NJDOT contract 26446 bid tabulation
MTN Beam Guide Rail & Attenuator Central 2026. Let by New Jersey DOT on October 14, 2025, Hunterdon, Mercer, Middlesex, Monmouth, Ocean,, C4. 3 bids received; low bid $2,664,661 by M.L. Ruberton Construction Co., Inc..
- Owner
- New Jersey DOT
- Letting
- 14 OCT 2025
- Pay items
- 42
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | M.L. Ruberton Construction Co., Inc. | $2,664,661 | Low |
| 2 | J. Fletcher Creamer & Son, Inc. | $2,887,976 | +8.0% |
| 3 | South State, Inc. | $3,875,040 | +45% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M.L. Ruberton Construction Co., Inc. | 2. J. Fletcher Creamer & Son, Inc. | 3. South State, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $14,575 | $10,000 | $15,000 |
| 0002 | Special mobilization (MMR005M) | U | 4 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0003 | Emergency mobilization (MMR006M) | U | 15 | $5,000.00 | $5,000.00 | $5,000.00 |
| 0004 | Telephone service (MMG010M) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 0005 | Pollution liability insurance (152015P) | DOL | 1 | $12,573 | $1.00 | $1.00 |
| 0006 | Field office equipment (MMG018M) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 0007 | Force account (109006M) | DOL | 292,654 | $1.00 | $1.00 | $1.00 |
| 0008 | Excavation, test pit (202006M) | CY | 20 | $1.00 | $1.00 | $1.00 |
| 0009 | Oil only emergency spill kit, type 1 (158072M) | U | 1 | $1.00 | $1.00 | $2,000.00 |
| 0010 | Traffic director, flagger (159141M) | HR | 10 | $1.00 | $1.00 | $1.00 |
| 0011 | Asphalt cold patch (MMR115M) | LB | 150 | $20.00 | $1.00 | $10.00 |
| 0012 | Fuel price adjustment (160004M) | DOL | 500 | $1.00 | $1.00 | $1.00 |
| 0013 | 9" X 14" concrete vertical curb (607034P) | LF | 50 | $40.00 | $84.00 | $100.00 |
| 0014 | 9" X 16" concrete vertical curb (607018P) | LF | 50 | $40.00 | $84.00 | $100.00 |
| 0015 | Sawcut vertical curb (607120P) | LF | 300 | $65.00 | $74.00 | $30.00 |
| 0016 | Nonvegetative surface, hot mix asphalt (608003P) | SY | 300 | $60.00 | $40.00 | $60.00 |
| 0017 | Nonvegetative surface, porous hot mix asphalt, 6" thick (608005P) | SY | 350 | $20.00 | $40.00 | $75.00 |
| 0018 | Non-vegetative surface, polyester matting (MMR073M) | SY | 50 | $1.00 | $1.00 | $1.00 |
| 0019 | Miscellaneous concrete (MMG151M) | CY | 20 | $1.00 | $500.00 | $1.00 |
| 0020 | Inspection of units (MMA001M) | U | 20 | $800.00 | $800.00 | $800.00 |
| 0021 | Beam guide rail (609003M) | LF | 30,000 | $43.00 | $45.00 | $65.00 |
| 0022 | Modified thrie beam guide rail (609009M) | LF | 1,000 | $44.00 | $49.00 | $50.00 |
| 0023 | Flared guide rail terminal (609024M) | U | 50 | $1,500.00 | $3,000.00 | $4,700.00 |
| 0024 | Buried guide rail terminal (609025M) | U | 5 | $1.00 | $100.00 | $1.00 |
| 0025 | Tangent guide rail terminal (609027M) | U | 150 | $3,000.00 | $3,000.00 | $4,500.00 |
| 0026 | Telescoping guide rail end terminal (609030M) | U | 6 | $3,200.00 | $4,200.00 | $7,000.00 |
| 0027 | Controlled release terminal (609033M) | U | 8 | $1.00 | $750.00 | $750.00 |
| 0028 | Controlled release terminal anchorage (609036M) | U | 5 | $1.00 | $750.00 | $750.00 |
| 0029 | Beam guide rail anchorage (609039M) | U | 30 | $1,150.00 | $1,200.00 | $1,150.00 |
| 0030 | Attachment to structure , balustrade, detail no. CD-609- 12.1 (MMG032M) | LF | 5 | $1.00 | $1.00 | $100.00 |
| 0031 | Attachment to structure , detail no. CD-609-11.1 (MMG032M) | LF | 5 | $150.00 | $200.00 | $100.00 |
| 0032 | Attachment to structure , detail no. CD-609-11.1, W/existing beam guide rail element (MMG033M) | U | 5 | $1.00 | $1.00 | $100.00 |
| 0033 | Attachment to structure, type A (MMR047M) | U | 5 | $1,000.00 | $2,400.00 | $2,500.00 |
| 0034 | Attachment to structure, type B (MMR048M) | U | 5 | $250.00 | $100.00 | $250.00 |
| 0035 | Buffer end pieces for end treatments (MMR055M) | U | 10 | $50.00 | $150.00 | $100.00 |
| 0036 | Wooden posts for end treatments (MMR056M) | U | 25 | $250.00 | $100.00 | $250.00 |
| 0037 | Rail elements for end treatments (MMR057M) | U | 100 | $500.00 | $500.00 | $300.00 |
| 0038 | Reflective sheeting for end treatments (MMR058M) | SF | 30 | $1.00 | $1.00 | $1.00 |
| 0039 | Guide rail extruders (MMR076M) | U | 15 | $750.00 | $500.00 | $750.00 |
| 0040 | Steel post for end treatment (MMG030M) | U | 100 | $500.00 | $250.00 | $300.00 |
| 0041 | Repair category "A" (MMB181M) | HR | 150 | $1,000.00 | $1,500.00 | $1,300.00 |
| 0042 | Mobilization (154003P) | LS | 1 | $5,000.00 | $22,500 | $115,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of October 14, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.