NJDOT contract 26429 bid tabulation
MTN STEEL & ALUMINUM REP. CENTRAL- 2026. Let by New Jersey DOT on October 28, 2025, Hunterdon, Mercer, Middlesex, Monmouth, Ocean,, C4. 3 bids received; low bid $7,079,180 by Iew Construction Group, Inc..
- Owner
- New Jersey DOT
- Letting
- 28 OCT 2025
- Pay items
- 13
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Iew Construction Group, Inc. | $7,079,180 | Low |
| 2 | Sparwick Contracting, Inc. | $7,163,492 | +1.0% |
| 3 | Joseph M. Sanzari, Inc. | $7,696,860 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Iew Construction Group, Inc. | 2. Sparwick Contracting, Inc. | 3. Joseph M. Sanzari, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $1.00 | $1.00 | $60,000 |
| 0002 | Pollution liability insurance (152015P) | DOL | 1 | $0.01 | $1.00 | $7,500.00 |
| 0003 | Telephone service (MMG010M) | DOL | 2,050 | $1.00 | $1.00 | $1.00 |
| 0004 | Lane closures (MMB172M) | HR | 4,010 | $0.01 | $0.01 | $50.00 |
| 0005 | Solid waste disposal (MMB173M) | DOL | 25,000 | $1.00 | $1.00 | $1.00 |
| 0006 | Disposal of regulated material (MMG027M) | DOL | 2,500 | $1.00 | $1.00 | $1.00 |
| 0007 | Disposal of regulated material, hazardous (MMG064M) | DOL | 2,500 | $1.00 | $1.00 | $1.00 |
| 0008 | Adjustment factor , (force account) (MMG095M) | PCT | 1,822,000 | $1.00 | $1.15 | $1.14 |
| 0009 | Labor crew , sign (MMB186M) | HR | 2,010 | $209.63 | $685.00 | $648.00 |
| 0010 | Labor crew , steel (MMB186M) | HR | 4,000 | $693.33 | $685.00 | $617.00 |
| 0011 | Labor crew , welding (MMB186M) | HR | 5,250 | $361.65 | $150.00 | $270.00 |
| 0012 | Crew coordinator (MMB092M) | HR | 50 | $135.00 | $135.00 | $135.00 |
| 0013 | Overtime differential (OD) (MMG025M) | DOL | 125,000 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of October 28, 2025. Compiled by Mirage Metrics.