NYSDOT contract D265425 bid tabulation

Pavement Resurfacing and Drainage Rehabilitation I-490. Let by New York State DOT on February 27, 2025, Monroe, Region 04. 3 bids received; low bid $23,927,391 by Cold Spring Construction Company.

Owner
New York State DOT
Letting
27 FEB 2025
Pay items
204
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Cold Spring Construction Company$23,927,391Low
2Villager Construction Inc$26,890,000+12%
3Sealand Contractors Corp.$28,574,000+19%
NYSDOT contract D265425: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Cold Spring Construction Company2. Villager Construction Inc3. Sealand Contractors Corp.
1 (201.07000004)33,044$5.25$5.50$5.50
2 (201.07010004)6$1,450.00$1,550.00$2,500.00
3Unclassified Excavation and Disposal (203.02)CY2,691$45.00$160.00$120.00
4Embankment In Place (203.03)CY33$10.00$130.00$150.00
5Select Granular Fill (203.07)CY49$63.00$78.00$200.00
6 (203.24010017)618$58.00$250.00$150.00
7Controlled Low Strength Material (CLSM) (204.01)CY5$960.00$720.00$1,500.00
8Trench and Culvert Excavation (206.0201)CY192$95.00$270.00$180.00
9Conduit Excavation and Backfill including Surface Restoration (206.03)LF610$30.00$38.00$37.00
10Test Pit Excavation (206.05)EACH14$2,000.00$1,500.00$2,000.00
11Geotextile Separation (207.21)SY61$3.75$5.00$12.00
12Geotextile Drainage (207.22)SY302$3.25$2.00$5.00
13Mulch – Temporary (209.100101)SY7,000$0.90$1.00$0.91
14Seed and Mulch – Temporary (209.1003)SY16,500$0.90$1.00$0.91
15Rolled Erosion Control Product, Class I Type A, Short Term (209.1801)SY1,750$5.00$5.40$4.95
16Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301)SY500$8.50$9.00$8.35
17Soil Stabilizers, Class IV Type A (209.2101)SY9,183$1.00$1.10$1.00
18 (209.23010009)200$16.50$18.00$25.00
19Subbase Course, Type 2 (304.12)CY220$160.00$200.00$300.00
20 (404.0001)TON1,422$95.00$95.00$95.00
21Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT1,422$95.00$95.00$95.00
22Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT1,342$95.00$95.00$95.00
23 (404.0189)TON269$165.00$230.00$275.00
24 (404.1989)TON4$400.00$330.00$1,200.00
25 (404.3789)TON7$420.00$220.00$1,000.00
26 (406.1252)TON28,418$141.00$140.00$145.00
27Diluted Tack Coat (407.0102)GAL19,379$9.00$7.20$9.40
28Asphalt Pavement Joint Adhesive (418.7603)LF177,133$0.75$0.50$1.15
29Production Cold-Mill Surface Planing of Bituminous Concrete (490.15)SY242,229$3.05$3.70$4.60
30PCC Foundation for Pavement, PEM Concrete (503.1013)CY31$1,650.00$700.00$2,000.00
31 (553.030001)EACH1$1.00$5,000.00$5,000.00
32Concrete for Structures, Performance (555.0021)CY1$9,000.00$3,350.00$10,000
33Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$15.50$15.50$15.50
34Bridge Joint Seal (567.63)LF314$136.00$140.00$250.00
35Transition Bridge Railing (568.70)LF68$200.00$210.00$225.00
36 (602.3618)LF276$200.00$250.00$375.00
37 (602.3624)LF2,004$200.00$240.00$225.00
38 (602.3630)LF193$325.00$370.00$378.00
39 (602.3636)LF1,141$335.00$370.00$378.00
40 (602.3648)LF254$620.00$670.00$520.00
41 (602.421001)SF18,210$100.00$230.00$195.00
42Culvert-End Safety Grate (603.0101)SF1,364$32.00$40.00$50.00
43 (603.061412)LF5$550.00$950.00$1,200.00
44 (603.171216)EACH7$600.00$1,650.00$1,200.00
45 (603.171316)EACH4$650.00$1,650.00$1,300.00
46 (603.171416)EACH25$900.00$1,750.00$1,400.00
47 (603.171614)EACH4$1,100.00$2,400.00$1,600.00
48 (603.171814)EACH15$1,300.00$2,500.00$1,800.00
49 (603.172012)EACH4$3,600.00$4,800.00$3,600.00
50 (603.6601)LF14$325.00$200.00$300.00
51 (603.67010008)2$5,000.00$3,900.00$6,500.00
52 (603.7302)EACH4$3,000.00$2,100.00$3,600.00
53 (603.7402)LF114$180.00$180.00$135.00
54Concrete Collars (603.77)EACH1$2,400.00$1,200.00$5,000.00
55 (603.9818)LF102$175.00$80.00$125.00
56 (604.070401)EACH4$7,000.00$1,400.00$5,000.00
57 (604.070402)EACH2$3,500.00$1,900.00$5,000.00
58Box Beam Guide Railing (606.10)LF36,072$45.00$48.00$50.30
59Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF2,384$50.00$53.00$55.50
60Box Beam Median Barrier (606.11)LF1,239$59.00$62.00$65.50
61Box Beam Median Barrier (Shop Bent or Shop Mitered) (606.110002)LF613$68.00$72.00$75.50
62Box Beam End Piece (606.120101)EACH37$600.00$630.00$670.00
63Box Beam Guide Railing End Assembly Type I (606.120102)EACH17$3,900.00$4,100.00$4,350.00
64Box Beam Guide Railing End Assembly Type I with 18 ft Extension (606.120103)EACH6$4,800.00$5,050.00$5,325.00
65Box Beam End Assembly Type III (606.1203)EACH10$6,400.00$6,750.00$7,350.00
66Box Beam Median Barrier End Assembly, Type B (606.1402)EACH3$2,350.00$2,500.00$2,650.00
67Single-Slope Concrete Median Barrier (Precast) (606.3042)LF686$190.00$260.00$230.00
68 (606.32960011)296$23.00$83.00$50.00
69Resetting Corrugated Beam Guide Railing (606.51)LF20$31.00$33.00$45.00
70Resetting Box Beam Guide Railing (New Posts) (606.5348)LF232$40.00$42.00$59.00
71Removing and Storing Precast Concrete Barrier-Half Section (606.6510)LF450$23.00$43.00$50.00
72Removing and Storing Weak- and Heavy-Post Corrugated Beam Terminals (606.6911)EACH1$1,000.00$1,050.00$1,150.00
73Removing and Storing Box Beam Guide Railing End Assembly (606.6920)EACH3$275.00$290.00$320.00
74Removing and Disposing Corrugated Beam Guide Railing (606.71)LF18,961$2.55$2.80$3.00
75Removing and Disposing Box Beam Guide Railing (606.73)LF6,269$2.75$3.00$3.25
76Removing and Disposing Box Beam Median Barrier (606.74)LF1,714$2.25$2.50$2.65
77Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910)EACH39$230.00$240.00$265.00
78Removing and Disposing Box Beam Median Barrier End Assembly--Type B (606.7931)EACH5$215.00$230.00$250.00
79 (606.85020001)7$680.00$730.00$775.00
80Transition Between Box Beam Guide Rail and Single Slope Half Section Concrete Barrier (One or Two Way Operation) (606.8803)EACH25$14,250$13,000$14,300
81Transition between Half-Section and Full-Section Single Slope Concrete Barrier (Left Pocket) (606.9003)EACH15$7,000.00$4,200.00$5,600.00
82Transition between Half-Section and Full-Section Single Slope Concrete Barrier (Right Pocket) (606.9004)EACH11$7,000.00$4,200.00$5,600.00
83 (607.36000011)255$100.00$55.00$55.00
84 (607.41010010)40$37.00$9.00$20.00
85 (607.62000010)230$12.00$17.00$17.00
86Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT1$95.00$95.00$95.00
87Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON1,134$325.00$240.00$240.00
88Stone Curb – Near Vertical Face (NVF) (609.0212)LF25$150.00$300.00$400.00
89Turf Establishment - Roadside (610.1601)SY8,250$1.10$1.20$1.10
90Watering Vegetation (610.19)1,000 GALLONS1,204$24.00$30.00$25.00
91 (614.060202)EACH10$1,300.00$1,400.00$1,800.00
92 (614.060302)EACH10$1,600.00$1,650.00$2,100.00
93 (614.060402)EACH10$1,800.00$1,900.00$2,400.00
94 (614.060602)EACH2$3,400.00$3,600.00$4,600.00
95 (617.01010024)100$10.00$20.00$19.00
96 (617.10000024)1,226$110.00$230.00$82.00
97 (617.11000024)LS1$250.00$15,000$3,000.00
98Basic Work Zone Traffic Control (619.01)LS1$2,900,000$1,312,926$2,445,092
99Type III Construction Barricades (619.04)EACH200$70.00$100.00$250.00
100 (619.080102)LF2,495$0.80$0.85$0.80
101 (619.0901)LF201,014$0.25$0.27$0.25
102 (619.110611)WEEK50$1,000.00$540.00$1,250.00
103Nighttime Operations (Entire Project) (619.24)LS1$200,000$240,000$200,000
104Pavement Patching (Force Acount) (619.2601)DOL50,000$1.00$1.00$1.00
105Stone Filling (Light) (620.03)CY1,152$135.00$300.00$205.00
106Stone Filling (Medium) (620.04)CY406$145.00$560.00$255.00
107Bedding Material, Type 1 (620.0801)CY453$90.00$220.00$285.00
108Cleaning Culverts with Span of More Than 50 in. (621.02)LF65$20.00$200.00$250.00
109 (621.05020004)41,916$4.00$3.80$7.70
110 (621.51970008)15,412$25.00$14.00$20.00
111Crushed Stone (In-Place Measure) (623.12)CY17$145.00$140.00$300.00
112Survey Operations (625.01)LS1$60,000$105,000$120,000
113 (625.09010015)LS1$1.00$10,000$9,000.00
114 (627.50140008)1,515$5.00$11.00$15.00
115Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403)SY760$205.00$100.00$250.00
116Stress Relieving Pavement Repairs (633.16)SY760$205.00$120.00$210.00
117Cleaning and Preparation of Pavement Surfaces-Lines (635.0103)LF7,615$0.77$0.82$0.78
118Concrete Cylinder Curing Equipment (637.04)EACH1$300.00$2,200.00$10,000
119Engineer’s Field Office – Type 2 (637.12)MONTH26$2,500.00$2,500.00$3,000.00
120Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00
121Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00
122 (637.41000115)26$150.00$100.00$50.00
123 (637.41000215)26$150.00$100.00$50.00
124 (637.41000315)26$150.00$100.00$50.00
125 (637.41000415)26$150.00$100.00$50.00
126 (637.41000515)26$150.00$100.00$50.00
127 (637.41000615)26$150.00$100.00$50.00
128 (642.31600008)14$9,900.00$11,000$10,000
129 (644.03120103)1$4,500.00$2,750.00$5,700.00
130 (644.03120703)1$800.00$2,750.00$4,300.00
131 (644.03120803)1$4,600.00$1,450.00$1,400.00
132 (644.03121403)1$1,800.00$2,750.00$4,300.00
133 (644.03121503)1$4,000.00$3,800.00$3,600.00
134 (644.03121803)1$2,200.00$6,600.00$6,300.00
135Anchor Bolts (644.11)LB8,805$12.00$9.00$8.50
136 (644.11010003)8$195.00$2,750.00$2,700.00
137Drilled Shaft for Overhead Sign Structures (644.20)CY318$3,500.00$5,800.00$7,300.00
138 (644.421230)EACH1$100,000$116,000$110,000
139 (644.432560)EACH1$135,000$171,000$163,000
140 (644.432590)EACH1$150,000$193,000$184,000
141 (644.433030)EACH1$140,000$177,000$168,000
142 (644.433060)EACH2$150,000$194,000$184,000
143 (644.433560)EACH1$170,000$205,000$194,000
144 (644.434060)EACH1$200,000$227,000$215,000
145 (644.434560)EACH1$220,000$249,000$236,000
146 (644.434590)EACH2$200,000$227,000$215,000
147Performance Concrete Quality Adjustment (644.99)QUALITY UNIT1$12.00$12.00$12.00
148 (645.03040015)3$3,000.00$5,000.00$5,000.00
149Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF1,847$34.00$28.00$26.00
150Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103)SF780$35.00$34.00$33.00
151Overhead Sign Panels (645.61)SF5,458$34.00$31.00$29.50
152Type A Sign Posts (645.81)EACH223$190.00$230.00$215.00
153High-Capacity Type A Sign Posts with Soil Plates Only (645.8106)EACH2$1,000.00$990.00$950.00
154 (645.81090003)60$68.00$50.00$48.00
155 (645.830601)EACH2$4,700.00$5,850.00$5,600.00
156 (645.830602)EACH3$4,700.00$6,100.00$5,800.00
157 (645.830701)EACH6$5,300.00$7,050.00$6,700.00
158Reference Marker Panel (646.21)EACH56$26.00$33.00$32.00
159Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH667$26.00$22.00$21.00
160Steel Post, 1.1 lb/ft (646.31)EACH56$79.00$55.00$53.00
161Steel Post, 2.0 lb/ft (646.32)EACH667$100.00$66.00$63.00
162Removal of Single Span Overhead Sign Panel(s), Structure, and Foundations (647.21)EACH10$21,000$19,000$20,500
163Remove and Dispose Overhead Sign Panel, Sign Panel Assembly (647.25)EACH5$2,000.00$1,900.00$1,800.00
164Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH4$160.00$200.00$190.00
165Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51)EACH1$26.00$150.00$150.00
166Remove and Dispose Sign Panel, Sign Panel Assembly Size III (Over 100 Square Feet) (647.53)EACH5$37.00$320.00$305.00
167Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH88$47.00$39.00$37.00
168Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size II (30-100 Square Feet) (647.62)EACH5$370.00$99.00$95.00
169Remove and Dispose High Capacity Type A Ground Mounted Sign Support and Foundation (647.64)EACH1$160.00$150.00$150.00
170Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65)EACH12$470.00$160.00$152.00
171 (647.83001002)723$26.00$19.00$18.00
172Milled-In Audible Roadway Delineators (MIARDs) (649.01)LF74,738$0.12$0.40$0.70
173Pavement Ride Quality Adjustment to Asphalt Level 1 (653.1010)QUALITY UNIT1,373$95.00$95.00$95.00
174 (670.0108)EACH4$9,000.00$2,400.00$2,300.00
175 (670.1130)EACH1$4,000.00$3,300.00$3,150.00
176 (670.1318)EACH1$3,250.00$1,400.00$1,300.00
177Breakaway Transformer Base (Aluminum) (670.19)EACH1$1,850.00$860.00$820.00
178 (670.2603)LF610$17.00$12.00$12.00
179Pullboxes 5 to 7 1/2 cubic feet, inside volume (Lighting) (670.3006)EACH2$3,000.00$2,400.00$2,300.00
180 (670.7004)LF2,040$3.25$3.70$3.50
181 (670.7006)LF520$3.50$1.80$1.70
182Ground Wire No. 6 AWG. (670.7501)LF680$3.75$3.20$3.05
183 (670.75070011)260$4.50$1.60$1.55
184 (670.77000105)2$1,500.00$480.00$460.00
185 (670.77000205)1$4,000.00$510.00$490.00
186 (670.77000305)1$4,000.00$150.00$150.00
187Remove and Dispose of Lamppost Assembly (670.81)EACH1$2,000.00$960.00$950.00
188Remove Lamppost Foundation (670.82)EACH4$1,000.00$760.00$750.00
189Relocate Lamppost Assembly (670.90)EACH3$5,000.00$1,250.00$1,200.00
190 (670.98000705)1$400.00$340.00$320.00
191Performance Concrete Quality Adjustment (670.99)QUALITY UNIT1$29.00$29.00$29.00
192 (680.51020009)1$1,100.00$1,050.00$1,020.00
193 (683.93143204)1$125,000$123,000$117,000
194 (683.93530010)2$15,000$4,400.00$4,200.00
195 (685.07200310)8$250.00$280.00$270.00
196 (685.16010014)124,321$1.50$1.60$1.55
197 (685.17010014)77,573$1.50$1.60$1.55
198White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF19,434$3.50$3.90$3.65
199 (691.04000020)82,950$1.00$1.00$1.00
200Field Change Payment (FCP) (697.03)DOL940,000$1.00$1.00$1.00
201Asphalt Price Adjustment (698.04)DOL54,415$1.00$1.00$1.00
202Fuel Price Adjustment (698.05)DOL15,950$1.00$1.00$1.00
203Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
204Mobilization (699.040001)LS1$920,000$1,000,000$1,098,000
NYSDOT contract D265425: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way