NYSDOT contract D265381 bid tabulation
Intersection Safety Enhancements Rte 33A/Rte 259. Let by New York State DOT on January 9, 2025, Monroe, Region 04. 3 bids received; low bid $4,135,263 by Keeler Construction Co Inc.
- Owner
- New York State DOT
- Letting
- 09 JAN 2025
- Pay items
- 206
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Keeler Construction Co Inc | $4,135,263 | Low |
| 2 | Sealand Contractors Corp. | $5,339,001 | +29% |
| 3 | Cold Spring Construction Company | $5,720,707 | +38% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Keeler Construction Co Inc | 2. Sealand Contractors Corp. | 3. Cold Spring Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $4,600.00 | $5,000.00 | $15,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 7,140 | $30.00 | $43.00 | $32.00 |
| 3 | Embankment In Place (203.03) | CY | 2,350 | $26.00 | $12.80 | $17.00 |
| 4 | Select Granular Fill (203.07) | CY | 1,613 | $72.00 | $82.00 | $101.00 |
| 5 | (203.24010017) | 74 | $127.00 | $200.00 | $40.00 | |
| 6 | Trench and Culvert Excavation (206.0201) | CY | 2,708 | $39.00 | $60.00 | $150.00 |
| 7 | (206.03060005) | 147 | $40.00 | $38.00 | $100.00 | |
| 8 | Test Pit Excavation (206.05) | EACH | 6 | $1,400.00 | $1,400.00 | $2,200.00 |
| 9 | Geotextile Bedding (207.20) | SY | 15 | $7.00 | $10.00 | $45.00 |
| 10 | Seed and Mulch – Temporary (209.1003) | SY | 3,410 | $1.60 | $1.44 | $1.50 |
| 11 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 550 | $8.00 | $7.30 | $7.50 |
| 12 | Soil Stabilizers, Class IV Type A (209.2101) | SY | 3,410 | $1.50 | $1.30 | $1.30 |
| 13 | Sediment Filter Log, 12″ (209.2301) | LF | 440 | $14.00 | $15.00 | $13.50 |
| 14 | Subbase Course, Type 2 (304.12) | CY | 3,720 | $87.00 | $93.00 | $95.00 |
| 15 | (404.0001) | TON | 294 | $95.00 | $95.00 | $95.00 |
| 16 | (404.0189) | TON | 100 | $166.00 | $205.00 | $150.00 |
| 17 | (404.0982) | TON | 1,398 | $129.00 | $122.00 | $125.00 |
| 18 | (404.1989) | TON | 1,590 | $125.00 | $134.00 | $115.00 |
| 19 | (404.3789) | TON | 2,883 | $103.00 | $114.00 | $95.00 |
| 20 | Diluted Tack Coat (407.0102) | GAL | 1,581 | $10.01 | $18.00 | $12.00 |
| 21 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 8,190 | $0.80 | $1.40 | $0.95 |
| 22 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 5,855 | $4.00 | $6.75 | $6.25 |
| 23 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 2 | $1,200.00 | $3,000.00 | $1,250.00 |
| 24 | (520.05000010) | 12 | $8.00 | $25.00 | $16.00 | |
| 25 | Shields and Shoring (552.17) | SF | 34,982 | $0.01 | $0.30 | $0.90 |
| 26 | Uncoated Bar Reinforcement for Concrete Structures (556.0201) | LB | 20 | $2.50 | $30.00 | $8.50 |
| 27 | (568.12010010) | 10 | $550.00 | $400.00 | $1,200.00 | |
| 28 | Culvert-End Safety Grate (603.0101) | SF | 23 | $59.00 | $55.00 | $38.00 |
| 29 | (603.6003) | LF | 26 | $131.00 | $125.00 | $110.00 |
| 30 | (603.6004) | LF | 58 | $116.00 | $130.00 | $115.00 |
| 31 | (603.7303) | EACH | 1 | $4,030.00 | $3,300.00 | $3,500.00 |
| 32 | (603.7304) | EACH | 1 | $4,870.00 | $4,000.00 | $4,500.00 |
| 33 | (603.98040007) | 30 | $35.00 | $160.00 | $240.00 | |
| 34 | (603.9815) | LF | 1,435 | $56.00 | $85.00 | $35.00 |
| 35 | (603.9818) | LF | 471 | $64.00 | $89.00 | $39.00 |
| 36 | (604.070401) | EACH | 6 | $2,000.00 | $5,000.00 | $4,500.00 |
| 37 | (604.070402) | EACH | 6 | $2,000.00 | $5,000.00 | $4,500.00 |
| 38 | (604.070403) | EACH | 1 | $2,450.00 | $5,000.00 | $3,500.00 |
| 39 | (604.070404) | EACH | 1 | $6,850.00 | $9,000.00 | $4,750.00 |
| 40 | (604.07260011) | 1 | $1,150.00 | $2,000.00 | $3,500.00 | |
| 41 | (604.13000011) | 10 | $350.00 | $1,200.00 | $555.00 | |
| 42 | (604.300211) | LF | 16 | $965.00 | $1,170.00 | $725.00 |
| 43 | (604.300611) | LF | 5 | $1,345.00 | $1,450.00 | $825.00 |
| 44 | (604.301911) | LF | 8 | $1,190.00 | $1,290.00 | $625.00 |
| 45 | (604.302122) | LF | 108 | $910.00 | $1,000.00 | $575.00 |
| 46 | Underdrain Filter, Type I (605.0901) | CY | 155 | $155.00 | $115.00 | $115.00 |
| 47 | (605.1601) | LF | 355 | $6.30 | $15.00 | $6.00 |
| 48 | (605.1701) | LF | 3,630 | $2.30 | $8.50 | $3.50 |
| 49 | (607.41010010) | 360 | $9.00 | $8.00 | $10.00 | |
| 50 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $95.00 | $95.00 | $95.00 |
| 51 | Concrete Sidewalks and Driveways (608.0101) | CY | 83 | $940.00 | $1,500.00 | $2,450.00 |
| 52 | Accelerated Cure Sidewalks and Driveways (608.0102) | CY | 38 | $815.00 | $1,530.00 | $2,750.00 |
| 53 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 204 | $315.00 | $310.00 | $225.00 |
| 54 | (608.21000003) | 14 | $400.00 | $620.00 | $450.00 | |
| 55 | (609.0401) | LF | 3,190 | $33.00 | $96.00 | $88.00 |
| 56 | (610.10020309) | 15 | $223.00 | $300.00 | $114.00 | |
| 57 | (610.15120208) | 170 | $3.00 | $27.00 | $6.50 | |
| 58 | Turf Establishment – Performance (610.1605) | SY | 3,410 | $19.00 | $16.00 | $21.00 |
| 59 | Watering Vegetation (610.19) | 1,000 GALLONS | 5 | $525.00 | $450.00 | $250.00 |
| 60 | (611.0201) | EACH | 2 | $1,300.00 | $1,150.00 | $1,200.00 |
| 61 | (611.0231) | EACH | 1 | $800.00 | $720.00 | $750.00 |
| 62 | (611.0452) | EACH | 5 | $350.00 | $310.00 | $325.00 |
| 63 | (611.0741) | EACH | 74 | $55.00 | $47.00 | $45.00 |
| 64 | (611.19020024) | 3 | $650.00 | $550.00 | $500.00 | |
| 65 | (611.19040024) | 5 | $175.00 | $150.00 | $125.00 | |
| 66 | (611.19070024) | 74 | $26.00 | $22.00 | $20.00 | |
| 67 | Care of Trees Over 48” to 60” Diam. at Breast Height – Pruning (614.0451) | EACH | 1 | $1,260.00 | $4,200.00 | $1,200.00 |
| 68 | (614.060102) | EACH | 2 | $560.00 | $1,250.00 | $750.00 |
| 69 | (614.060104) | EACH | 1 | $730.00 | $1,600.00 | $1,000.00 |
| 70 | (614.060204) | EACH | 1 | $1,300.00 | $2,100.00 | $1,500.00 |
| 71 | (614.060304) | EACH | 1 | $2,000.00 | $2,300.00 | $2,000.00 |
| 72 | (614.060404) | EACH | 1 | $2,800.00 | $2,900.00 | $3,000.00 |
| 73 | Pre-Existing Stump Removal up to 24” diameter at 6 inches above grade (614.0701) | EACH | 2 | $300.00 | $1,400.00 | $500.00 |
| 74 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $183,000 | $509,403 | $615,000 |
| 75 | Type III Construction Barricades (619.04) | EACH | 80 | $100.00 | $250.00 | $31.00 |
| 76 | (619.080101) | LF | 8,600 | $0.84 | $1.05 | $1.00 |
| 77 | (619.080201) | EACH | 1 | $111.00 | $80.00 | $75.00 |
| 78 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 300 | $6.00 | $3.50 | $3.40 |
| 79 | Cover Existing Pavement Marking Letters or Symbols (Removable Tape) (619.0804) | EACH | 1 | $110.00 | $175.00 | $170.00 |
| 80 | (619.100101) | LF | 21,800 | $0.50 | $0.24 | $0.22 |
| 81 | (619.100103) | LF | 648 | $4.00 | $4.00 | $3.90 |
| 82 | (619.100202) | EACH | 19 | $250.00 | $220.00 | $235.00 |
| 83 | (619.111211) | WEEK | 16 | $700.00 | $1,250.00 | $600.00 |
| 84 | Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613) | MONTH | 12 | $1,390.00 | $1,250.00 | $450.00 |
| 85 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 40 | $27.00 | $150.00 | $55.00 |
| 86 | (619.2401) | LS | 1 | $18,500 | $80,000 | $50,000 |
| 87 | Pavement Patching (Force Acount) (619.2601) | DOL | 10,000 | $1.00 | $1.00 | $1.00 |
| 88 | Mailboxes (619.27) | EACH | 10 | $400.00 | $300.00 | $350.00 |
| 89 | Stone Filling (Light) (620.03) | CY | 5 | $240.00 | $350.00 | $225.00 |
| 90 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 25 | $19.00 | $50.00 | $15.00 |
| 91 | Crushed Stone (By Weight) (623.03) | TON | 495 | $23.00 | $80.00 | $115.00 |
| 92 | Survey Operations (625.01) | LS | 1 | $73,000 | $56,000 | $115,000 |
| 93 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 16 | $450.00 | $575.00 | $175.00 |
| 94 | (625.09010015) | LS | 1 | $1,000.00 | $5,000.00 | $20,000 |
| 95 | (627.50140008) | 4,070 | $6.00 | $7.50 | $3.50 | |
| 96 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 400 | $3.00 | $3.20 | $3.00 |
| 97 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $600.00 | $5,000.00 | $250.00 |
| 98 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 12 | $2,400.00 | $2,500.00 | $2,600.00 |
| 99 | Rain Gauge (637.26) | EACH | 1 | $300.00 | $125.00 | $40.00 |
| 100 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 |
| 101 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 102 | (640.11020004) | 3,000 | $1.70 | $0.79 | $0.80 | |
| 103 | (640.12020004) | 3,280 | $1.70 | $0.79 | $0.80 | |
| 104 | White Paint Reflectorized Pavement Stripes – 20 mils (640.20) | LF | 5,260 | $0.60 | $0.26 | $0.25 |
| 105 | Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21) | LF | 6,050 | $0.60 | $0.26 | $0.25 |
| 106 | White Paint Reflectorized Pavement Symbols - 20 mils (640.23) | EACH | 21 | $135.00 | $100.00 | $100.00 |
| 107 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 365 | $40.00 | $36.00 | $35.00 |
| 108 | Overhead Sign Panels (645.61) | SF | 24 | $180.00 | $165.00 | $65.00 |
| 109 | Type A Sign Posts (645.81) | EACH | 34 | $200.00 | $187.00 | $185.00 |
| 110 | Type A Sign Posts with Extra Embedment (645.8104) | EACH | 4 | $200.00 | $189.00 | $185.00 |
| 111 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 8 | $1,000.00 | $942.00 | $925.00 |
| 112 | (645.81090003) | 4 | $70.00 | $67.00 | $65.00 | |
| 113 | Breakaway Wooden Sign Posts (645.82) | EACH | 1 | $380.00 | $350.00 | $400.00 |
| 114 | Reference Marker Panel (646.21) | EACH | 10 | $43.00 | $41.00 | $40.00 |
| 115 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 6 | $10.00 | $9.50 | $9.25 |
| 116 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 9 | $25.00 | $23.00 | $23.00 |
| 117 | Steel Post, 2.0 lb/ft (646.32) | EACH | 18 | $78.00 | $74.00 | $74.00 |
| 118 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 32 | $36.00 | $34.00 | $70.00 |
| 119 | Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65) | EACH | 2 | $140.00 | $130.00 | $100.00 |
| 120 | (647.83001002) | 14 | $10.00 | $9.50 | $60.00 | |
| 121 | Welded Frame & Reticuline Grate 11 (655.1111) | EACH | 5 | $900.00 | $1,100.00 | $3,200.00 |
| 122 | Welded Frame & Reticuline Grate 22 (655.1122) | EACH | 18 | $1,300.00 | $1,500.00 | $3,600.00 |
| 123 | (662.60010004) | 1,000 | $1.00 | $1.00 | $1.00 | |
| 124 | (663.0106) | LF | 20 | $207.00 | $220.00 | $135.00 |
| 125 | (663.0108) | LF | 85 | $209.00 | $300.00 | $190.00 |
| 126 | (663.0112) | LF | 15 | $302.00 | $425.00 | $265.00 |
| 127 | (663.0116) | LF | 650 | $200.00 | $275.00 | $255.00 |
| 128 | (663.0604) | LF | 150 | $54.00 | $100.00 | $135.00 |
| 129 | (663.1006) | EACH | 2 | $2,300.00 | $3,000.00 | $3,000.00 |
| 130 | (663.1008) | EACH | 1 | $3,300.00 | $4,000.00 | $4,000.00 |
| 131 | (663.1016) | EACH | 3 | $18,000 | $21,000 | $16,000 |
| 132 | (663.1301) | EACH | 2 | $5,800.00 | $8,000.00 | $8,500.00 |
| 133 | (663.161212) | EACH | 1 | $15,000 | $15,500 | $17,000 |
| 134 | (663.161608) | EACH | 1 | $10,500 | $10,500 | $12,000 |
| 135 | (663.1808) | EACH | 8 | $2,900.00 | $750.00 | $1,500.00 |
| 136 | (663.1816) | EACH | 4 | $4,500.00 | $2,900.00 | $3,500.00 |
| 137 | Iron Water Main Fittings (3 - 8 inch diameter) (663.2001) | LB | 523 | $19.00 | $21.00 | $45.00 |
| 138 | Iron Water Main Fittings (10 - 16 inch diameter) (663.2002) | LB | 4,756 | $14.00 | $16.00 | $18.00 |
| 139 | (663.2306) | LF | 20 | $2.00 | $10.00 | $30.00 |
| 140 | (663.2308) | LF | 85 | $2.00 | $10.00 | $8.00 |
| 141 | (663.2312) | LF | 15 | $2.00 | $12.00 | $26.00 |
| 142 | (663.2316) | LF | 660 | $3.00 | $12.00 | $6.00 |
| 143 | (663.2504) | EACH | 3 | $1,500.00 | $2,600.00 | $10,000 |
| 144 | Adjust Existing Valve Box Elevation (663.33) | EACH | 24 | $400.00 | $750.00 | $850.00 |
| 145 | Adjust Existing Curb Box Elevation (663.35) | EACH | 2 | $145.00 | $600.00 | $650.00 |
| 146 | Disconnect and Cap Existing Water Main (663.40) | EACH | 1 | $5,400.00 | $3,000.00 | $4,000.00 |
| 147 | (663.4108) | LF | 25 | $34.00 | $100.00 | $52.00 |
| 148 | (663.4112) | LF | 14 | $30.00 | $105.00 | $65.00 |
| 149 | (663.4116) | LF | 30 | $60.00 | $110.00 | $55.00 |
| 150 | Remove and Dispose of Existing Water Valve & Valve Box (663.42) | EACH | 5 | $170.00 | $750.00 | $750.00 |
| 151 | Remove and Store Existing Hydrant (663.46) | EACH | 1 | $430.00 | $1,500.00 | $1,600.00 |
| 152 | (680.05010007) | 1 | $26,000 | $23,300 | $25,000 | |
| 153 | (680.05020007) | 1 | $5,200.00 | $4,700.00 | $4,000.00 | |
| 154 | (680.05040004) | 4 | $4,200.00 | $3,800.00 | $3,250.00 | |
| 155 | Pole Excavation and Concrete Foundation (680.5001) | CY | 23 | $2,000.00 | $1,850.00 | $3,750.00 |
| 156 | Concrete Base for Controller Cabinet (680.5002) | EACH | 1 | $4,300.00 | $2,900.00 | $2,000.00 |
| 157 | (680.51020009) | 3 | $260.00 | $240.00 | $1,500.00 | |
| 158 | (680.510301) | EACH | 3 | $2,200.00 | $2,000.00 | $3,500.00 |
| 159 | (680.510401) | EACH | 1 | $2,400.00 | $2,200.00 | $3,500.00 |
| 160 | (680.520106) | LF | 20 | $35.00 | $32.00 | $100.00 |
| 161 | (680.520510) | LF | 36 | $36.00 | $33.00 | $65.00 |
| 162 | (680.520706) | LF | 86 | $25.00 | $23.00 | $40.00 |
| 163 | (680.520708) | LF | 49 | $46.00 | $43.00 | $115.00 |
| 164 | Conduit Jacking or Boring (680.53) | LF | 403 | $78.00 | $71.00 | $125.00 |
| 165 | (680.6708) | EACH | 7 | $1,600.00 | $1,410.00 | $1,550.00 |
| 166 | Riser Assembly, 2-inch Diameter (680.700606) | EACH | 1 | $600.00 | $550.00 | $1,850.00 |
| 167 | (680.730514) | LF | 2,020 | $4.40 | $4.00 | $4.50 |
| 168 | (680.730714) | LF | 510 | $5.50 | $5.00 | $7.00 |
| 169 | (680.78100108) | LS | 1 | $7,300.00 | $6,600.00 | $15,000 |
| 170 | (680.80324515) | 1 | $2,000.00 | $1,850.00 | $1,750.00 | |
| 171 | (680.80324603) | 1 | $1,400.00 | $1,250.00 | $1,500.00 | |
| 172 | Traffic Signal Module - 12-inch, Red Ball, LED (680.810101) | EACH | 10 | $120.00 | $107.00 | $200.00 |
| 173 | Traffic Signal Module - 12-inch, Red Arrow, LED (680.810102) | EACH | 3 | $125.00 | $110.00 | $200.00 |
| 174 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 8 | $120.00 | $107.00 | $175.00 |
| 175 | Traffic Signal Module - 12-inch, Yellow Arrow, LED (680.810104) | EACH | 10 | $135.00 | $120.00 | $175.00 |
| 176 | Traffic Signal Module - 12-inch, Green Ball, LED (680.810105) | EACH | 8 | $130.00 | $115.00 | $175.00 |
| 177 | Traffic Signal Module - 12-inch, Green Arrow, LED (680.810106) | EACH | 4 | $140.00 | $125.00 | $250.00 |
| 178 | Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601) | EACH | 43 | $230.00 | $205.00 | $225.00 |
| 179 | (680.81210004) | 13 | $520.00 | $465.00 | $625.00 | |
| 180 | Pedestrian Signal Module - 12-inch, Bi-Modal Hand/Man Symbols, LED (680.813105) | EACH | 8 | $290.00 | $260.00 | $850.00 |
| 181 | Pedestrian Signal Section - Polycarbonate, Type I, 12-inch (680.813106) | EACH | 16 | $320.00 | $290.00 | $250.00 |
| 182 | Pedestrian Signal Post Top Mount Assembly (680.8142) | EACH | 8 | $1,250.00 | $1,120.00 | $275.00 |
| 183 | Pedestrian Signal Module - 12-inch Countdown Timer, LED (680.815001) | EACH | 8 | $300.00 | $260.00 | $4,000.00 |
| 184 | (680.8151) | EACH | 8 | $1,300.00 | $1,180.00 | $1,850.00 |
| 185 | Backplates for Traffic Signal Heads (680.8199) | EACH | 13 | $400.00 | $365.00 | $275.00 |
| 186 | (680.8205) | EACH | 6 | $620.00 | $560.00 | $1,050.00 |
| 187 | Meter Pan (680.9402) | EACH | 1 | $1,750.00 | $1,570.00 | $1,250.00 |
| 188 | Install Electrical Disconnect/Generator Transfer Switch (680.9499) | EACH | 1 | $1,000.00 | $910.00 | $1,250.00 |
| 189 | (680.950106) | LF | 60 | $3.50 | $3.00 | $23.00 |
| 190 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $11.50 | $11.50 | $11.50 |
| 191 | (680.99130004) | 4 | $5,800.00 | $5,250.00 | $10,000 | |
| 192 | (683.94000304) | 806 | $6.50 | $5.80 | $23.00 | |
| 193 | (683.95060104) | 4 | $750.00 | $680.00 | $1,350.00 | |
| 194 | (683.97940108) | LS | 1 | $10,000 | $10,000 | $10,000 |
| 195 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 5,260 | $1.10 | $0.78 | $1.00 |
| 196 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 6,050 | $1.10 | $0.78 | $1.00 |
| 197 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 3,000 | $2.80 | $3.67 | $2.65 |
| 198 | Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204) | LF | 3,280 | $2.80 | $3.67 | $2.65 |
| 199 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 21 | $250.00 | $205.00 | $240.00 |
| 200 | Yellow Thermoplastic Reflectorized Pavement Stripes (687.0201) | LF | 160 | $22.00 | $2.65 | $2.65 |
| 201 | (691.04000020) | 29,400 | $1.00 | $1.00 | $1.00 | |
| 202 | Field Change Payment (FCP) (697.03) | DOL | 326,000 | $1.00 | $1.00 | $1.00 |
| 203 | Asphalt Price Adjustment (698.04) | DOL | 5,109 | $1.00 | $1.00 | $1.00 |
| 204 | Fuel Price Adjustment (698.05) | DOL | 1,794 | $1.00 | $1.00 | $1.00 |
| 205 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 206 | Mobilization (699.040001) | LS | 1 | $159,000 | $205,000 | $220,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.