KYTC contract 25-2986 bid tabulation

BRIDGE SUPERSTRUCTURE REPLACEMENT KY 217 (HWY 217). Let by Kentucky Transportation Cabinet on June 5, 2025. 6 bids received; low bid $367,311 by Kay & Kay Contracting LLC, -36% against the engineer's estimate of $569,899.

Owner
Kentucky Transportation Cabinet
Letting
05 JUN 2025
Pay items
39
Data through
22 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kay & Kay Contracting LLC$367,311Low-36%
2Irvine Contracting Limited Liability Company$397,546+8.0%-30%
3M & M Services Co Inc$411,410+12%-28%
4Bush & Burchett Inc$488,291+33%-14%
5Hinkle Construction Services LLC$562,628+53%-1.0%
6Haydon Bridge Company Inc$793,622+116%+39%
KYTC contract 25-2986: bids by rank

Engineer's estimate: $569,899.

Bid tabulation

LinePay itemUnitQuantity1. Kay & Kay Contracting LLC2. Irvine Contracting Limited Liability Company3. M & M Services Co Inc4. Bush & Burchett Inc5. Hinkle Construction Services LLC6. Haydon Bridge Company Inc
0010Dga baseTON A A65$80.00$75.00$58.00$75.00$79.00$200.00
0020Asphalt seal aggregateTON A A1$3,300.00$3,300.00$1,500.00$3,300.00$3,475.00$4,000.00
0030Asphalt seal coatTON A A0.10$10,000$10,000$5,000.00$10,000$10,525$12,500
0040CL2 asph base 1.00D PG64-22TON A A13$450.00$450.00$155.00$450.00$470.00$550.00
0050CL2 asph surf 0.38D PG64-22TON A A18$460.00$460.00$155.00$460.00$480.00$550.00
0060Asphalt material for tackTON A A0.09$3,500.00$3,500.00$2,500.00$3,500.00$3,685.00$3,500.00
0070Delineator for guardrail BI directional whiteEACH A A7$13.47$13.47$15.00$13.47$14.30$25.00
0080Remove pavementSQYD A A96$49.50$10.00$45.00$15.00$20.00$45.00
0090Roadway excavationCUYD A A20$78.00$95.00$155.00$50.00$150.00$45.00
0100Guardrail-steel W beam-S faceLF A A212.50$34.10$34.10$36.00$34.10$36.00$43.75
0110Guardrail end treatment type 1EACH A A1$3,967.36$3,967.36$4,000.00$3,967.36$4,235.00$5,100.00
0120Guardrail end treatment type 7EACH A A1$1,872.30$1,872.30$2,000.00$1,872.30$2,000.00$2,350.00
0130Guardrail end treatment type 3EACH A A1$1,318.41$1,318.42$1,400.00$1,318.42$1,400.00$1,650.00
0140Guardrail end treatment type 4AEACH A A1$4,132.92$4,132.92$4,200.00$4,132.92$4,415.00$5,250.00
0150Extra length guardrail postEACH A A34$70.47$70.47$80.00$70.47$75.00$70.50
0160Edge keyLF A A60$73.50$73.50$15.00$73.50$77.00$125.00
0170Maintain & control trafficLS A A1$32,500$8,500.00$35,000$30,000$97,950$45,000
0180StakingLS A A1$12,000$1,000.00$15,000$4,000.00$3,015.00$10,000
0190Remove structureLS A A1$14,350$44,285$38,000$99,000$57,000$200,000
0200Temp mulchSQYD A A1,064$0.48$0.48$0.50$0.48$0.50$0.48
0210Temp seeding and protectionSQYD A A806$0.36$0.51$0.50$0.51$0.55$0.51
0220Initial fertilizerTON A A0.04$1,517.12$1,517.12$1,600.00$1,517.12$1,620.00$1,750.00
0230Maintenance fertilizerTON A A0.02$1,517.12$1,517.12$1,600.00$1,517.12$1,620.00$1,750.00
0240Seeding and protectionSQYD A A779$0.83$0.83$0.85$0.83$0.90$0.95
0250Object marker TY 3EACH A A2$44.10$44.10$50.00$44.10$47.00$60.00
0260Remove & relocate signsEACH A A4$356.69$356.69$400.00$356.69$380.00$460.00
0270Longitudinal edge keyLF A A53$98.85$98.85$15.00$98.85$105.00$130.00
0280Structure granular backfillCUYD A A42.70$118.00$166.00$60.00$100.00$150.00$150.00
0290Remove concrete masonryCUYD A A10.80$1,050.00$2,000.00$850.00$50.00$1,225.00$1,050.00
0300Masonry coatingSQYD A A153$14.00$12.00$55.00$5.00$43.00$10.00
0310Armored edge for concreteLF A A48$82.00$100.00$90.00$125.00$90.00$175.00
0320Structure excavation-commonCUYD A A82.80$38.00$65.00$145.00$30.00$65.00$45.00
0330Concrete-class ACUYD A A10.30$1,512.00$2,500.00$1,200.00$3,000.00$3,890.00$9,500.00
0340Concrete-class AACUYD A A28.20$1,080.00$1,200.00$1,450.00$2,500.00$2,725.00$3,750.00
0350Steel reinforcement-epoxy coatedLB A A6,367$2.10$2.70$2.85$2.00$1.80$3.50
0360Precast PC box beam CB12-48LF A A360.50$335.00$355.00$355.00$350.00$350.00$395.00
0370Concrete sealingSQFT A A1,746$2.75$2.00$2.00$3.00$5.50$3.00
0380Rail system side mounted MGSLF A A113$251.98$251.98$285.00$251.98$270.00$325.00
0390DemobilizationLS A A1$5,428.25$6,000.00$6,473.30$7,300.00$8,500.00$11,805
KYTC contract 25-2986: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from KYTC's tabulation for this contract. KYTC Bid Tab Award Sheets, November 2019 to October 2026. Bids that did not match their published total are left out.

Every contract let that day: KYTC letting of June 5, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy