NYSDOT contract D265389 bid tabulation

Large Culvert Rehabilitation Project. Let by New York State DOT on July 10, 2025, Broome, Otsego, Region 09. 7 bids received; low bid $9,074,029 by Vector Construction Corp.

Owner
New York State DOT
Letting
10 JUL 2025
Pay items
127
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Vector Construction Corp$9,074,029Low
2R De Vincentis Construction Inc$9,266,000+2.0%
3Economy Paving Co Inc$9,975,954+10%
4Lancaster Development and Tully Construction Co LLC$9,993,781+10%
5Gorick Construction Co Inc$10,137,552+12%
6Slate Hill Constructors Inc$10,491,026+16%
7Rutledge Excavating Inc$15,849,433+75%
NYSDOT contract D265389: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Vector Construction Corp2. R De Vincentis Construction Inc3. Economy Paving Co Inc4. Lancaster Development and Tully Construction Co LLC5. Gorick Construction Co Inc6. Slate Hill Constructors Inc
1Clearing and Grubbing (201.07)ACRE2.20$30,000$34,500$1,000.00$15,000$65,000$15,000
2 (203.01990006)494$55.00$97.00$25.00$180.00$72.00$120.00
3Unclassified Excavation and Disposal (203.02)CY469$50.00$45.00$5.00$50.00$16.00$56.00
4Embankment In Place (203.03)CY546$50.00$47.00$5.00$55.00$48.50$45.00
5Select Granular Fill (203.07)CY417$50.00$88.00$55.00$129.00$48.00$80.00
6Structure Excavation (206.01)CY2,957$20.00$33.00$5.00$70.40$18.00$56.00
7Geotextile Bedding (207.20)SY266$5.00$13.00$5.00$9.50$4.00$8.00
8Geotextile Separation (207.21)SY1,869$5.00$5.00$1.50$5.85$1.50$4.00
9Seed and Mulch – Temporary (209.1003)SY57$13.00$6.00$10.00$18.70$15.50$6.00
10 (209.11000001)1$600.00$450.00$500.00$738.00$900.00$30.00
11Silt Fence - Temporary (209.13)LF2,899$6.00$3.50$0.80$14.40$4.00$10.00
12Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901)SY4,390$5.00$5.50$5.00$7.55$8.50$6.00
13Soil Stabilizers, Class IV Type C (209.2103)SY6,108$2.20$2.50$2.00$3.40$1.00$3.00
14Stabilized Construction Access (209.22)SY1,181$25.00$42.00$55.00$81.60$24.00$34.00
15Sediment Filter Log, 18″ to 20″ (209.2302)LF199$11.00$30.00$10.00$27.20$12.00$40.00
16Subbase Course, Type 1 (304.11)CY125$120.00$105.00$50.00$149.00$64.00$85.00
17Subbase Course, Optional Type (304.15)CY1,091$55.00$74.00$45.00$123.00$62.00$85.00
18Interim Steel Sheeting (552.15)SF21,507$28.00$51.00$20.00$30.00$58.00$30.00
19 (553.020001)EACH2$1,000.00$12,000$1,000.00$14,000$1,260.00$1.00
20 (553.020002)EACH2$1,000.00$11,000$1,000.00$14,000$1,260.00$1.00
21 (553.020003)EACH2$1,000.00$12,000$1,000.00$14,000$1,260.00$1.00
22 (553.020004)EACH2$1,000.00$10,000$1,000.00$14,000$1,260.00$1.00
23 (553.020005)EACH2$1,000.00$18,000$1,000.00$14,000$1,260.00$1.00
24 (553.020006)EACH2$1,000.00$10,000$1,000.00$14,000$1,260.00$1.00
25 (553.020007)EACH2$1,000.00$9,000.00$1,000.00$14,000$1,260.00$1.00
26 (553.020008)EACH1$1,000.00$7,000.00$1,000.00$14,000$2,050.00$1.00
27 (553.020009)EACH2$1,000.00$7,000.00$1,000.00$14,000$1,260.00$1.00
28 (553.020010)EACH2$1.00$10,000$1,000.00$14,000$1,260.00$1.00
29 (553.020011)EACH4$1,000.00$11,000$1,000.00$14,000$1,260.00$1.00
30 (553.030001)EACH1$20,000$10,000$1,000.00$5,000.00$33,000$1.00
31 (553.030002)EACH1$20,000$12,000$1,000.00$5,000.00$33,000$1.00
32 (553.030003)EACH1$20,000$10,000$1,000.00$5,000.00$33,000$1.00
33 (553.030004)EACH1$20,000$8,000.00$1,000.00$5,000.00$33,000$1.00
34 (553.030005)EACH1$20,000$9,000.00$1,000.00$5,000.00$18,000$1.00
35 (553.030006)EACH1$20,000$9,000.00$1,000.00$5,000.00$23,000$1.00
36 (553.030007)EACH1$20,000$21,000$1,000.00$5,000.00$45,000$1.00
37 (553.030008)EACH1$20,000$21,000$1,000.00$5,000.00$38,000$1.00
38 (553.030009)EACH1$15,000$13,000$1,000.00$5,000.00$23,000$1.00
39 (553.030010)EACH1$1.00$14,000$1,000.00$5,000.00$33,000$1.00
40 (553.030011)EACH2$20,000$8,000.00$1,000.00$5,000.00$16,000$1.00
41 (555.97130016)28$4,000.00$7,000.00$5,500.00$7,500.00$3,300.00$5,500.00
42Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$17.50$17.50$17.50$17.50$17.50$17.50
43Transition Bridge Railing (568.70)LF34$220.00$232.00$200.00$275.00$8,800.00$230.00
44Structural Paving of Inverts with Portland Cement Concrete (602.2002)SF6,097$65.00$35.00$170.00$101.00$104.00$75.00
45Lining Culvert with Shotcrete (602.2101)SF393$165.00$180.00$190.00$185.00$76.00$200.00
46 (602.2748)LF190$1,200.00$823.00$1,350.00$627.00$749.00$650.00
47 (602.2760)LF153$1,400.00$775.00$1,400.00$948.00$966.00$800.00
48 (602.2772)LF225$1,500.00$1,020.00$1,600.00$952.00$1,128.00$820.00
49 (602.431001)SF2,176$170.00$147.00$215.00$182.00$175.00$155.00
50 (602.431002)SF2,461$170.00$163.00$215.00$193.00$195.00$155.00
51 (602.431003)SF2,503$170.00$165.00$215.00$192.00$192.00$155.00
52 (602.431004)SF1,909$210.00$220.00$225.00$221.00$220.00$200.00
53 (602.435001)SF4,306$145.00$110.00$150.00$99.90$125.00$105.00
54 (603.172212)EACH1$6,000.00$7,500.00$5,000.00$6,000.00$4,200.00$5,000.00
55 (603.67000001)294$1,600.00$2,195.00$1,850.00$1,600.00$1,750.00$1,650.00
56Box Beam Guide Railing (606.10)LF10,251$52.00$52.00$50.00$62.70$65.00$50.00
57Box Beam End Piece (606.120101)EACH4$700.00$688.00$650.00$836.00$2,050.00$670.00
58Box Beam Guide Railing End Assembly Type I with 18 ft Extension (606.120103)EACH2$6,000.00$5,500.00$5,000.00$6,640.00$6,200.00$5,400.00
59Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH4$2,200.00$2,250.00$2,000.00$2,650.00$2,500.00$2,200.00
60Resetting Box Beam Guide Railing (New Posts) (606.5348)LF2,064$32.00$34.00$30.00$40.70$41.00$33.00
61Resetting Box Beam Guide Rail Turned-Down Terminal (606.5920)EACH3$700.00$710.00$650.00$856.00$85.00$685.00
62Resetting Box Beam Guide Rail Energy-Absorbing Terminal (606.5921)EACH1$2,300.00$2,425.00$2,250.00$2,920.00$3,000.00$2,400.00
63Removing and Disposing Cable Guide Railing (606.70)LF2,390$1.75$2.00$15.00$7.15$2.00$5.00
64Removing and Disposing Corrugated Beam Guide Railing (606.71)LF7,901$2.20$2.25$10.00$2.80$2.50$2.30
65Removing and Disposing Box Beam Guide Railing (606.73)LF40$5.00$2.35$10.00$2.90$2.80$2.40
66Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH8$250.00$270.00$250.00$929.00$300.00$260.00
67Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910)EACH3$230.00$250.00$250.00$305.00$280.00$250.00
68Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH2$32.00$33.00$50.00$424.00$50.00$40.00
69Transition Between Box Beam Guide Rail and Single Slope Half Section Concrete Barrier (One or Two Way Operation) (606.8803)EACH1$8,000.00$8,200.00$5,000.00$16,600$9,000.00$14,000
70Right-of Way Fencing (607.19)LF452$50.00$51.00$50.00$63.00$8.00$80.00
71 (607.41010010)267$6.00$8.00$5.00$11.50$3.00$30.00
72 (607.99980007)452$8.00$15.00$10.00$18.60$1.00$22.00
73Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT3$90.00$90.00$90.00$90.00$90.00$90.00
74Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON694$235.00$303.00$195.00$200.00$289.00$310.00
75Weed Removal (610.13)SY14,152$0.40$0.45$0.10$0.53$2.25$0.75
76Topsoil – Reuse On-Site Materials (610.1401)CY1,046$35.00$72.00$5.00$105.00$55.00$45.00
77Topsoil - Roadside (610.1402)CY1,025$45.00$110.00$10.00$126.00$98.00$85.00
78Topsoil - Lawns (610.1403)CY26$120.00$155.00$65.00$347.00$150.00$90.00
79Topsoil - Special Planting Mix (610.1404)CY75$150.00$165.00$65.00$199.00$175.00$100.00
80Turf Establishment - Roadside (610.1601)SY13,396$1.60$1.75$1.50$2.75$7.75$1.75
81Turf Establishment -Lawns (610.1602)SY93$3.00$3.30$3.00$5.80$22.00$3.25
82 (610.16092824)904$3.00$3.30$3.00$4.75$8.00$3.25
83Watering Vegetation (610.19)1,000 GALLONS2,238$2.00$2.25$2.00$2.00$62.00$2.25
84Mowing (610.21)SY15,273$0.50$0.60$0.50$0.66$1.00$0.75
85 (611.0151)EACH14$820.00$880.00$1,000.00$1,060.00$1,300.00$840.00
86 (611.0292)EACH31$720.00$770.00$750.00$929.00$662.00$735.00
87 (611.0351)EACH17$520.00$550.00$500.00$663.00$595.00$525.00
88 (611.19010024)14$20.00$22.00$20.00$26.50$308.00$21.00
89 (611.19020024)31$10.00$11.00$10.00$13.30$220.00$10.50
90 (611.19030024)17$5.00$5.50$5.00$6.65$212.00$5.25
91 (613.04000001)572$35.00$62.00$5.00$104.00$43.00$80.00
92 (614.060504)EACH2$1,200.00$4,000.00$3,000.00$5,390.00$5,500.00$2,350.00
93 (616.08000024)335$12.00$14.00$10.00$15.90$31.00$13.00
94 (617.10000024)59$75.00$180.00$10.00$126.00$232.00$115.00
95 (617.11000024)LS1$3,500.00$7,500.00$1,000.00$3,080.00$2,800.00$5,000.00
96 (617.11100009)LS1$3,500.00$7,500.00$1,000.00$2,940.00$3,100.00$5,000.00
97Basic Work Zone Traffic Control (619.01)LS1$940,000$426,000$1,215,000$243,000$335,500$2,600,000
98Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF3,127$40.00$62.00$50.00$76.90$50.00$65.00
99Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802)EACH3$6,500.00$7,500.00$5,000.00$16,000$2,050.00$7,000.00
100Stone Filling (Light) (620.03)CY15$110.00$162.00$155.00$221.00$140.00$145.00
101Stone Filling (Heavy) (620.05)CY798$145.00$154.00$165.00$169.00$112.00$155.00
102Bedding Material, Type 1 (620.0801)CY502$96.00$130.00$145.00$185.00$58.00$105.00
103Bedding Material, Type 2 (620.0802)CY37$86.00$240.00$155.00$159.00$88.00$130.00
104 (620.14020009)1,504$145.00$166.00$165.00$154.00$120.00$160.00
105 (620.29030006)80$150.00$165.00$115.00$180.00$95.00$200.00
106 (621.05020004)13,017$4.50$4.00$5.00$5.20$4.00$4.50
107Survey Operations (625.01)LS1$55,000$28,000$20,000$210,382$34,000$30,000
108 (625.09010015)LS1$1,000.00$16,500$1,000.00$44,800$1,400.00$2,000.00
109Concrete Cylinder Curing Equipment (637.04)EACH1$4,000.00$5,000.00$5,000.00$4,440.00$2,500.00$2,500.00
110Engineer’s Field Office – Type 2 (637.12)MONTH26$2,200.00$1,900.00$2,500.00$7,520.00$2,500.00$2,600.00
111Office Technology and Supplies (637.34)DOL500$1.00$1.00$1.00$1.00$1.00$1.00
112Construction Testing supplies – Consumables (637.36)DOL500$1.00$1.00$1.00$1.00$1.00$1.00
113 (637.41000115)26$75.00$175.00$100.00$143.00$250.00$110.00
114 (637.41000215)26$75.00$175.00$100.00$143.00$250.00$110.00
115Ground-Mounted Sign Panels without Z-bars (645.5101)SF1$67.00$73.00$100.00$121.00$110.00$100.00
116Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF4$60.00$67.00$100.00$76.90$72.00$62.00
117Type A Sign Posts (645.81)EACH2$250.00$250.00$250.00$225.00$50.00$240.00
118Reference Marker Panel (646.21)EACH21$45.00$47.00$50.00$55.70$52.00$45.00
119Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH34$16.00$17.00$15.00$19.90$18.50$17.00
120Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH90$22.00$24.00$20.00$27.20$26.00$22.00
121Steel Post, 2.0 lb/ft (646.32)EACH95$83.00$95.00$100.00$113.00$100.00$95.00
122Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH72$11.00$12.00$10.00$13.30$14.00$11.00
123Field Change Payment (FCP) (697.03)DOL670,000$1.00$1.00$1.00$1.00$1.00$1.00
124Asphalt Price Adjustment (698.04)DOL1,870$1.00$1.00$1.00$1.00$1.00$1.00
125Fuel Price Adjustment (698.05)DOL4,323$1.00$1.00$1.00$1.00$1.00$1.00
126Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
127Mobilization (699.040001)LS1$340,000$351,505$311,682$383,452$345,000$350,000
NYSDOT contract D265389: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of July 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way