NYSDOT contract D265337 bid tabulation

RT 34 BRIDGE REPLACEMENT OVER SENECA RIVER. Let by New York State DOT on January 9, 2025, Cayuga, Region 03. 4 bids received; low bid $24,221,390 by Vector Construction Corp.

Owner
New York State DOT
Letting
09 JAN 2025
Pay items
164
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Vector Construction Corp$24,221,390Low
2Economy Paving Co Inc$24,242,0420.0%
3Cold Spring Construction Company$24,275,8450.0%
4Slate Hill Constructors Inc$30,527,359+26%
NYSDOT contract D265337: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Vector Construction Corp2. Economy Paving Co Inc3. Cold Spring Construction Company4. Slate Hill Constructors Inc
1Clearing and Grubbing (201.06)LS1$48,000$185,000$75,000$150,000
2 (202.120001)LS1$1,950,000$2,500,000$2,500,000$6,400,000
3Removal of Substructures (202.19)CY612$140.00$155.00$200.00$280.00
4Unclassified Excavation and Disposal (203.02)CY5,378$21.00$15.00$25.00$50.00
5Embankment In Place (203.03)CY10,402$27.00$20.00$13.50$50.00
6Select Granular Fill (203.07)CY151$80.00$55.00$56.00$110.00
7Settlement Rods (203.12)EACH35$331.00$250.00$300.00$825.00
8Select Granular Subgrade (203.20)CY4,379$60.00$65.00$65.00$85.00
9Select Structural Fill (203.21)CY585$68.00$75.00$80.00$95.00
10 (203.24010017)69$46.00$10.00$43.00$100.00
11 (203.51990006)832$11.00$1.00$15.00$11.00
12Structure Excavation (206.01)CY5,495$24.00$25.00$24.00$50.00
13Trench and Culvert Excavation (206.0201)CY406$34.00$5.00$32.00$50.00
14Conduit Excavation and Backfill including Surface Restoration (206.03)LF100$45.00$1.00$33.00$37.00
15Geotextile Drainage (207.22)SY166$5.00$1.00$5.00$14.00
16Prefabricated Composite Integral Abutment Drain (207.27)SY226$18.00$8.85$19.00$20.00
17 (208.01030022)17$130.00$135.00$160.00$150.00
18Mulch – Temporary (209.100101)SY22,500$0.81$1.00$0.80$1.30
19Seed and Mulch – Temporary (209.1003)SY7,000$0.86$1.00$0.85$1.30
20 (209.11010024)1$261.00$150.00$250.00$550.00
21Silt Fence - Temporary (209.13)LF50$7.00$5.00$40.50$10.00
22Turbidity Curtain – Temporary (209.1501)LF235$34.00$20.00$58.00$17.00
23Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301)SY635$6.00$10.00$6.25$5.75
24Soil Stabilizers, Class IV Type A (209.2101)SY12,198$0.95$1.00$0.95$1.75
25 (209.23010009)4,372$9.85$7.50$12.50$10.50
26Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312)SF102$175.00$10.00$85.00$190.00
27Subbase Course, Optional Type (304.15)CY3,334$73.00$75.00$72.00$90.00
28 (404.0001)TON229$70.00$70.00$70.00$70.00
29 (404.0189)TON9$105.00$140.00$200.00$110.00
30 (404.0972)TON846$105.00$120.00$116.00$110.00
31 (404.1979)TON1,328$93.00$110.00$97.00$100.00
32 (404.2589)TON2,390$85.00$110.00$98.00$90.00
33 (404.4489)TON19$190.00$160.00$185.00$195.00
34 (404.4589)TON28$190.00$160.00$150.00$195.00
35Diluted Tack Coat (407.0102)GAL791$2.00$3.40$7.00$2.20
36Asphalt Pavement Joint Adhesive (418.7603)LF13,688$0.30$0.35$0.01$0.30
37Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY584$15.00$25.00$15.00$15.00
38Steel H-Piles (HP 14x89) (551.014089)LF10,176$72.00$28.50$16.00$2.50
39Splices for Steel H-Piles (551.12)EACH76$10.00$1.00$0.01$20.00
40Furnishing Equipment for Driving Piles (551.13)LS1$560,000$1,000,000$1,000,000$1,300,000
41Shields and Shoring (552.17)SF2,456$1.00$0.10$1.25$5.00
42 (553.010001)EACH1$350,000$500,000$250,000$175,000
43 (553.010002)EACH1$350,000$500,000$250,000$175,000
44Footing Concrete, Performance (555.0011)CY277$680.00$600.00$800.00$1,000.00
45Concrete for Structures, Performance (555.0021)CY649$1,200.00$850.00$1,150.00$1,100.00
46 (555.02000001)456$762.00$450.00$715.00$850.00
47Performance Concrete Quality Adjustment – Footing Concrete (555.9901)QUALITY UNIT1$2.75$2.75$2.75$2.75
48Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$5.00$5.00$5.00$5.00
49Galvanized Bar Reinforcement for Structures (556.0203)LB196,564$2.06$2.00$2.50$2.20
50Stud Shear Connectors for Bridges (556.03)EACH9,486$5.20$5.00$7.25$5.60
51 (557.1019)SY287$435.00$435.00$490.00$500.00
52 (557.1119)SY3,370$515.00$450.00$500.00$540.00
53Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29)SY3,615$0.01$0.10$0.01$0.10
54Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901)QUALITY UNIT1$6.63$6.63$6.63$6.63
55Longitudinal Sawcut Grooving of Structural Slab Surface (558.02)SY3,385$6.00$7.00$7.65$7.50
56Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01)SF30,464$0.45$0.55$0.55$1.10
57Protective Sealing of New Structural Concrete (559.02)SF5,961$1.10$0.90$1.25$2.50
58 (564.0501)LS1$7,600,000$7,750,000$7,200,000$6,000,000
59Type M.R. Expansion Bearing (226 to 450 k) (565.1522)EACH12$7,000.00$5,650.00$6,000.00$7,500.00
60Type M.R. Expansion Bearing (676 to 900 k) (565.1524)EACH12$9,000.00$8,250.00$9,000.00$12,000
61Modular Expansion Joint System - Two Cell (566.02)LF82$2,100.00$1,950.00$2,250.00$2,200.00
62Transition Bridge Railing (568.70)LF160$160.00$155.00$160.00$170.00
63Single Slope (Half-Section) Concrete Bridge Barrier (569.04)LF1,376$230.00$160.00$210.00$215.00
64Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99)QUALITY UNIT1$9.92$9.92$9.92$9.92
65Lead-Exposure Control Plan (570.01)LS1$1.00$100.00$250.00$3,000.00
66Medical Testing (570.02)DOL1,500$1.00$1.00$1.00$1.00
67Personal-Exposure-Monitoring Sample Analysis (570.03)DOL1,500$1.00$1.00$1.00$1.00
68Decontamination Facilities (570.04)CALENDAR WEEK5$1.00$100.00$350.00$600.00
69 (570.10)LS1$1.00$100.00$0.01$1.00
70 (572.00020101)LS1$1,750,000$1,400,000$1,700,000$1,500,000
71Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH36$60.00$35.00$170.00$320.00
72Field Drill Holes in Existing Structural Steel (586.10)EACH36$16.00$50.00$75.00$100.00
73Treated Timber and Lumber (594.03)CF5$300.00$10.00$140.00$1,100.00
74 (594.04020603)24$90.00$1.00$20.00$95.00
75Culvert-End Safety Grate (603.0101)SF30$30.00$35.00$35.00$70.00
76 (603.6002)LF82$80.00$75.00$115.00$95.00
77 (603.6005)LF54$95.00$115.00$175.00$110.00
78 (603.6007)LF115$170.00$155.00$235.00$135.00
79 (603.7302)EACH4$3,000.00$2,035.00$2,400.00$2,750.00
80 (603.7305)EACH2$4,200.00$3,675.00$3,750.00$4,000.00
81 (603.7307)EACH2$4,600.00$5,145.00$4,500.00$4,700.00
82Underdrain Filter, Type II (605.1001)CY10$140.00$200.00$225.00$195.00
83 (605.1602)LF112$20.00$2.15$30.00$140.00
84Box Beam Guide Railing (606.10)LF2,612$43.00$45.00$42.00$45.00
85Box Beam Guide Railing End Assembly Type I with 18 ft Extension (606.120103)EACH8$4,500.00$4,215.00$4,400.00$4,600.00
86Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH2$1,800.00$1,750.00$1,775.00$1,900.00
87Removing and Disposing Corrugated Beam Guide Railing (606.71)LF2,192$4.00$5.00$5.50$5.00
88 (607.41010010)440$6.50$5.50$5.25$5.50
89Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT11$70.00$70.00$70.00$70.00
90Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON228$155.00$145.00$250.00$160.00
91Stone Curb – Bridge (Type A) (609.0301)LF57$120.00$120.00$162.00$170.00
92Compost (610.10)CY1,009$47.00$35.00$50.56$92.00
93Topsoil - Roadside (610.1402)CY1,453$52.00$30.00$115.00$110.00
94Turf Establishment - Roadside (610.1601)SY990$32.00$3.50$3.25$1.60
95 (610.16030224)12,098$1.10$1.00$1.15$3.75
96Turf Establishment – Performance (610.1605)SY398$20.00$20.00$21.00$17.00
97Watering Vegetation (610.19)1,000 GALLONS1,763$5.00$1.00$60.00$24.00
98 (617.01010024)500$4.00$5.00$5.25$5.50
99 (617.10000024)10$120.00$100.00$175.00$150.00
100 (617.11000024)LS1$6,000.00$100.00$250.00$3,000.00
101Basic Work Zone Traffic Control (619.01)LS1$80,000$500,000$200,000$2,350,000
102Type III Construction Barricades (619.04)EACH49$135.00$200.00$100.00$50.00
103 (619.111112)EACH2$22,000$10,000$15,000$8,250.00
104Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF40$33.00$25.00$60.00$110.00
105Mailboxes (619.27)EACH3$300.00$500.00$300.00$100.00
106 (619.99230101)LS1$2,000.00$2,000.00$2,000.00$2,000.00
107 (619.99230201)14$240.00$250.00$50.00$250.00
108Stone Filling (Light) (620.03)CY70$140.00$75.00$210.00$145.00
109Stone Filling (Heavy) (620.05)CY1,861$135.00$125.00$130.00$160.00
110Bedding Material, Type 1 (620.0801)CY367$95.00$115.00$140.00$120.00
111 (621.05020004)2,727$4.00$0.10$3.00$11.00
112 (621.51000015)44$12.00$1.00$13.00$60.00
113Survey Operations (625.01)LS1$55,000$30,000$80,000$60,000
114 (625.09010015)LS1$14,000$1,000.00$4,000.00$1,000.00
115 (627.50140008)106$10.00$1.00$5.00$5.00
116 (634.99010017)LS1$4,400.00$5,000.00$5,700.00$5,500.00
117 (634.99020017)LS1$7,500.00$3,000.00$5,500.00$3,250.00
118Concrete Cylinder Curing Equipment (637.04)EACH2$1,000.00$3,000.00$250.00$3,000.00
119Engineer’s Field Office – Type 1 (637.11)MONTH18$2,700.00$3,000.00$2,600.00$3,400.00
120Rain Gauge (637.26)EACH1$200.00$100.00$40.00$75.00
121Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00$1.00
122Partnering Workshop (637.35)DOL5,000$1.00$1.00$1.00$1.00
123Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00$1.00
124 (639.21010011)LS1$75,000$75,000$75,000$75,000
125 (642.31510024)100$20.00$35.00$37.00$40.00
126 (645.13070010)4$210.00$500.00$420.00$265.00
127 (645.13080010)52$26.00$25.00$21.00$55.00
128Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF57$40.00$40.00$39.00$65.00
129Type A Sign Posts with Extra Embedment (645.8104)EACH10$210.00$205.00$210.00$350.00
130Reference Marker Panel (646.21)EACH2$45.00$40.00$40.00$70.00
131Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH53$19.00$20.00$17.00$40.00
132Reference Marker, Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels Relocation (646.24)EACH3$16.00$15.00$15.00$66.00
133Steel Post, 2.0 lb/ft (646.32)EACH30$70.00$70.00$65.00$155.00
134Brackets for Barrier and Multidirectional Mounting (646.50)EACH4$70.00$70.00$65.00$220.00
135Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41)EACH5$60.00$50.00$125.00$43.00
136Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51)EACH4$30.00$50.00$125.00$50.00
137 (647.83001002)1$15.00$50.00$125.00$18.00
138Miscellaneous Metals (656.01)LB159$5.00$1.00$10.00$12.00
139 (665.98000103)LS1$100,000$50,000$100,000$140,000
140Cast Iron Junction Boxes (670.40)EACH8$1,800.00$3,000.00$2,600.00$1,750.00
141Photoelectric Controls (670.60)EACH2$90.00$20.00$475.00$230.00
142 (670.75040011)60$4.00$25.00$6.00$3.50
143Concrete Work Pad (5 feet x 5 feet x 4 inches) (680.5003)EACH1$900.00$2,000.00$2,500.00$775.00
144 (680.510501)EACH4$2,200.00$2,000.00$2,500.00$3,000.00
145 (680.520103)LF10$20.00$6.00$30.00$11.00
146 (680.520106)LF110$40.00$30.00$37.00$17.50
147 (680.520110)LF55$90.00$50.00$72.00$65.00
148 (680.520203)LF14$80.00$6.50$80.00$11.00
149 (680.520406)LF900$70.00$35.00$100.00$70.00
150 (680.520410)LF10$300.00$120.00$750.00$390.00
151Riser Assembly, 2-inch Diameter (680.700606)EACH1$800.00$2,500.00$1,300.00$1,300.00
152 (680.730310)LF2,600$8.00$5.00$4.50$10.00
153 (680.80620103)1$13,000$10,000$10,000$9,000.00
154 (680.90920103)1$2,500.00$2,000.00$3,000.00$1,600.00
155 (680.950104)LF800$5.00$10.00$6.25$3.50
156White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF8,926$0.80$0.50$1.00$1.25
157Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF4,496$0.80$0.50$1.00$1.25
158 (690.01000105)LS1$210,000$75,000$65,000$300,000
159 (691.04000020)21,000$1.00$1.00$1.00$1.00
160Field Change Payment (FCP) (697.03)DOL2,150,000$1.00$1.00$1.00$1.00
161Asphalt Price Adjustment (698.04)DOL10,613$1.00$1.00$1.00$1.00
162Fuel Price Adjustment (698.05)DOL3,980$1.00$1.00$1.00$1.00
163Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00
164Mobilization (699.040001)LS1$920,000$899,977$933,000$1,000,000
NYSDOT contract D265337: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of January 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way