NYSDOT contract D265425 bid tabulation
Pavement Resurfacing and Drainage Rehabilitation I-490. Let by New York State DOT on February 27, 2025, Monroe, Region 04. 3 bids received; low bid $23,927,391 by Cold Spring Construction Company.
- Owner
- New York State DOT
- Letting
- 27 FEB 2025
- Pay items
- 204
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Cold Spring Construction Company | $23,927,391 | Low |
| 2 | Villager Construction Inc | $26,890,000 | +12% |
| 3 | Sealand Contractors Corp. | $28,574,000 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cold Spring Construction Company | 2. Villager Construction Inc | 3. Sealand Contractors Corp. |
|---|---|---|---|---|---|---|
| 1 | (201.07000004) | 33,044 | $5.25 | $5.50 | $5.50 | |
| 2 | (201.07010004) | 6 | $1,450.00 | $1,550.00 | $2,500.00 | |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 2,691 | $45.00 | $160.00 | $120.00 |
| 4 | Embankment In Place (203.03) | CY | 33 | $10.00 | $130.00 | $150.00 |
| 5 | Select Granular Fill (203.07) | CY | 49 | $63.00 | $78.00 | $200.00 |
| 6 | (203.24010017) | 618 | $58.00 | $250.00 | $150.00 | |
| 7 | Controlled Low Strength Material (CLSM) (204.01) | CY | 5 | $960.00 | $720.00 | $1,500.00 |
| 8 | Trench and Culvert Excavation (206.0201) | CY | 192 | $95.00 | $270.00 | $180.00 |
| 9 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 610 | $30.00 | $38.00 | $37.00 |
| 10 | Test Pit Excavation (206.05) | EACH | 14 | $2,000.00 | $1,500.00 | $2,000.00 |
| 11 | Geotextile Separation (207.21) | SY | 61 | $3.75 | $5.00 | $12.00 |
| 12 | Geotextile Drainage (207.22) | SY | 302 | $3.25 | $2.00 | $5.00 |
| 13 | Mulch – Temporary (209.100101) | SY | 7,000 | $0.90 | $1.00 | $0.91 |
| 14 | Seed and Mulch – Temporary (209.1003) | SY | 16,500 | $0.90 | $1.00 | $0.91 |
| 15 | Rolled Erosion Control Product, Class I Type A, Short Term (209.1801) | SY | 1,750 | $5.00 | $5.40 | $4.95 |
| 16 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 500 | $8.50 | $9.00 | $8.35 |
| 17 | Soil Stabilizers, Class IV Type A (209.2101) | SY | 9,183 | $1.00 | $1.10 | $1.00 |
| 18 | (209.23010009) | 200 | $16.50 | $18.00 | $25.00 | |
| 19 | Subbase Course, Type 2 (304.12) | CY | 220 | $160.00 | $200.00 | $300.00 |
| 20 | (404.0001) | TON | 1,422 | $95.00 | $95.00 | $95.00 |
| 21 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1,422 | $95.00 | $95.00 | $95.00 |
| 22 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 1,342 | $95.00 | $95.00 | $95.00 |
| 23 | (404.0189) | TON | 269 | $165.00 | $230.00 | $275.00 |
| 24 | (404.1989) | TON | 4 | $400.00 | $330.00 | $1,200.00 |
| 25 | (404.3789) | TON | 7 | $420.00 | $220.00 | $1,000.00 |
| 26 | (406.1252) | TON | 28,418 | $141.00 | $140.00 | $145.00 |
| 27 | Diluted Tack Coat (407.0102) | GAL | 19,379 | $9.00 | $7.20 | $9.40 |
| 28 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 177,133 | $0.75 | $0.50 | $1.15 |
| 29 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 242,229 | $3.05 | $3.70 | $4.60 |
| 30 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 31 | $1,650.00 | $700.00 | $2,000.00 |
| 31 | (553.030001) | EACH | 1 | $1.00 | $5,000.00 | $5,000.00 |
| 32 | Concrete for Structures, Performance (555.0021) | CY | 1 | $9,000.00 | $3,350.00 | $10,000 |
| 33 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $15.50 | $15.50 | $15.50 |
| 34 | Bridge Joint Seal (567.63) | LF | 314 | $136.00 | $140.00 | $250.00 |
| 35 | Transition Bridge Railing (568.70) | LF | 68 | $200.00 | $210.00 | $225.00 |
| 36 | (602.3618) | LF | 276 | $200.00 | $250.00 | $375.00 |
| 37 | (602.3624) | LF | 2,004 | $200.00 | $240.00 | $225.00 |
| 38 | (602.3630) | LF | 193 | $325.00 | $370.00 | $378.00 |
| 39 | (602.3636) | LF | 1,141 | $335.00 | $370.00 | $378.00 |
| 40 | (602.3648) | LF | 254 | $620.00 | $670.00 | $520.00 |
| 41 | (602.421001) | SF | 18,210 | $100.00 | $230.00 | $195.00 |
| 42 | Culvert-End Safety Grate (603.0101) | SF | 1,364 | $32.00 | $40.00 | $50.00 |
| 43 | (603.061412) | LF | 5 | $550.00 | $950.00 | $1,200.00 |
| 44 | (603.171216) | EACH | 7 | $600.00 | $1,650.00 | $1,200.00 |
| 45 | (603.171316) | EACH | 4 | $650.00 | $1,650.00 | $1,300.00 |
| 46 | (603.171416) | EACH | 25 | $900.00 | $1,750.00 | $1,400.00 |
| 47 | (603.171614) | EACH | 4 | $1,100.00 | $2,400.00 | $1,600.00 |
| 48 | (603.171814) | EACH | 15 | $1,300.00 | $2,500.00 | $1,800.00 |
| 49 | (603.172012) | EACH | 4 | $3,600.00 | $4,800.00 | $3,600.00 |
| 50 | (603.6601) | LF | 14 | $325.00 | $200.00 | $300.00 |
| 51 | (603.67010008) | 2 | $5,000.00 | $3,900.00 | $6,500.00 | |
| 52 | (603.7302) | EACH | 4 | $3,000.00 | $2,100.00 | $3,600.00 |
| 53 | (603.7402) | LF | 114 | $180.00 | $180.00 | $135.00 |
| 54 | Concrete Collars (603.77) | EACH | 1 | $2,400.00 | $1,200.00 | $5,000.00 |
| 55 | (603.9818) | LF | 102 | $175.00 | $80.00 | $125.00 |
| 56 | (604.070401) | EACH | 4 | $7,000.00 | $1,400.00 | $5,000.00 |
| 57 | (604.070402) | EACH | 2 | $3,500.00 | $1,900.00 | $5,000.00 |
| 58 | Box Beam Guide Railing (606.10) | LF | 36,072 | $45.00 | $48.00 | $50.30 |
| 59 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 2,384 | $50.00 | $53.00 | $55.50 |
| 60 | Box Beam Median Barrier (606.11) | LF | 1,239 | $59.00 | $62.00 | $65.50 |
| 61 | Box Beam Median Barrier (Shop Bent or Shop Mitered) (606.110002) | LF | 613 | $68.00 | $72.00 | $75.50 |
| 62 | Box Beam End Piece (606.120101) | EACH | 37 | $600.00 | $630.00 | $670.00 |
| 63 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 17 | $3,900.00 | $4,100.00 | $4,350.00 |
| 64 | Box Beam Guide Railing End Assembly Type I with 18 ft Extension (606.120103) | EACH | 6 | $4,800.00 | $5,050.00 | $5,325.00 |
| 65 | Box Beam End Assembly Type III (606.1203) | EACH | 10 | $6,400.00 | $6,750.00 | $7,350.00 |
| 66 | Box Beam Median Barrier End Assembly, Type B (606.1402) | EACH | 3 | $2,350.00 | $2,500.00 | $2,650.00 |
| 67 | Single-Slope Concrete Median Barrier (Precast) (606.3042) | LF | 686 | $190.00 | $260.00 | $230.00 |
| 68 | (606.32960011) | 296 | $23.00 | $83.00 | $50.00 | |
| 69 | Resetting Corrugated Beam Guide Railing (606.51) | LF | 20 | $31.00 | $33.00 | $45.00 |
| 70 | Resetting Box Beam Guide Railing (New Posts) (606.5348) | LF | 232 | $40.00 | $42.00 | $59.00 |
| 71 | Removing and Storing Precast Concrete Barrier-Half Section (606.6510) | LF | 450 | $23.00 | $43.00 | $50.00 |
| 72 | Removing and Storing Weak- and Heavy-Post Corrugated Beam Terminals (606.6911) | EACH | 1 | $1,000.00 | $1,050.00 | $1,150.00 |
| 73 | Removing and Storing Box Beam Guide Railing End Assembly (606.6920) | EACH | 3 | $275.00 | $290.00 | $320.00 |
| 74 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 18,961 | $2.55 | $2.80 | $3.00 |
| 75 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 6,269 | $2.75 | $3.00 | $3.25 |
| 76 | Removing and Disposing Box Beam Median Barrier (606.74) | LF | 1,714 | $2.25 | $2.50 | $2.65 |
| 77 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 39 | $230.00 | $240.00 | $265.00 |
| 78 | Removing and Disposing Box Beam Median Barrier End Assembly--Type B (606.7931) | EACH | 5 | $215.00 | $230.00 | $250.00 |
| 79 | (606.85020001) | 7 | $680.00 | $730.00 | $775.00 | |
| 80 | Transition Between Box Beam Guide Rail and Single Slope Half Section Concrete Barrier (One or Two Way Operation) (606.8803) | EACH | 25 | $14,250 | $13,000 | $14,300 |
| 81 | Transition between Half-Section and Full-Section Single Slope Concrete Barrier (Left Pocket) (606.9003) | EACH | 15 | $7,000.00 | $4,200.00 | $5,600.00 |
| 82 | Transition between Half-Section and Full-Section Single Slope Concrete Barrier (Right Pocket) (606.9004) | EACH | 11 | $7,000.00 | $4,200.00 | $5,600.00 |
| 83 | (607.36000011) | 255 | $100.00 | $55.00 | $55.00 | |
| 84 | (607.41010010) | 40 | $37.00 | $9.00 | $20.00 | |
| 85 | (607.62000010) | 230 | $12.00 | $17.00 | $17.00 | |
| 86 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $95.00 | $95.00 | $95.00 |
| 87 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 1,134 | $325.00 | $240.00 | $240.00 |
| 88 | Stone Curb – Near Vertical Face (NVF) (609.0212) | LF | 25 | $150.00 | $300.00 | $400.00 |
| 89 | Turf Establishment - Roadside (610.1601) | SY | 8,250 | $1.10 | $1.20 | $1.10 |
| 90 | Watering Vegetation (610.19) | 1,000 GALLONS | 1,204 | $24.00 | $30.00 | $25.00 |
| 91 | (614.060202) | EACH | 10 | $1,300.00 | $1,400.00 | $1,800.00 |
| 92 | (614.060302) | EACH | 10 | $1,600.00 | $1,650.00 | $2,100.00 |
| 93 | (614.060402) | EACH | 10 | $1,800.00 | $1,900.00 | $2,400.00 |
| 94 | (614.060602) | EACH | 2 | $3,400.00 | $3,600.00 | $4,600.00 |
| 95 | (617.01010024) | 100 | $10.00 | $20.00 | $19.00 | |
| 96 | (617.10000024) | 1,226 | $110.00 | $230.00 | $82.00 | |
| 97 | (617.11000024) | LS | 1 | $250.00 | $15,000 | $3,000.00 |
| 98 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $2,900,000 | $1,312,926 | $2,445,092 |
| 99 | Type III Construction Barricades (619.04) | EACH | 200 | $70.00 | $100.00 | $250.00 |
| 100 | (619.080102) | LF | 2,495 | $0.80 | $0.85 | $0.80 |
| 101 | (619.0901) | LF | 201,014 | $0.25 | $0.27 | $0.25 |
| 102 | (619.110611) | WEEK | 50 | $1,000.00 | $540.00 | $1,250.00 |
| 103 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $200,000 | $240,000 | $200,000 |
| 104 | Pavement Patching (Force Acount) (619.2601) | DOL | 50,000 | $1.00 | $1.00 | $1.00 |
| 105 | Stone Filling (Light) (620.03) | CY | 1,152 | $135.00 | $300.00 | $205.00 |
| 106 | Stone Filling (Medium) (620.04) | CY | 406 | $145.00 | $560.00 | $255.00 |
| 107 | Bedding Material, Type 1 (620.0801) | CY | 453 | $90.00 | $220.00 | $285.00 |
| 108 | Cleaning Culverts with Span of More Than 50 in. (621.02) | LF | 65 | $20.00 | $200.00 | $250.00 |
| 109 | (621.05020004) | 41,916 | $4.00 | $3.80 | $7.70 | |
| 110 | (621.51970008) | 15,412 | $25.00 | $14.00 | $20.00 | |
| 111 | Crushed Stone (In-Place Measure) (623.12) | CY | 17 | $145.00 | $140.00 | $300.00 |
| 112 | Survey Operations (625.01) | LS | 1 | $60,000 | $105,000 | $120,000 |
| 113 | (625.09010015) | LS | 1 | $1.00 | $10,000 | $9,000.00 |
| 114 | (627.50140008) | 1,515 | $5.00 | $11.00 | $15.00 | |
| 115 | Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403) | SY | 760 | $205.00 | $100.00 | $250.00 |
| 116 | Stress Relieving Pavement Repairs (633.16) | SY | 760 | $205.00 | $120.00 | $210.00 |
| 117 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 7,615 | $0.77 | $0.82 | $0.78 |
| 118 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $300.00 | $2,200.00 | $10,000 |
| 119 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 26 | $2,500.00 | $2,500.00 | $3,000.00 |
| 120 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 |
| 121 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 122 | (637.41000115) | 26 | $150.00 | $100.00 | $50.00 | |
| 123 | (637.41000215) | 26 | $150.00 | $100.00 | $50.00 | |
| 124 | (637.41000315) | 26 | $150.00 | $100.00 | $50.00 | |
| 125 | (637.41000415) | 26 | $150.00 | $100.00 | $50.00 | |
| 126 | (637.41000515) | 26 | $150.00 | $100.00 | $50.00 | |
| 127 | (637.41000615) | 26 | $150.00 | $100.00 | $50.00 | |
| 128 | (642.31600008) | 14 | $9,900.00 | $11,000 | $10,000 | |
| 129 | (644.03120103) | 1 | $4,500.00 | $2,750.00 | $5,700.00 | |
| 130 | (644.03120703) | 1 | $800.00 | $2,750.00 | $4,300.00 | |
| 131 | (644.03120803) | 1 | $4,600.00 | $1,450.00 | $1,400.00 | |
| 132 | (644.03121403) | 1 | $1,800.00 | $2,750.00 | $4,300.00 | |
| 133 | (644.03121503) | 1 | $4,000.00 | $3,800.00 | $3,600.00 | |
| 134 | (644.03121803) | 1 | $2,200.00 | $6,600.00 | $6,300.00 | |
| 135 | Anchor Bolts (644.11) | LB | 8,805 | $12.00 | $9.00 | $8.50 |
| 136 | (644.11010003) | 8 | $195.00 | $2,750.00 | $2,700.00 | |
| 137 | Drilled Shaft for Overhead Sign Structures (644.20) | CY | 318 | $3,500.00 | $5,800.00 | $7,300.00 |
| 138 | (644.421230) | EACH | 1 | $100,000 | $116,000 | $110,000 |
| 139 | (644.432560) | EACH | 1 | $135,000 | $171,000 | $163,000 |
| 140 | (644.432590) | EACH | 1 | $150,000 | $193,000 | $184,000 |
| 141 | (644.433030) | EACH | 1 | $140,000 | $177,000 | $168,000 |
| 142 | (644.433060) | EACH | 2 | $150,000 | $194,000 | $184,000 |
| 143 | (644.433560) | EACH | 1 | $170,000 | $205,000 | $194,000 |
| 144 | (644.434060) | EACH | 1 | $200,000 | $227,000 | $215,000 |
| 145 | (644.434560) | EACH | 1 | $220,000 | $249,000 | $236,000 |
| 146 | (644.434590) | EACH | 2 | $200,000 | $227,000 | $215,000 |
| 147 | Performance Concrete Quality Adjustment (644.99) | QUALITY UNIT | 1 | $12.00 | $12.00 | $12.00 |
| 148 | (645.03040015) | 3 | $3,000.00 | $5,000.00 | $5,000.00 | |
| 149 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 1,847 | $34.00 | $28.00 | $26.00 |
| 150 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 780 | $35.00 | $34.00 | $33.00 |
| 151 | Overhead Sign Panels (645.61) | SF | 5,458 | $34.00 | $31.00 | $29.50 |
| 152 | Type A Sign Posts (645.81) | EACH | 223 | $190.00 | $230.00 | $215.00 |
| 153 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 2 | $1,000.00 | $990.00 | $950.00 |
| 154 | (645.81090003) | 60 | $68.00 | $50.00 | $48.00 | |
| 155 | (645.830601) | EACH | 2 | $4,700.00 | $5,850.00 | $5,600.00 |
| 156 | (645.830602) | EACH | 3 | $4,700.00 | $6,100.00 | $5,800.00 |
| 157 | (645.830701) | EACH | 6 | $5,300.00 | $7,050.00 | $6,700.00 |
| 158 | Reference Marker Panel (646.21) | EACH | 56 | $26.00 | $33.00 | $32.00 |
| 159 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 667 | $26.00 | $22.00 | $21.00 |
| 160 | Steel Post, 1.1 lb/ft (646.31) | EACH | 56 | $79.00 | $55.00 | $53.00 |
| 161 | Steel Post, 2.0 lb/ft (646.32) | EACH | 667 | $100.00 | $66.00 | $63.00 |
| 162 | Removal of Single Span Overhead Sign Panel(s), Structure, and Foundations (647.21) | EACH | 10 | $21,000 | $19,000 | $20,500 |
| 163 | Remove and Dispose Overhead Sign Panel, Sign Panel Assembly (647.25) | EACH | 5 | $2,000.00 | $1,900.00 | $1,800.00 |
| 164 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 4 | $160.00 | $200.00 | $190.00 |
| 165 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 1 | $26.00 | $150.00 | $150.00 |
| 166 | Remove and Dispose Sign Panel, Sign Panel Assembly Size III (Over 100 Square Feet) (647.53) | EACH | 5 | $37.00 | $320.00 | $305.00 |
| 167 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 88 | $47.00 | $39.00 | $37.00 |
| 168 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size II (30-100 Square Feet) (647.62) | EACH | 5 | $370.00 | $99.00 | $95.00 |
| 169 | Remove and Dispose High Capacity Type A Ground Mounted Sign Support and Foundation (647.64) | EACH | 1 | $160.00 | $150.00 | $150.00 |
| 170 | Remove and Dispose Type B Ground Mounted Sign Support and Foundation (647.65) | EACH | 12 | $470.00 | $160.00 | $152.00 |
| 171 | (647.83001002) | 723 | $26.00 | $19.00 | $18.00 | |
| 172 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 74,738 | $0.12 | $0.40 | $0.70 |
| 173 | Pavement Ride Quality Adjustment to Asphalt Level 1 (653.1010) | QUALITY UNIT | 1,373 | $95.00 | $95.00 | $95.00 |
| 174 | (670.0108) | EACH | 4 | $9,000.00 | $2,400.00 | $2,300.00 |
| 175 | (670.1130) | EACH | 1 | $4,000.00 | $3,300.00 | $3,150.00 |
| 176 | (670.1318) | EACH | 1 | $3,250.00 | $1,400.00 | $1,300.00 |
| 177 | Breakaway Transformer Base (Aluminum) (670.19) | EACH | 1 | $1,850.00 | $860.00 | $820.00 |
| 178 | (670.2603) | LF | 610 | $17.00 | $12.00 | $12.00 |
| 179 | Pullboxes 5 to 7 1/2 cubic feet, inside volume (Lighting) (670.3006) | EACH | 2 | $3,000.00 | $2,400.00 | $2,300.00 |
| 180 | (670.7004) | LF | 2,040 | $3.25 | $3.70 | $3.50 |
| 181 | (670.7006) | LF | 520 | $3.50 | $1.80 | $1.70 |
| 182 | Ground Wire No. 6 AWG. (670.7501) | LF | 680 | $3.75 | $3.20 | $3.05 |
| 183 | (670.75070011) | 260 | $4.50 | $1.60 | $1.55 | |
| 184 | (670.77000105) | 2 | $1,500.00 | $480.00 | $460.00 | |
| 185 | (670.77000205) | 1 | $4,000.00 | $510.00 | $490.00 | |
| 186 | (670.77000305) | 1 | $4,000.00 | $150.00 | $150.00 | |
| 187 | Remove and Dispose of Lamppost Assembly (670.81) | EACH | 1 | $2,000.00 | $960.00 | $950.00 |
| 188 | Remove Lamppost Foundation (670.82) | EACH | 4 | $1,000.00 | $760.00 | $750.00 |
| 189 | Relocate Lamppost Assembly (670.90) | EACH | 3 | $5,000.00 | $1,250.00 | $1,200.00 |
| 190 | (670.98000705) | 1 | $400.00 | $340.00 | $320.00 | |
| 191 | Performance Concrete Quality Adjustment (670.99) | QUALITY UNIT | 1 | $29.00 | $29.00 | $29.00 |
| 192 | (680.51020009) | 1 | $1,100.00 | $1,050.00 | $1,020.00 | |
| 193 | (683.93143204) | 1 | $125,000 | $123,000 | $117,000 | |
| 194 | (683.93530010) | 2 | $15,000 | $4,400.00 | $4,200.00 | |
| 195 | (685.07200310) | 8 | $250.00 | $280.00 | $270.00 | |
| 196 | (685.16010014) | 124,321 | $1.50 | $1.60 | $1.55 | |
| 197 | (685.17010014) | 77,573 | $1.50 | $1.60 | $1.55 | |
| 198 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 19,434 | $3.50 | $3.90 | $3.65 |
| 199 | (691.04000020) | 82,950 | $1.00 | $1.00 | $1.00 | |
| 200 | Field Change Payment (FCP) (697.03) | DOL | 940,000 | $1.00 | $1.00 | $1.00 |
| 201 | Asphalt Price Adjustment (698.04) | DOL | 54,415 | $1.00 | $1.00 | $1.00 |
| 202 | Fuel Price Adjustment (698.05) | DOL | 15,950 | $1.00 | $1.00 | $1.00 |
| 203 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 204 | Mobilization (699.040001) | LS | 1 | $920,000 | $1,000,000 | $1,098,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 27, 2025. Compiled by Mirage Metrics.