KYTC contract 25-1037 bid tabulation

BRIDGE WITH GRADE, DRAIN & SURFACE CR-1169. Let by Kentucky Transportation Cabinet on December 11, 2025. 5 bids received; low bid $1,241,796 by Kay & Kay Contracting LLC, -17% against the engineer's estimate of $1,495,925.

Owner
Kentucky Transportation Cabinet
Letting
11 DEC 2025
Pay items
75
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kay & Kay Contracting LLC$1,241,796Low-17%
2Jave LLC$1,245,6580.0%-17%
3Frederick & May Construction Co$1,418,175+14%-5.0%
4Bush & Burchett Inc$1,430,126+15%-4.0%
5Adams Contracting LLC$1,674,954+35%+12%
KYTC contract 25-1037: bids by rank

Engineer's estimate: $1,495,925.

Bid tabulation

LinePay itemUnitQuantity1. Kay & Kay Contracting LLC2. Jave LLC3. Frederick & May Construction Co4. Bush & Burchett Inc5. Adams Contracting LLC
0010Electronic delivery MGMT system - aggLS A A1$10.00$1.03$500.00$1,000.00$2,000.00
0020Dga baseTON A A653$60.95$41.20$55.00$62.00$57.00
0030Traffic bound baseTON A A67$50.90$51.50$50.00$62.00$61.00
0040Crushed aggregate size no 2TON A A3,726$49.65$41.20$44.00$58.00$44.00
0050Asphalt seal aggregateTON A A15.40$250.00$257.50$250.00$200.00$440.00
0060Asphalt seal coatTON A A1.80$450.00$463.50$450.00$1,500.00$2,200.00
0070CL2 asph base 1.00D PG64-22TON A A244$150.00$154.50$150.00$150.00$170.00
0080CL2 asph surf 0.38D PG64-22TON A A86$200.00$206.00$200.00$200.00$220.00
0090Asphalt material for tackTON A A0.50$10.00$10.30$10.00$10.00$1,100.00
0100Delineator for guardrail BI directional whiteEACH A A21$12.99$13.38$12.99$12.99$15.00
0110Remove pavementSQYD A A81$50.80$10.30$15.00$20.00$58.00
0120Temp ditchLF A A340$10.00$2.06$1.00$3.00$21.00
0130Clean temp ditchLF A A170$5.00$1.03$0.10$3.00$21.00
0140Roadway excavationCUYD A A1,914$32.20$24.72$30.00$40.00$44.00
0150Granular embankmentCUYD A A234$61.80$66.95$90.00$65.00$76.00
0160Guardrail-steel W beam-S faceLF A A443.75$28.03$28.87$28.03$28.03$31.00
0170Guardrail end treatment type 7EACH A A4$1,674.59$1,724.83$1,674.59$1,674.59$1,900.00
0180Extra length guardrail postEACH A A71$16.25$16.74$16.25$16.25$18.00
0190Witness postEACH A A16$121.34$54.99$275.00$121.34$140.00
0200Clearing and grubbingLS A A1$20,500$7,725.00$45,040$8,000.00$35,000
0210Fabric-geotextile class 2SQYD A A785$2.00$3.09$2.75$5.00$4.00
0220Fabric-geotextile class 1ASQYD A A5,433$4.00$5.15$5.00$5.00$5.00
0230Maintain & control trafficLS A A1$10,500$11,350$17,000$60,000$30,000
0240Portable changeable message signEACH A A4$2,226.00$4,914.00$4,500.00$2,000.00$4,900.00
0250Temp silt fenceLF A A340$3.50$3.61$3.00$4.00$4.25
0260Silt trap type AEACH A A1$500.00$309.00$100.00$250.00$200.00
0270Silt trap type BEACH A A1$500.00$309.00$100.00$250.00$150.00
0280Silt trap type CEACH A A1$500.00$309.00$100.00$300.00$500.00
0290Clean silt trap type AEACH A A1$500.00$51.50$50.00$240.00$20.00
0300Clean silt trap type BEACH A A1$80.00$51.50$50.00$400.00$20.00
0310Clean silt trap type CEACH A A1$80.00$51.50$50.00$400.00$20.00
0320StakingLS A A1$5,000.00$7,840.00$12,500$25,000$15,000
0330Remove structureLS A A1$35,800$29,718$30,000$30,000$125,000
0340Conc barrier wall type 9TLF A A656$60.00$110.67$100.00$20.00$100.00
0350Temp signalLS A A1$12,402$23,874$37,500$4,000.00$28,000
0360Erosion control blanketSQYD A A1,302$2.00$2.06$2.00$2.00$2.25
0370Temp mulchSQYD A A2,935$0.32$0.33$0.32$0.32$0.40
0380Temp seeding and protectionSQYD A A2,201$0.34$0.35$0.34$0.34$0.40
0390Initial fertilizerTON A A1$1,310.54$1,349.86$1,310.54$1,310.54$1,500.00
0400Maintenance fertilizerTON A A1$1,310.54$1,349.86$1,310.54$1,310.54$1,500.00
0410Seeding and protectionSQYD A A1,346$0.88$0.91$0.88$0.88$1.00
0420Agricultural limestoneTON A A2$64.74$66.68$64.74$64.74$77.00
0430Pave striping-temp paint-6 inLF A A2,748$0.65$1.24$0.65$1.50$0.70
0440Pave marking-thermo stop bar-24INLF A A9$15.00$15.45$15.00$25.00$17.00
0450Sawcut pavementLF A A103$5.00$5.85$5.00$2.00$5.00
0460Temp crash cushionEACH A A2$9,179.05$3,100.50$9,179.05$9,179.05$11,000
0470Remove signEACH A A1$12.01$12.37$12.01$12.01$13.00
0480Pave mark temp paint stop bar-24 inLF A A60$10.00$10.30$10.00$25.00$11.00
0490R/W monument type 3EACH A A16$137.63$343.98$275.00$137.63$150.00
0500Culvert pipe-24 inLF A A51$135.00$139.05$200.00$212.00$220.00
0510Perforated pipe-6 inLF A A19$55.30$36.05$20.00$3.00$50.00
0520Non-perforated pipe-6 inLF A A8$66.00$39.14$20.00$3.00$75.00
0530Perf pipe headwall TY 1-6 inEACH A A1$1,050.00$1,030.00$800.00$1,800.00$1,500.00
0540S & F box inlet-outlet-24 inEACH A A2$3,900.00$4,635.00$5,000.00$7,000.00$5,500.00
0550Structure granular backfillCUYD A A302$71.00$130.53$90.00$65.00$130.00
0560MobilizationLS A A1$58,000$50,770$55,000$66,000$77,500
0570Armored edge for concreteLF A A48$104.00$96.28$150.00$100.00$98.00
0580Foundation preparationLS A A1$48,500$16,544$65,000$100,000$50,000
0590Cyclopean stone rip rapTON A A768$76.10$49.96$70.00$60.00$56.00
0600Test pilesLF A A51$115.00$224.64$160.00$200.00$350.00
0610Piles-steel HP12X53LF A A225$110.00$198.90$150.00$130.00$400.00
0620Pile points-12 inEACH A A12$156.00$148.59$200.00$150.00$150.00
0630Concrete-class ACUYD A A64$1,100.00$1,436.76$925.00$1,200.00$1,600.00
0640Concrete-class AACUYD A A54.10$1,250.00$1,515.15$1,825.00$1,600.00$2,300.00
0650Mechanical reinf coupler #5 epoxy coatedEACH A A16$131.80$86.58$150.00$50.00$170.00
0660Mechanical reinf coupler #6 epoxy coatedEACH A A2$240.00$97.11$150.00$100.00$180.00
0670Steel reinforcement-epoxy coatedLB A A10,158$3.10$2.97$4.00$2.50$2.25
0680Precast PC box beam CB27-48LF A A543$340.00$346.32$400.00$400.00$355.00
0690Concrete sealingSQFT A A3,093$2.00$3.52$4.00$2.00$2.00
0700Mechanical reinf coupler #8-epoxy coatedEACH A A9$204.50$148.59$200.00$120.00$190.00
0710Rail system side mounted MGSLF A A168$192.68$198.46$192.68$192.68$220.00
0720SBM alum sheet signs .080 inSQFT A A6.25$34.81$35.85$34.81$34.81$39.00
0730Steel post type 1LF A A10.50$26.95$29.15$28.30$28.30$32.00
0740Barcode sign inventoryEACH A A1$48.03$49.47$48.03$48.03$52.00
0750DemobilizationLS A A1$18,352$18,409$20,960$22,500$25,000
KYTC contract 25-1037: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of December 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy