MoDOT contract 260220-G03 bid tabulation
JSR0274-ROUTE I-49-VERNON COUNTY. Let by Missouri DOT on February 20, 2026, Vernon, Southwest. 4 bids received; low bid $3,836,222 by Capital Paving & Construction, LLC.
- Owner
- Missouri DOT
- Letting
- 20 FEB 2026
- Pay items
- 122
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Capital Paving & Construction, LLC | $3,836,222 | Low |
| 2 | Louis-Company, LLC | $4,748,115 | +24% |
| 3 | Concrete Strategies, LLC | $4,793,706 | +25% |
| 4 | West Plains Bridge & Grading, LLC | $5,020,000 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Capital Paving & Construction, LLC | 2. Louis-Company, LLC | 3. Concrete Strategies, LLC | 4. West Plains Bridge & Grading, LLC |
|---|---|---|---|---|---|---|---|
| 0010 | Removal of improvements (2022010) | LS | 1 | $80,000 | $79,724 | $147,050 | $72,000 |
| 0020 | Unclassified excavation (2035000) | CY | 1,023 | $28.00 | $28.56 | $25.50 | $57.70 |
| 0030 | Embankment in place (2035500) | CY | 597 | $75.00 | $50.49 | $45.00 | $40.00 |
| 0040 | Compacting embankment (2036000) | CY | 695 | $10.00 | $11.71 | $10.50 | $10.00 |
| 0050 | Compacting in cut (2037075) | STA | 30.30 | $250.00 | $526.58 | $468.00 | $800.00 |
| 0060 | Linear grading class 2 (2072000) | STA | 31.70 | $2,100.00 | $1,563.59 | $1,390.00 | $1,500.00 |
| 0065 | Shaping slopes, class III (2153000) | 100F | 3 | $4,855.00 | $2,572.75 | $2,287.00 | $2,500.00 |
| 0070 | Type 5 aggregate for base (4 in. thick) (3040504) | SY | 5,448.60 | $9.00 | $12.80 | $11.40 | $15.85 |
| 0080 | Misc.optional pavement (4019905) | SY | 5,448.60 | $50.40 | $82.33 | $73.20 | $55.00 |
| 0090 | Furnishing type 2 rock blanket (6113020) | CY | 295 | $95.00 | $91.98 | $39.00 | $80.00 |
| 0100 | Placing type 2 rock blanket (6113040) | CY | 295 | $25.00 | $43.02 | $22.00 | $48.00 |
| 0110 | Impact attenuator 70 MPH (sand barrel array) (6122019) | EACH | 10 | $3,000.00 | $3,859.13 | $3,430.00 | $3,400.00 |
| 0120 | Replacement sand barrel (6122020) | EACH | 10 | $409.84 | $514.55 | $457.00 | $400.00 |
| 0130 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $5,000.00 | $6,431.87 | $24,050 | $50,000 |
| 0140 | Construction signs (6161005) | SF | 2,563 | $7.17 | $9.00 | $8.00 | $7.80 |
| 0150 | Channelizer (trim-line) (6161025) | EACH | 175 | $38.94 | $48.88 | $43.50 | $41.50 |
| 0160 | Type 3 moveable barricade (6161030) | EACH | 24 | $230.54 | $289.43 | $258.00 | $250.00 |
| 0170 | Direction indicator barricade (6161033) | EACH | 72 | $153.69 | $192.96 | $171.50 | $175.00 |
| 0180 | Flashing arrow panel (6161040) | EACH | 4 | $2,049.22 | $2,572.75 | $2,287.00 | $2,250.00 |
| 0190 | Sequential flashing warning light (6161055) | EACH | 72 | $138.32 | $173.66 | $155.00 | $148.00 |
| 0200 | Tubular marker (6161070) | EACH | 253 | $71.72 | $90.05 | $80.00 | $80.00 |
| 0210 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $6,659.95 | $8,361.44 | $7,450.00 | $8,000.00 |
| 0220 | Mobilization (6181000) | LS | 1 | $300,000 | $263,768 | $550,000 | $487,118 |
| 0230 | Additional mobilization for seeding (6181020) | EACH | 4 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0240 | Temporary removable marking tape 4 in., white (6205301B) | LF | 18,225 | $1.43 | $1.80 | $1.60 | $1.55 |
| 0250 | Temporary removable marking tape 4 in., yellow (6205303B) | LF | 28,381 | $1.43 | $1.80 | $1.60 | $1.55 |
| 0260 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 5,234 | $0.56 | $0.71 | $0.63 | $0.60 |
| 0270 | 6 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903B) | LF | 9,530 | $0.56 | $0.71 | $0.63 | $0.60 |
| 0280 | Pavement marking removal (6207001) | LF | 12,313 | $0.31 | $0.39 | $0.35 | $0.35 |
| 0290 | Temporary raised pavement marker (6208064A) | EACH | 132 | $3.07 | $3.86 | $3.50 | $3.30 |
| 0300 | Flowable backfill (6214600A) | CY | 10 | $200.00 | $1,234.95 | $2,700.00 | $1,800.00 |
| 0310 | Permanent erosion control geotextile (6240103A) | SY | 442 | $1.15 | $8.76 | $5.50 | $4.50 |
| 0320 | Portland cement concrete shoulder rumble strip (6262000A) | STA | 24.50 | $160.55 | $196.82 | $280.00 | $370.00 |
| 0330 | Contractor furnished surveying and staking (6274000) | LS | 1 | $10,135 | $15,437 | $14,300 | $52,000 |
| 0340 | Mulching (8025006) | ACRE | 7.60 | $1,577.20 | $1,929.56 | $1,715.00 | $1,500.00 |
| 0350 | Seeding - cool season grasses (8051000A) | ACRE | 3.80 | $3,049.25 | $3,730.49 | $3,316.00 | $2,900.00 |
| 0360 | Rock ditch check (8061005) | LF | 767 | $8.41 | $10.29 | $9.15 | $9.00 |
| 0370 | Sediment removal (8061016) | CY | 42 | $30.00 | $41.13 | $227.00 | $6.00 |
| 0380 | Temporary seeding (8061017) | ACRE | 3.80 | $1,261.76 | $1,543.65 | $1,372.00 | $1,200.00 |
| 0390 | MGS bridge approach transition section (regular/no curb) (6061069) | EACH | 8 | $4,114.65 | $5,145.50 | $4,574.00 | $4,500.00 |
| 0400 | Removal of miscellaneous acm (non-friable) (2024043) | SF | 23 | $299.78 | $373.05 | $331.00 | $350.00 |
| 0410 | Total surface hydro demolition (2161001) | SY | 996 | $60.00 | $89.54 | $45.00 | $105.00 |
| 0420 | Removal of asphalt wearing surface (2161501) | SF | 8,960 | $1.22 | $1.57 | $3.10 | $1.50 |
| 0430 | Removal of existing deck repair (2161503) | SF | 400 | $25.00 | $18.51 | $40.00 | $25.50 |
| 0440 | Removal of existing expansion joint & adjacent concrete (2164500) | LF | 82 | $475.00 | $218.66 | $450.00 | $475.00 |
| 0450 | Misc.remove and replace barrier (2169903) | LF | 21 | $380.00 | $635.95 | $795.00 | $765.00 |
| 0460 | Bridge approach slab (major) (5031010A) | SY | 171 | $450.00 | $357.67 | $485.00 | $450.00 |
| 0470 | Supplementary wearing surface material (5050004) | CY | 28 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0480 | Latex modified concrete wearing surface (5052000) | SY | 996 | $145.00 | $200.48 | $148.00 | $233.00 |
| 0490 | Diamond grinding (7031004) | SY | 996 | $14.39 | $11.84 | $6.30 | $6.00 |
| 0500 | Class B-2 concrete (7034214) | CY | 40.50 | $1,850.00 | $3,085.22 | $1,200.00 | $3,150.00 |
| 0510 | Curb blockout (7034600) | LF | 535 | $115.00 | $129.57 | $180.00 | $155.00 |
| 0520 | Full depth repair (7040106) | SF | 700 | $35.00 | $80.31 | $160.00 | $65.00 |
| 0530 | Cleaning and epoxy coating (7040113) | SF | 1,546 | $13.35 | $16.48 | $14.90 | $15.00 |
| 0540 | Reinforcing steel (epoxy coated) (7101000) | LB | 2,090 | $3.42 | $8.74 | $3.50 | $5.00 |
| 0550 | Misc.cored slab drains (7129902) | EACH | 60 | $410.00 | $691.14 | $825.00 | $550.00 |
| 0560 | Misc.plugging existing curb outlets (7129902) | EACH | 62 | $260.00 | $217.53 | $430.00 | $400.00 |
| 0570 | Vertical drain at end bents (7151001) | EACH | 2 | $15,000 | $3,953.97 | $24,600 | $9,000.00 |
| 0580 | Removal of miscellaneous acm (non-friable) (2024043) | SF | 34 | $299.78 | $373.05 | $331.00 | $350.00 |
| 0590 | Total surface hydro demolition (2161001) | SY | 1,496 | $55.00 | $89.54 | $45.00 | $102.00 |
| 0600 | Removal of asphalt wearing surface (2161501) | SF | 13,466 | $1.13 | $1.57 | $1.85 | $1.55 |
| 0610 | Removal of existing deck repair (2161503) | SF | 300 | $25.00 | $18.51 | $40.00 | $26.50 |
| 0620 | Removal of existing expansion joint & adjacent concrete (2164500) | LF | 87 | $475.00 | $250.49 | $450.00 | $460.00 |
| 0630 | Misc.removal of end diaphragms and bearing stiffeners (2169902) | EACH | 4 | $5,000.00 | $6,800.23 | $1,850.00 | $1,500.00 |
| 0640 | Misc.removal of existing bearings and anchor bolts (2169902) | EACH | 10 | $3,100.00 | $7,603.25 | $4,500.00 | $6,800.00 |
| 0650 | Misc.remove and replace barrier (2169903) | LF | 19 | $425.00 | $635.67 | $795.00 | $750.00 |
| 0660 | Bridge approach slab (major) (5031010A) | SY | 171 | $450.00 | $342.20 | $485.00 | $450.00 |
| 0670 | Supplementary wearing surface material (5050004) | CY | 20 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0680 | Latex modified concrete wearing surface (5052000) | SY | 1,501 | $145.00 | $214.41 | $148.00 | $210.00 |
| 0690 | Diamond grinding (7031004) | SY | 1,501 | $14.05 | $11.84 | $4.80 | $5.25 |
| 0700 | Class B-2 concrete (7034214) | CY | 10.70 | $5,600.00 | $5,666.29 | $6,250.00 | $6,700.00 |
| 0710 | Curb blockout (7034600) | LF | 771 | $94.00 | $116.70 | $180.00 | $135.00 |
| 0720 | Substructure repair (formed) (7040101) | SF | 30 | $255.00 | $202.76 | $275.00 | $145.00 |
| 0730 | Full depth repair (7040106) | SF | 100 | $35.00 | $80.31 | $160.00 | $95.00 |
| 0740 | Cleaning and epoxy coating (7040113) | SF | 2,540 | $10.03 | $12.37 | $14.90 | $10.50 |
| 0750 | Reinforcing steel (epoxy coated) (7101000) | LB | 780 | $7.53 | $8.74 | $2.00 | $5.00 |
| 0760 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $8,760.94 | $10,811 | $10,750 | $9,250.00 |
| 0770 | Fabricated structural carbon steel (misc) (7121000) | LB | 2,000 | $45.00 | $41.14 | $50.00 | $35.00 |
| 0780 | Surface preparation for recoating structural steel (7125200) | SF | 1,100 | $50.97 | $62.89 | $99.50 | $54.00 |
| 0790 | Field application of inorganic zinc primer (7125210) | SF | 1,100 | $18.20 | $22.46 | $3.45 | $19.20 |
| 0800 | Intermediate field coat (system G) (7125365A) | SF | 200 | $10.01 | $12.35 | $2.30 | $10.50 |
| 0810 | Finish field coat (system G) (7125370A) | SF | 200 | $10.01 | $12.35 | $2.30 | $10.50 |
| 0825 | Misc.miscellaneous weld repairs (7129902) | EACH | 8 | $3,500.00 | $4,978.64 | $1,800.00 | $3,100.00 |
| 0830 | Misc.cored slab drains (7129902) | EACH | 60 | $465.00 | $691.14 | $825.00 | $550.00 |
| 0840 | Misc.plugging exisitng curb outlets (7129902) | EACH | 88 | $190.00 | $217.55 | $430.00 | $325.00 |
| 0850 | Vertical drain at end bents (7151001) | EACH | 2 | $15,000 | $3,953.97 | $24,600 | $9,000.00 |
| 0860 | Laminated neoprene bearing pad assembly (7162000) | EACH | 10 | $2,900.00 | $7,966.88 | $3,950.00 | $6,950.00 |
| 0870 | Strip seal expansion joint system (7172001) | LF | 81 | $710.00 | $3,048.95 | $675.00 | $850.00 |
| 0880 | Total surface hydro demolition (2161001) | SY | 750 | $60.00 | $89.54 | $45.00 | $112.00 |
| 0890 | Removal of asphalt wearing surface (2161501) | SF | 6,748 | $2.04 | $1.57 | $2.00 | $2.05 |
| 0900 | Removal of existing deck repair (2161503) | SF | 125 | $25.00 | $18.51 | $40.00 | $30.00 |
| 0910 | Bridge approach slab (major) (5031010A) | SY | 172 | $475.00 | $342.19 | $485.00 | $450.00 |
| 0920 | Supplementary wearing surface material (5050004) | CY | 12 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0930 | Latex modified concrete wearing surface (5052000) | SY | 750 | $155.00 | $209.80 | $148.00 | $270.00 |
| 0940 | Diamond grinding (7031004) | SY | 750 | $14.72 | $11.84 | $6.70 | $5.25 |
| 0950 | Curb blockout (7034600) | LF | 386 | $145.00 | $145.01 | $180.00 | $195.00 |
| 0960 | Substructure repair (formed) (7040101) | SF | 50 | $200.00 | $202.74 | $275.00 | $125.00 |
| 0970 | Full depth repair (7040106) | SF | 100 | $35.00 | $80.31 | $160.00 | $100.00 |
| 0980 | Epoxy pressure injecting (7040110) | LF | 6 | $500.00 | $57.36 | $420.00 | $650.00 |
| 0990 | Cleaning and epoxy coating (7040113) | SF | 1,194 | $14.22 | $17.55 | $14.90 | $15.00 |
| 1000 | Misc.pile encasement (7049902) | EACH | 20 | $2,000.00 | $4,759.39 | $2,850.00 | $3,200.00 |
| 1010 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $14,732 | $5,145.50 | $15,550 | $15,500 |
| 1020 | Surface preparation for applying epoxy-mastic primer (7125102) | LS | 1 | $8,488.93 | $10,475 | $5,150.00 | $9,000.00 |
| 1030 | Gray epoxy-mastic primer (7125961) | LS | 1 | $8,488.93 | $10,475 | $4,500.00 | $9,000.00 |
| 1040 | Misc.cored slab drains (7129902) | EACH | 26 | $465.00 | $691.17 | $825.00 | $550.00 |
| 1050 | Misc.plugging existing curb outlets (7129902) | EACH | 42 | $290.00 | $217.54 | $430.00 | $500.00 |
| 1060 | Vertical drain at end bents (7151001) | EACH | 2 | $15,000 | $3,953.97 | $24,600 | $7,500.00 |
| 1070 | Total surface hydro demolition (2161001) | SY | 454 | $60.00 | $89.54 | $45.00 | $121.00 |
| 1080 | Removal of asphalt wearing surface (2161501) | SF | 4,085 | $2.27 | $1.57 | $2.25 | $3.50 |
| 1090 | Removal of existing deck repair (2161503) | SF | 525 | $25.00 | $18.51 | $40.00 | $30.00 |
| 1100 | Bridge approach slab (major) (5031010A) | SY | 171 | $450.00 | $342.20 | $485.00 | $450.00 |
| 1110 | Supplementary wearing surface material (5050004) | CY | 25 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 1120 | Latex modified concrete wearing surface (5052000) | SY | 454 | $200.00 | $237.64 | $148.00 | $360.00 |
| 1130 | Diamond grinding (7031004) | SY | 454 | $15.60 | $11.84 | $9.10 | $8.50 |
| 1140 | Curb blockout (7034600) | LF | 245 | $185.00 | $175.88 | $180.00 | $260.00 |
| 1150 | Substructure repair (formed) (7040101) | SF | 30 | $200.00 | $202.76 | $275.00 | $125.00 |
| 1160 | Full depth repair (7040106) | SF | 300 | $35.00 | $80.31 | $160.00 | $75.00 |
| 1170 | Cleaning and epoxy coating (7040113) | SF | 723 | $15.50 | $19.13 | $14.90 | $16.50 |
| 1180 | Protective coating - concrete bents and piers (epoxy) (7110200) | LS | 1 | $14,732 | $18,179 | $15,550 | $15,500 |
| 1190 | Misc.cored slab drains (7129902) | EACH | 14 | $465.00 | $691.12 | $825.00 | $710.00 |
| 1200 | Misc.plugging existing curb outlets (7129902) | EACH | 22 | $300.00 | $217.57 | $430.00 | $700.00 |
| 1210 | Vertical drain at end bents (7151001) | EACH | 2 | $15,000 | $3,953.97 | $24,600 | $7,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of February 20, 2026. Compiled by Mirage Metrics.