NYSDOT contract D265381 bid tabulation

Intersection Safety Enhancements Rte 33A/Rte 259. Let by New York State DOT on January 9, 2025, Monroe, Region 04. 3 bids received; low bid $4,135,263 by Keeler Construction Co Inc.

Owner
New York State DOT
Letting
09 JAN 2025
Pay items
206
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Keeler Construction Co Inc$4,135,263Low
2Sealand Contractors Corp.$5,339,001+29%
3Cold Spring Construction Company$5,720,707+38%
NYSDOT contract D265381: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Keeler Construction Co Inc2. Sealand Contractors Corp.3. Cold Spring Construction Company
1Clearing and Grubbing (201.06)LS1$4,600.00$5,000.00$15,000
2Unclassified Excavation and Disposal (203.02)CY7,140$30.00$43.00$32.00
3Embankment In Place (203.03)CY2,350$26.00$12.80$17.00
4Select Granular Fill (203.07)CY1,613$72.00$82.00$101.00
5 (203.24010017)74$127.00$200.00$40.00
6Trench and Culvert Excavation (206.0201)CY2,708$39.00$60.00$150.00
7 (206.03060005)147$40.00$38.00$100.00
8Test Pit Excavation (206.05)EACH6$1,400.00$1,400.00$2,200.00
9Geotextile Bedding (207.20)SY15$7.00$10.00$45.00
10Seed and Mulch – Temporary (209.1003)SY3,410$1.60$1.44$1.50
11Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301)SY550$8.00$7.30$7.50
12Soil Stabilizers, Class IV Type A (209.2101)SY3,410$1.50$1.30$1.30
13Sediment Filter Log, 12″ (209.2301)LF440$14.00$15.00$13.50
14Subbase Course, Type 2 (304.12)CY3,720$87.00$93.00$95.00
15 (404.0001)TON294$95.00$95.00$95.00
16 (404.0189)TON100$166.00$205.00$150.00
17 (404.0982)TON1,398$129.00$122.00$125.00
18 (404.1989)TON1,590$125.00$134.00$115.00
19 (404.3789)TON2,883$103.00$114.00$95.00
20Diluted Tack Coat (407.0102)GAL1,581$10.01$18.00$12.00
21Asphalt Pavement Joint Adhesive (418.7603)LF8,190$0.80$1.40$0.95
22Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY5,855$4.00$6.75$6.25
23PCC Foundation for Pavement, PEM Concrete (503.1013)CY2$1,200.00$3,000.00$1,250.00
24 (520.05000010)12$8.00$25.00$16.00
25Shields and Shoring (552.17)SF34,982$0.01$0.30$0.90
26Uncoated Bar Reinforcement for Concrete Structures (556.0201)LB20$2.50$30.00$8.50
27 (568.12010010)10$550.00$400.00$1,200.00
28Culvert-End Safety Grate (603.0101)SF23$59.00$55.00$38.00
29 (603.6003)LF26$131.00$125.00$110.00
30 (603.6004)LF58$116.00$130.00$115.00
31 (603.7303)EACH1$4,030.00$3,300.00$3,500.00
32 (603.7304)EACH1$4,870.00$4,000.00$4,500.00
33 (603.98040007)30$35.00$160.00$240.00
34 (603.9815)LF1,435$56.00$85.00$35.00
35 (603.9818)LF471$64.00$89.00$39.00
36 (604.070401)EACH6$2,000.00$5,000.00$4,500.00
37 (604.070402)EACH6$2,000.00$5,000.00$4,500.00
38 (604.070403)EACH1$2,450.00$5,000.00$3,500.00
39 (604.070404)EACH1$6,850.00$9,000.00$4,750.00
40 (604.07260011)1$1,150.00$2,000.00$3,500.00
41 (604.13000011)10$350.00$1,200.00$555.00
42 (604.300211)LF16$965.00$1,170.00$725.00
43 (604.300611)LF5$1,345.00$1,450.00$825.00
44 (604.301911)LF8$1,190.00$1,290.00$625.00
45 (604.302122)LF108$910.00$1,000.00$575.00
46Underdrain Filter, Type I (605.0901)CY155$155.00$115.00$115.00
47 (605.1601)LF355$6.30$15.00$6.00
48 (605.1701)LF3,630$2.30$8.50$3.50
49 (607.41010010)360$9.00$8.00$10.00
50Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT1$95.00$95.00$95.00
51Concrete Sidewalks and Driveways (608.0101)CY83$940.00$1,500.00$2,450.00
52Accelerated Cure Sidewalks and Driveways (608.0102)CY38$815.00$1,530.00$2,750.00
53Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON204$315.00$310.00$225.00
54 (608.21000003)14$400.00$620.00$450.00
55 (609.0401)LF3,190$33.00$96.00$88.00
56 (610.10020309)15$223.00$300.00$114.00
57 (610.15120208)170$3.00$27.00$6.50
58Turf Establishment – Performance (610.1605)SY3,410$19.00$16.00$21.00
59Watering Vegetation (610.19)1,000 GALLONS5$525.00$450.00$250.00
60 (611.0201)EACH2$1,300.00$1,150.00$1,200.00
61 (611.0231)EACH1$800.00$720.00$750.00
62 (611.0452)EACH5$350.00$310.00$325.00
63 (611.0741)EACH74$55.00$47.00$45.00
64 (611.19020024)3$650.00$550.00$500.00
65 (611.19040024)5$175.00$150.00$125.00
66 (611.19070024)74$26.00$22.00$20.00
67Care of Trees Over 48” to 60” Diam. at Breast Height – Pruning (614.0451)EACH1$1,260.00$4,200.00$1,200.00
68 (614.060102)EACH2$560.00$1,250.00$750.00
69 (614.060104)EACH1$730.00$1,600.00$1,000.00
70 (614.060204)EACH1$1,300.00$2,100.00$1,500.00
71 (614.060304)EACH1$2,000.00$2,300.00$2,000.00
72 (614.060404)EACH1$2,800.00$2,900.00$3,000.00
73Pre-Existing Stump Removal up to 24” diameter at 6 inches above grade (614.0701)EACH2$300.00$1,400.00$500.00
74Basic Work Zone Traffic Control (619.01)LS1$183,000$509,403$615,000
75Type III Construction Barricades (619.04)EACH80$100.00$250.00$31.00
76 (619.080101)LF8,600$0.84$1.05$1.00
77 (619.080201)EACH1$111.00$80.00$75.00
78Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803)LF300$6.00$3.50$3.40
79Cover Existing Pavement Marking Letters or Symbols (Removable Tape) (619.0804)EACH1$110.00$175.00$170.00
80 (619.100101)LF21,800$0.50$0.24$0.22
81 (619.100103)LF648$4.00$4.00$3.90
82 (619.100202)EACH19$250.00$220.00$235.00
83 (619.111211)WEEK16$700.00$1,250.00$600.00
84Maintain Traffic Signal Equipment (Requirement C) Intersection (619.1613)MONTH12$1,390.00$1,250.00$450.00
85Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF40$27.00$150.00$55.00
86 (619.2401)LS1$18,500$80,000$50,000
87Pavement Patching (Force Acount) (619.2601)DOL10,000$1.00$1.00$1.00
88Mailboxes (619.27)EACH10$400.00$300.00$350.00
89Stone Filling (Light) (620.03)CY5$240.00$350.00$225.00
90Clean, Grade and Shape Existing Roadside Section (621.05)LF25$19.00$50.00$15.00
91Crushed Stone (By Weight) (623.03)TON495$23.00$80.00$115.00
92Survey Operations (625.01)LS1$73,000$56,000$115,000
93Steel Pin and Cap Right of Way Markers (625.05)EACH16$450.00$575.00$175.00
94 (625.09010015)LS1$1,000.00$5,000.00$20,000
95 (627.50140008)4,070$6.00$7.50$3.50
96Cleaning and Preparation of Pavement Surfaces-Lines (635.0103)LF400$3.00$3.20$3.00
97Concrete Cylinder Curing Equipment (637.04)EACH1$600.00$5,000.00$250.00
98Engineer’s Field Office – Type 2 (637.12)MONTH12$2,400.00$2,500.00$2,600.00
99Rain Gauge (637.26)EACH1$300.00$125.00$40.00
100Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00
101Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00
102 (640.11020004)3,000$1.70$0.79$0.80
103 (640.12020004)3,280$1.70$0.79$0.80
104White Paint Reflectorized Pavement Stripes – 20 mils (640.20)LF5,260$0.60$0.26$0.25
105Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21)LF6,050$0.60$0.26$0.25
106White Paint Reflectorized Pavement Symbols - 20 mils (640.23)EACH21$135.00$100.00$100.00
107Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF365$40.00$36.00$35.00
108Overhead Sign Panels (645.61)SF24$180.00$165.00$65.00
109Type A Sign Posts (645.81)EACH34$200.00$187.00$185.00
110Type A Sign Posts with Extra Embedment (645.8104)EACH4$200.00$189.00$185.00
111High-Capacity Type A Sign Posts with Soil Plates Only (645.8106)EACH8$1,000.00$942.00$925.00
112 (645.81090003)4$70.00$67.00$65.00
113Breakaway Wooden Sign Posts (645.82)EACH1$380.00$350.00$400.00
114Reference Marker Panel (646.21)EACH10$43.00$41.00$40.00
115Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH6$10.00$9.50$9.25
116Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH9$25.00$23.00$23.00
117Steel Post, 2.0 lb/ft (646.32)EACH18$78.00$74.00$74.00
118Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH32$36.00$34.00$70.00
119Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65)EACH2$140.00$130.00$100.00
120 (647.83001002)14$10.00$9.50$60.00
121Welded Frame & Reticuline Grate 11 (655.1111)EACH5$900.00$1,100.00$3,200.00
122Welded Frame & Reticuline Grate 22 (655.1122)EACH18$1,300.00$1,500.00$3,600.00
123 (662.60010004)1,000$1.00$1.00$1.00
124 (663.0106)LF20$207.00$220.00$135.00
125 (663.0108)LF85$209.00$300.00$190.00
126 (663.0112)LF15$302.00$425.00$265.00
127 (663.0116)LF650$200.00$275.00$255.00
128 (663.0604)LF150$54.00$100.00$135.00
129 (663.1006)EACH2$2,300.00$3,000.00$3,000.00
130 (663.1008)EACH1$3,300.00$4,000.00$4,000.00
131 (663.1016)EACH3$18,000$21,000$16,000
132 (663.1301)EACH2$5,800.00$8,000.00$8,500.00
133 (663.161212)EACH1$15,000$15,500$17,000
134 (663.161608)EACH1$10,500$10,500$12,000
135 (663.1808)EACH8$2,900.00$750.00$1,500.00
136 (663.1816)EACH4$4,500.00$2,900.00$3,500.00
137Iron Water Main Fittings (3 - 8 inch diameter) (663.2001)LB523$19.00$21.00$45.00
138Iron Water Main Fittings (10 - 16 inch diameter) (663.2002)LB4,756$14.00$16.00$18.00
139 (663.2306)LF20$2.00$10.00$30.00
140 (663.2308)LF85$2.00$10.00$8.00
141 (663.2312)LF15$2.00$12.00$26.00
142 (663.2316)LF660$3.00$12.00$6.00
143 (663.2504)EACH3$1,500.00$2,600.00$10,000
144Adjust Existing Valve Box Elevation (663.33)EACH24$400.00$750.00$850.00
145Adjust Existing Curb Box Elevation (663.35)EACH2$145.00$600.00$650.00
146Disconnect and Cap Existing Water Main (663.40)EACH1$5,400.00$3,000.00$4,000.00
147 (663.4108)LF25$34.00$100.00$52.00
148 (663.4112)LF14$30.00$105.00$65.00
149 (663.4116)LF30$60.00$110.00$55.00
150Remove and Dispose of Existing Water Valve & Valve Box (663.42)EACH5$170.00$750.00$750.00
151Remove and Store Existing Hydrant (663.46)EACH1$430.00$1,500.00$1,600.00
152 (680.05010007)1$26,000$23,300$25,000
153 (680.05020007)1$5,200.00$4,700.00$4,000.00
154 (680.05040004)4$4,200.00$3,800.00$3,250.00
155Pole Excavation and Concrete Foundation (680.5001)CY23$2,000.00$1,850.00$3,750.00
156Concrete Base for Controller Cabinet (680.5002)EACH1$4,300.00$2,900.00$2,000.00
157 (680.51020009)3$260.00$240.00$1,500.00
158 (680.510301)EACH3$2,200.00$2,000.00$3,500.00
159 (680.510401)EACH1$2,400.00$2,200.00$3,500.00
160 (680.520106)LF20$35.00$32.00$100.00
161 (680.520510)LF36$36.00$33.00$65.00
162 (680.520706)LF86$25.00$23.00$40.00
163 (680.520708)LF49$46.00$43.00$115.00
164Conduit Jacking or Boring (680.53)LF403$78.00$71.00$125.00
165 (680.6708)EACH7$1,600.00$1,410.00$1,550.00
166Riser Assembly, 2-inch Diameter (680.700606)EACH1$600.00$550.00$1,850.00
167 (680.730514)LF2,020$4.40$4.00$4.50
168 (680.730714)LF510$5.50$5.00$7.00
169 (680.78100108)LS1$7,300.00$6,600.00$15,000
170 (680.80324515)1$2,000.00$1,850.00$1,750.00
171 (680.80324603)1$1,400.00$1,250.00$1,500.00
172Traffic Signal Module - 12-inch, Red Ball, LED (680.810101)EACH10$120.00$107.00$200.00
173Traffic Signal Module - 12-inch, Red Arrow, LED (680.810102)EACH3$125.00$110.00$200.00
174Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103)EACH8$120.00$107.00$175.00
175Traffic Signal Module - 12-inch, Yellow Arrow, LED (680.810104)EACH10$135.00$120.00$175.00
176Traffic Signal Module - 12-inch, Green Ball, LED (680.810105)EACH8$130.00$115.00$175.00
177Traffic Signal Module - 12-inch, Green Arrow, LED (680.810106)EACH4$140.00$125.00$250.00
178Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601)EACH43$230.00$205.00$225.00
179 (680.81210004)13$520.00$465.00$625.00
180Pedestrian Signal Module - 12-inch, Bi-Modal Hand/Man Symbols, LED (680.813105)EACH8$290.00$260.00$850.00
181Pedestrian Signal Section - Polycarbonate, Type I, 12-inch (680.813106)EACH16$320.00$290.00$250.00
182Pedestrian Signal Post Top Mount Assembly (680.8142)EACH8$1,250.00$1,120.00$275.00
183Pedestrian Signal Module - 12-inch Countdown Timer, LED (680.815001)EACH8$300.00$260.00$4,000.00
184 (680.8151)EACH8$1,300.00$1,180.00$1,850.00
185Backplates for Traffic Signal Heads (680.8199)EACH13$400.00$365.00$275.00
186 (680.8205)EACH6$620.00$560.00$1,050.00
187Meter Pan (680.9402)EACH1$1,750.00$1,570.00$1,250.00
188Install Electrical Disconnect/Generator Transfer Switch (680.9499)EACH1$1,000.00$910.00$1,250.00
189 (680.950106)LF60$3.50$3.00$23.00
190Performance Concrete Quality Adjustment (680.99)QUALITY UNIT1$11.50$11.50$11.50
191 (680.99130004)4$5,800.00$5,250.00$10,000
192 (683.94000304)806$6.50$5.80$23.00
193 (683.95060104)4$750.00$680.00$1,350.00
194 (683.97940108)LS1$10,000$10,000$10,000
195White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF5,260$1.10$0.78$1.00
196Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF6,050$1.10$0.78$1.00
197White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF3,000$2.80$3.67$2.65
198Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204)LF3,280$2.80$3.67$2.65
199White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404)EACH21$250.00$205.00$240.00
200Yellow Thermoplastic Reflectorized Pavement Stripes (687.0201)LF160$22.00$2.65$2.65
201 (691.04000020)29,400$1.00$1.00$1.00
202Field Change Payment (FCP) (697.03)DOL326,000$1.00$1.00$1.00
203Asphalt Price Adjustment (698.04)DOL5,109$1.00$1.00$1.00
204Fuel Price Adjustment (698.05)DOL1,794$1.00$1.00$1.00
205Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
206Mobilization (699.040001)LS1$159,000$205,000$220,000
NYSDOT contract D265381: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of January 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy