.00 | $20.00 | $58.00 |
| 0120 | Temp ditch | LF A A | 340 | $10.00 | $2.06 | $1.00 | $3.00 | $21.00 |
| 0130 | Clean temp ditch | LF A A | 170 | $5.00 | $1.03 | $0.10 | $3.00 | $21.00 |
| 0140 | Roadway excavation | CUYD A A | 1,914 | $32.20 | $24.72 | $30.00 | $40.00 | $44.00 |
| 0150 | Granular embankment | CUYD A A | 234 | $61.80 | $66.95 | $90.00 | $65.00 | $76.00 |
| 0160 | Guardrail-steel W beam-S face | LF A A | 443.75 | $28.03 | $28.87 | $28.03 | $28.03 | $31.00 |
| 0170 | Guardrail end treatment type 7 | EACH A A | 4 | $1,674.59 | $1,724.83 | $1,674.59 | $1,674.59 | $1,900.00 |
| 0180 | Extra length guardrail post | EACH A A | 71 | $16.25 | $16.74 | $16.25 | $16.25 | $18.00 |
| 0190 | Witness post | EACH A A | 16 | $121.34 | $54.99 | $275.00 | $121.34 | $140.00 |
| 0200 | Clearing and grubbing | LS A A | 1 | $20,500 | $7,725.00 | $45,040 | $8,000.00 | $35,000 |
| 0210 | Fabric-geotextile class 2 | SQYD A A | 785 | $2.00 | $3.09 | $2.75 | $5.00 | $4.00 |
| 0220 | Fabric-geotextile class 1A | SQYD A A | 5,433 | $4.00 | $5.15 | $5.00 | $5.00 | $5.00 |
| 0230 | Maintain & control traffic | LS A A | 1 | $10,500 | $11,350 | $17,000 | $60,000 | $30,000 |
| 0240 | Portable changeable message sign | EACH A A | 4 | $2,226.00 | $4,914.00 | $4,500.00 | $2,000.00 | $4,900.00 |
| 0250 | Temp silt fence | LF A A | 340 | $3.50 | $3.61 | $3.00 | $4.00 | $4.25 |
| 0260 | Silt trap type A | EACH A A | 1 | $500.00 | $309.00 | $100.00 | $250.00 | $200.00 |
| 0270 | Silt trap type B | EACH A A | 1 | $500.00 | $309.00 | $100.00 | $250.00 | $150.00 |
| 0280 | Silt trap type C | EACH A A | 1 | $500.00 | $309.00 | $100.00 | $300.00 | $500.00 |
| 0290 | Clean silt trap type A | EACH A A | 1 | $500.00 | $51.50 | $50.00 | $240.00 | $20.00 |
| 0300 | Clean silt trap type B | EACH A A | 1 | $80.00 | $51.50 | $50.00 | $400.00 | $20.00 |
| 0310 | Clean silt trap type C | EACH A A | 1 | $80.00 | $51.50 | $50.00 | $400.00 | $20.00 |
| 0320 | Staking | LS A A | 1 | $5,000.00 | $7,840.00 | $12,500 | $25,000 | $15,000 |
| 0330 | Remove structure | LS A A | 1 | $35,800 | $29,718 | $30,000 | $30,000 | $125,000 |
| 0340 | Conc barrier wall type 9T | LF A A | 656 | $60.00 | $110.67 | $100.00 | $20.00 | $100.00 |
| 0350 | Temp signal | LS A A | 1 | $12,402 | $23,874 | $37,500 | $4,000.00 | $28,000 |
| 0360 | Erosion control blanket | SQYD A A | 1,302 | $2.00 | $2.06 | $2.00 | $2.00 | $2.25 |
| 0370 | Temp mulch | SQYD A A | 2,935 | $0.32 | $0.33 | $0.32 | $0.32 | $0.40 |
| 0380 | Temp seeding and protection | SQYD A A | 2,201 | $0.34 | $0.35 | $0.34 | $0.34 | $0.40 |
| 0390 | Initial fertilizer | TON A A | 1 | $1,310.54 | $1,349.86 | $1,310.54 | $1,310.54 | $1,500.00 |
| 0400 | Maintenance fertilizer | TON A A | 1 | $1,310.54 | $1,349.86 | $1,310.54 | $1,310.54 | $1,500.00 |
| 0410 | Seeding and protection | SQYD A A | 1,346 | $0.88 | $0.91 | $0.88 | $0.88 | $1.00 |
| 0420 | Agricultural limestone | TON A A | 2 | $64.74 | $66.68 | $64.74 | $64.74 | $77.00 |
| 0430 | Pave striping-temp paint-6 in | LF A A | 2,748 | $0.65 | $1.24 | $0.65 | $1.50 | $0.70 |
| 0440 | Pave marking-thermo stop bar-24IN | LF A A | 9 | $15.00 | $15.45 | $15.00 | $25.00 | $17.00 |
| 0450 | Sawcut pavement | LF A A | 103 | $5.00 | $5.85 | $5.00 | $2.00 | $5.00 |
| 0460 | Temp crash cushion | EACH A A | 2 | $9,179.05 | $3,100.50 | $9,179.05 | $9,179.05 | $11,000 |
| 0470 | Remove sign | EACH A A | 1 | $12.01 | $12.37 | $12.01 | $12.01 | $13.00 |
| 0480 | Pave mark temp paint stop bar-24 in | LF A A | 60 | $10.00 | $10.30 | $10.00 | $25.00 | $11.00 |
| 0490 | R/W monument type 3 | EACH A A | 16 | $137.63 | $343.98 | $275.00 | $137.63 | $150.00 |
| 0500 | Culvert pipe-24 in | LF A A | 51 | $135.00 | $139.05 | $200.00 | $212.00 | $220.00 |
| 0510 | Perforated pipe-6 in | LF A A | 19 | $55.30 | $36.05 | $20.00 | $3.00 | $50.00 |
| 0520 | Non-perforated pipe-6 in | LF A A | 8 | $66.00 | $39.14 | $20.00 | $3.00 | $75.00 |
| 0530 | Perf pipe headwall TY 1-6 in | EACH A A | 1 | $1,050.00 | $1,030.00 | $800.00 | $1,800.00 | $1,500.00 |
| 0540 | S & F box inlet-outlet-24 in | EACH A A | 2 | $3,900.00 | $4,635.00 | $5,000.00 | $7,000.00 | $5,500.00 |
| 0550 | Structure granular backfill | CUYD A A | 302 | $71.00 | $130.53 | $90.00 | $65.00 | $130.00 |
| 0560 | Mobilization | LS A A | 1 | $58,000 | $50,770 | $55,000 | $66,000 | $77,500 |
| 0570 | Armored edge for concrete | LF A A | 48 | $104.00 | $96.28 | $150.00 | $100.00 | $98.00 |
| 0580 | Foundation preparation | LS A A | 1 | $48,500 | $16,544 | $65,000 | $100,000 | $50,000 |
| 0590 | Cyclopean stone rip rap | TON A A | 768 | $76.10 | $49.96 | $70.00 | $60.00 | $56.00 |
| 0600 | Test piles | LF A A | 51 | $115.00 | $224.64 | $160.00 | $200.00 | $350.00 |
| 0610 | Piles-steel HP12X53 | LF A A | 225 | $110.00 | $198.90 | $150.00 | $130.00 | $400.00 |
| 0620 | Pile points-12 in | EACH A A | 12 | $156.00 | $148.59 | $200.00 | $150.00 | $150.00 |
| 0630 | Concrete-class A | CUYD A A | 64 | $1,100.00 | $1,436.76 | $925.00 | $1,200.00 | $1,600.00 |
| 0640 | Concrete-class AA | CUYD A A | 54.10 | $1,250.00 | $1,515.15 | $1,825.00 | $1,600.00 | $2,300.00 |
| 0650 | Mechanical reinf coupler #5 epoxy coated | EACH A A | 16 | $131.80 | $86.58 | $150.00 | $50.00 | $170.00 |
| 0660 | Mechanical reinf coupler #6 epoxy coated | EACH A A | 2 | $240.00 | $97.11 | $150.00 | $100.00 | $180.00 |
| 0670 | Steel reinforcement-epoxy coated | LB A A | 10,158 | $3.10 | $2.97 | $4.00 | $2.50 | $2.25 |
| 0680 | Precast PC box beam CB27-48 | LF A A | 543 | $340.00 | $346.32 | $400.00 | $400.00 | $355.00 |
| 0690 | Concrete sealing | SQFT A A | 3,093 | $2.00 | $3.52 | $4.00 | $2.00 | $2.00 |
| 0700 | Mechanical reinf coupler #8-epoxy coated | EACH A A | 9 | $204.50 | $148.59 | $200.00 | $120.00 | $190.00 |
| 0710 | Rail system side mounted MGS | LF A A | 168 | $192.68 | $198.46 | $192.68 | $192.68 | $220.00 |
| 0720 | SBM alum sheet signs .080 in | SQFT A A | 6.25 | $34.81 | $35.85 | $34.81 | $34.81 | $39.00 |
| 0730 | Steel post type 1 | LF A A | 10.50 | $26.95 | $29.15 | $28.30 | $28.30 | $32.00 |
| 0740 | Barcode sign inventory | EACH A A | 1 | $48.03 | $49.47 | $48.03 | $48.03 | $52.00 |
| 0750 | Demobilization | LS A A | 1 | $18,352 | $18,409 | $20,960 | $22,500 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.
Every contract let that day: KYTC letting of December 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.