NYSDOT contract D265319 bid tabulation
BRIDGE REPLACEMENT - US Route 9W over CSX Railroad. Let by New York State DOT on March 27, 2025, Albany, Region 01. 3 bids received; low bid $16,425,400 by Ing Civil Inc.
- Owner
- New York State DOT
- Letting
- 27 MAR 2025
- Pay items
- 122
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ing Civil Inc | $16,425,400 | Low |
| 2 | James H Maloy Inc | $16,934,000 | +3.0% |
| 3 | Rifenburg Construction Inc | $17,173,115 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ing Civil Inc | 2. James H Maloy Inc | 3. Rifenburg Construction Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $250,000 | $55,000 | $35,000 |
| 2 | (202.120001) | LS | 1 | $1,550,000 | $2,220,000 | $1,250,000 |
| 3 | Removal of Substructures (202.19) | CY | 1,263 | $65.00 | $400.00 | $278.00 |
| 4 | Unclassified Excavation and Disposal (203.02) | CY | 21,006 | $18.00 | $29.00 | $35.00 |
| 5 | Embankment In Place (203.03) | CY | 8,730 | $45.00 | $10.00 | $25.00 |
| 6 | Select Granular Fill (203.07) | CY | 109 | $115.00 | $135.00 | $37.00 |
| 7 | Select Granular Fill, Slope Protection - Type A (203.0801) | CY | 276 | $72.00 | $145.00 | $131.00 |
| 8 | Select Structural Fill (203.21) | CY | 76 | $147.00 | $175.00 | $37.00 |
| 9 | Structure Excavation (206.01) | CY | 7,887 | $20.00 | $30.00 | $75.00 |
| 10 | Trench and Culvert Excavation (206.0201) | CY | 157 | $64.00 | $90.00 | $65.00 |
| 11 | Geotextile Stabilization (207.24) | SY | 23,052 | $1.20 | $2.00 | $0.85 |
| 12 | Prefabricated Composite Integral Abutment Drain (207.27) | SY | 98 | $30.00 | $34.00 | $25.00 |
| 13 | Mulch – Temporary (209.100101) | SY | 13,253 | $0.50 | $1.25 | $0.95 |
| 14 | Seed and Mulch – Temporary (209.1003) | SY | 13,253 | $0.55 | $1.50 | $1.10 |
| 15 | (209.11010024) | 3 | $500.00 | $400.00 | $225.00 | |
| 16 | Check Dam, Prefabricated – Temporary (209.1105) | LF | 131 | $26.00 | $75.00 | $40.00 |
| 17 | Silt Fence - Temporary (209.13) | LF | 6,835 | $5.00 | $7.00 | $4.90 |
| 18 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 2,287 | $5.50 | $6.50 | $5.50 |
| 19 | Stabilized Construction Access (209.22) | SY | 210 | $34.00 | $35.00 | $47.00 |
| 20 | Soil Nail Wall System (Temporary) (211.01) | SF | 4,269 | $244.00 | $110.00 | $222.00 |
| 21 | Subbase Course, Type 2 (304.12) | CY | 5,784 | $86.00 | $105.00 | $93.00 |
| 22 | (404.0001) | TON | 560 | $85.00 | $85.00 | $85.00 |
| 23 | (404.0189) | TON | 33 | $485.00 | $600.00 | $500.00 |
| 24 | (404.0962) | TON | 2,197 | $93.00 | $100.00 | $134.25 |
| 25 | (404.0982) | TON | 233 | $165.00 | $175.00 | $215.50 |
| 26 | (404.1979) | TON | 2,072 | $110.00 | $120.00 | $97.00 |
| 27 | (404.1989) | TON | 390 | $165.00 | $175.00 | $115.00 |
| 28 | (404.3779) | TON | 5,097 | $100.00 | $108.00 | $83.00 |
| 29 | (404.3789) | TON | 637 | $165.00 | $175.00 | $118.50 |
| 30 | Straight Tack Coat (407.0103) | GAL | 1,840 | $13.00 | $15.00 | $3.00 |
| 31 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 19,563 | $0.80 | $0.85 | $0.60 |
| 32 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 12,230 | $3.00 | $3.50 | $2.50 |
| 33 | Steel H-Piles (HP 12x74) (551.012074) | LF | 12,634 | $74.00 | $65.00 | $81.00 |
| 34 | Splices for Steel H-Piles (551.12) | EACH | 316 | $75.00 | $1.00 | $75.00 |
| 35 | Furnishing Equipment for Driving Piles (551.13) | LS | 1 | $1,800,000 | $95,000 | $300,000 |
| 36 | Temporary Steel Sheeting (552.13) | SF | 1,582 | $38.00 | $50.00 | $38.00 |
| 37 | Footing Concrete, Performance (555.0011) | CY | 138 | $1,000.00 | $1,350.00 | $1,500.00 |
| 38 | Concrete for Structures, Performance (555.0021) | CY | 482 | $1,300.00 | $1,400.00 | $1,750.00 |
| 39 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $2.50 | $2.50 | $2.50 |
| 40 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $7.00 | $7.00 | $7.00 |
| 41 | Galvanized Bar Reinforcement for Structures (556.0203) | LB | 97,328 | $1.75 | $2.15 | $2.00 |
| 42 | Stud Shear Connectors for Bridges (556.03) | EACH | 7,170 | $4.00 | $5.00 | $4.00 |
| 43 | (557.1019) | SY | 305 | $500.00 | $590.00 | $775.00 |
| 44 | (557.1119) | SY | 1,501 | $450.00 | $650.00 | $600.00 |
| 45 | Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29) | SY | 1,760 | $0.01 | $9.00 | $0.01 |
| 46 | Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901) | QUALITY UNIT | 1 | $7.35 | $7.35 | $7.35 |
| 47 | Longitudinal Sawcut Grooving of Structural Slab Surface (558.02) | SY | 1,640 | $8.00 | $9.50 | $8.72 |
| 48 | Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01) | SF | 14,759 | $0.50 | $0.70 | $0.65 |
| 49 | Protective Sealing of New Structural Concrete (559.02) | SF | 3,180 | $1.00 | $1.65 | $0.75 |
| 50 | (564.0501) | LS | 1 | $1,800,000 | $2,790,000 | $1,806,000 |
| 51 | (564.0502) | LS | 1 | $300,000 | $80,000 | $75,000 |
| 52 | Type E.B. Expansion Bearing (Over 225 k) (565.2035) | EACH | 10 | $3,000.00 | $4,000.00 | $3,000.00 |
| 53 | (565.30130101) | 10 | $450.00 | $350.00 | $1,000.00 | |
| 54 | Armorless Bridge Joint (567.60) | LF | 100 | $285.00 | $300.00 | $250.00 |
| 55 | Transition Bridge Railing (568.70) | LF | 160 | $186.00 | $200.00 | $185.50 |
| 56 | Single Slope (Half-Section) Concrete Bridge Barrier (569.04) | LF | 728 | $122.00 | $265.00 | $300.00 |
| 57 | Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99) | QUALITY UNIT | 1 | $9.09 | $9.09 | $9.09 |
| 58 | (572.00020101) | LS | 1 | $340,000 | $450,000 | $354,100 |
| 59 | (603.171116) | EACH | 10 | $320.00 | $600.00 | $280.00 |
| 60 | (603.171614) | EACH | 2 | $730.00 | $1,200.00 | $875.00 |
| 61 | (603.9812) | LF | 157 | $32.00 | $32.00 | $157.00 |
| 62 | (603.9824) | LF | 65 | $60.00 | $135.00 | $268.00 |
| 63 | (604.302122) | LF | 10 | $800.00 | $800.00 | $1,535.00 |
| 64 | Underdrain Filter, Type II (605.1001) | CY | 529 | $160.00 | $130.00 | $150.00 |
| 65 | (605.1701) | LF | 7,125 | $2.00 | $4.00 | $7.50 |
| 66 | Box Beam Guide Railing (606.10) | LF | 1,434 | $47.00 | $52.00 | $46.50 |
| 67 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 90 | $77.00 | $78.00 | $76.50 |
| 68 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 7 | $4,300.00 | $4,500.00 | $4,300.00 |
| 69 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 5 | $2,250.00 | $2,350.00 | $2,250.00 |
| 70 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 2,445 | $7.00 | $7.00 | $6.50 |
| 71 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 16 | $200.00 | $185.00 | $175.00 |
| 72 | (607.06400016) | 616 | $80.00 | $140.00 | $73.00 | |
| 73 | (607.41010010) | 459 | $11.00 | $7.00 | $9.00 | |
| 74 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 771 | $195.00 | $250.00 | $215.00 |
| 75 | Stone Curb – Bridge (Type A) (609.0301) | LF | 57 | $244.00 | $200.00 | $200.00 |
| 76 | Compost (610.10) | CY | 1,105 | $96.00 | $100.00 | $96.00 |
| 77 | (610.15120208) | 13,253 | $3.40 | $3.50 | $3.40 | |
| 78 | Turf Establishment – Performance (610.1605) | SY | 11,770 | $11.50 | $12.00 | $11.50 |
| 79 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $400,000 | $450,108 | $1,339,644 |
| 80 | Type III Construction Barricades (619.04) | EACH | 28 | $200.00 | $500.00 | $200.00 |
| 81 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 17,890 | $5.80 | $6.00 | $5.79 |
| 82 | (619.100101) | LF | 43,400 | $0.40 | $0.40 | $0.37 |
| 83 | (619.111113) | EACH | 2 | $15,000 | $20,000 | $3,750.00 |
| 84 | Temporary Positive Barrier – Category 3 (Pinning Prohibited) (619.1713) | LF | 1,480 | $20.00 | $74.00 | $53.00 |
| 85 | Temporary Impact Attenuator - Gating (Test Level 3) (619.1813) | EACH | 4 | $8,000.00 | $14,000 | $8,000.00 |
| 86 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $100,000 | $20,000 | $500,000 |
| 87 | Mailboxes (619.27) | EACH | 5 | $600.00 | $400.00 | $700.00 |
| 88 | (619.99230101) | LS | 1 | $10,000 | $5,000.00 | $10,000 |
| 89 | (619.99230201) | 15 | $100.00 | $150.00 | $150.00 | |
| 90 | Stone Filling (Light) (620.03) | CY | 17 | $115.00 | $175.00 | $295.00 |
| 91 | Bedding Material, Type 1 (620.0801) | CY | 18 | $240.00 | $170.00 | $314.00 |
| 92 | Cleaning Culverts with Span of 50 in. or Less (621.01) | LF | 520 | $22.00 | $26.00 | $21.65 |
| 93 | (621.51000015) | 602 | $112.00 | $20.00 | $19.00 | |
| 94 | Survey Operations (625.01) | LS | 1 | $200,000 | $150,000 | $80,000 |
| 95 | (625.09010015) | LS | 1 | $1.00 | $5,000.00 | $15,000 |
| 96 | (627.50140008) | 12,865 | $3.60 | $4.00 | $3.75 | |
| 97 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 12,230 | $0.60 | $0.70 | $0.75 |
| 98 | Field Laboratory (637.01) | EACH | 1 | $1,000.00 | $10,000 | $5,000.00 |
| 99 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $10,000 | $3,000.00 | $4,000.00 |
| 100 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 18 | $1.00 | $4,200.00 | $3,000.00 |
| 101 | Rain Gauge (637.26) | EACH | 1 | $500.00 | $350.00 | $200.00 |
| 102 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 |
| 103 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 104 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 251 | $36.00 | $38.00 | $35.25 |
| 105 | Type A Sign Posts (645.81) | EACH | 42 | $200.00 | $220.00 | $200.00 |
| 106 | Reference Marker Panel (646.21) | EACH | 9 | $37.00 | $40.00 | $36.50 |
| 107 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 15 | $24.00 | $25.00 | $23.50 |
| 108 | Steel Post, 2.0 lb/ft (646.32) | EACH | 24 | $85.00 | $90.00 | $85.00 |
| 109 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 1 | $50.00 | $52.00 | $50.00 |
| 110 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 34 | $37.00 | $40.00 | $36.25 |
| 111 | Welded Frame & Reticuline Grate 22 (655.1122) | EACH | 2 | $2,000.00 | $2,000.00 | $1,400.00 |
| 112 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 9,755 | $0.80 | $0.85 | $0.79 |
| 113 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 11,262 | $0.80 | $0.85 | $0.79 |
| 114 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 573 | $3.60 | $4.00 | $3.59 |
| 115 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 1,292 | $3.00 | $3.25 | $2.99 |
| 116 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 22 | $215.00 | $235.00 | $215.00 |
| 117 | (691.04000020) | 60,000 | $1.00 | $1.00 | $1.00 | |
| 118 | Field Change Payment (FCP) (697.03) | DOL | 761,381.86 | $1.00 | $1.00 | $1.00 |
| 119 | Asphalt Price Adjustment (698.04) | DOL | 16,598 | $1.00 | $1.00 | $1.00 |
| 120 | Fuel Price Adjustment (698.05) | DOL | 5,004 | $1.00 | $1.00 | $1.00 |
| 121 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 122 | Mobilization (699.040001) | LS | 1 | $627,492 | $650,000 | $660,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 27, 2025. Compiled by Mirage Metrics.