NJDOT contract 26447 bid tabulation

MTN Beam Guide Rail & Attenuator South 2026. Let by New Jersey DOT on October 16, 2025, Atlantic, Burlington, Camden, Cape May,, S4. 3 bids received; low bid $2,230,742 by M.L. Ruberton Construction Co., Inc..

Owner
New Jersey DOT
Letting
16 OCT 2025
Pay items
42
Data through
16 APR 2026

Bidders

RankBidderTotal bidAgainst the low bid
1M.L. Ruberton Construction Co., Inc.$2,230,742Low
2J. Fletcher Creamer & Son, Inc.$2,715,474+22%
3South State, Inc.$3,035,098+36%
NJDOT contract 26447: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. M.L. Ruberton Construction Co., Inc.2. J. Fletcher Creamer & Son, Inc.3. South State, Inc.
0001Performance bond and payment bond (151006M)DOL1$12,205$8,000.00$5,000.00
0002Special mobilization (MMR005M)U10$2,000.00$2,000.00$2,000.00
0003Emergency mobilization (MMR006M)U35$5,000.00$5,000.00$5,000.00
0004Telephone service (MMG010M)DOL1,000$1.00$1.00$1.00
0005Pollution liability insurance (152015P)DOL1$12,538$1.00$1.00
0006Field office equipment (MMG018M)DOL1,000$1.00$1.00$1.00
0007Force account (109006M)DOL280,000$1.00$1.00$1.00
0008Excavation, test pit (202006M)CY15$1.00$1.00$1.00
0009Oil only emergency spill kit, type 1 (158072M)U1$1.00$1.00$2,000.00
0010Traffic director, flagger (159141M)HR150$1.00$1.00$1.00
0011Asphalt cold patch (MMR115M)LB300$1.00$1.00$15.00
0012Fuel price adjustment (160004M)DOL850$1.00$1.00$1.00
00139" X 14" concrete vertical curb (607034P)LF100$30.00$84.00$100.00
00149" X 16" concrete vertical curb (607018P)LF100$30.00$84.00$100.00
0015Sawcut vertical curb (607120P)LF1,000$65.00$74.00$45.00
0016Nonvegetative surface, hot mix asphalt (608003P)SY85$20.00$40.00$40.00
0017Nonvegetative surface, porous hot mix asphalt, 6" thick (608005P)SY360$20.00$40.00$40.00
0018Non-vegetative surface, polyester matting (MMR073M)SY10$1.00$1.00$1.00
0019Miscellaneous concrete (MMG151M)CY20$1.00$50.00$1.00
0020Inspection of units (MMA001M)U15$1,000.00$1,000.00$1,000.00
0021Beam guide rail (609003M)LF29,000$38.00$52.00$55.00
0022Modified thrie beam guide rail (609009M)LF1,250$50.00$52.00$60.00
0023Flared guide rail terminal (609024M)U25$1,800.00$3,000.00$3,700.00
0024Buried guide rail terminal (609025M)U2$1.00$100.00$1.00
0025Tangent guide rail terminal (609027M)U40$3,500.00$3,000.00$3,500.00
0026Telescoping guide rail end terminal (609030M)U9$3,500.00$4,200.00$6,000.00
0027Controlled release terminal (609033M)U5$1.00$750.00$1,000.00
0028Controlled release terminal anchorage (609036M)U5$1.00$750.00$1,000.00
0029Beam guide rail anchorage (609039M)U25$1,250.00$1,200.00$1,000.00
0030Attachment to structure , balustrade, detail no. CD-609- 12.1 (MMG032M)LF15$1.00$1.00$100.00
0031Attachment to structure , detail no. CD-609-11.1 (MMG032M)LF10$1.00$200.00$100.00
0032Attachment to structure , detail no. CD-609-11.1, W/existing beam guide rail element (MMG033M)U10$1.00$1.00$100.00
0033Attachment to structure, type A (MMR047M)U5$2,000.00$2,400.00$2,400.00
0034Attachment to structure, type B (MMR048M)U5$250.00$100.00$200.00
0035Buffer end pieces for end treatments (MMR055M)U20$1.00$150.00$110.00
0036Wooden posts for end treatments (MMR056M)U20$50.00$100.00$350.00
0037Rail elements for end treatments (MMR057M)U55$800.00$500.00$750.00
0038Reflective sheeting for end treatments (MMR058M)SF50$1.00$1.00$1.00
0039Guide rail extruders (MMR076M)U15$500.00$500.00$750.00
0040Steel post for end treatment (MMG030M)U50$200.00$250.00$300.00
0041Repair category "A" (MMB181M)HR130$1,100.00$1,300.00$1,300.00
0042Mobilization (154003P)LS1$3,635.50$24,972$194,000
NJDOT contract 26447: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.

Every contract let that day: NJDOT letting of October 16, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy