NYSDOT contract D265703 bid tabulation

2026 Guiderail Requirements Contract. Let by New York State DOT on February 26, 2026, Broome, Chenango, Tioga, Region 09. 3 bids received; low bid $2,185,444 by Emi Guide Rail LLC.

Owner
New York State DOT
Letting
26 FEB 2026
Pay items
31
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Emi Guide Rail LLC$2,185,444Low
2Elderlee Inc$2,216,260+1.0%
3Road Safety Systems LLC$2,771,402+27%
NYSDOT contract D265703: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Emi Guide Rail LLC2. Elderlee Inc3. Road Safety Systems LLC
1Unclassified Excavation and Disposal (203.02)CY35$62.00$150.00$75.60
2 (203.24010017)675$146.00$95.00$79.60
3Box Beam Guide Railing (606.10)LF26,768$40.50$45.00$55.30
4Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF200$55.00$55.00$73.80
5Box Beam Guide Railing With Extra Long Posts (606.1001)LF4,564$45.25$50.00$56.40
6Box Beam End Piece (606.120101)EACH4$550.00$700.00$643.60
7Box Beam Guide Railing End Assembly Type I (606.120102)EACH16$4,000.00$3,750.00$4,467.70
8Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH40$1,850.00$2,200.00$2,033.80
9Box Beam End Assembly Type III (606.1203)EACH20$6,000.00$5,300.00$7,525.60
10Removing and Disposing Cable Guide Railing (606.70)LF14,300$2.00$1.00$1.80
11Removing and Disposing Corrugated Beam Guide Railing (606.71)LF18,000$2.75$2.00$2.40
12Removing and Disposing Box Beam Guide Railing (606.73)LF60$4.75$3.00$3.50
13Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH48$500.00$170.00$1,102.00
14Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910)EACH46$500.00$170.00$1,102.00
15Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH1$70.00$50.00$110.20
16 (617.11000024)LS1$1,200.00$1,000.00$2,880.00
17Basic Work Zone Traffic Control (619.01)LS1$160,000$140,185$192,427
18Mailboxes (619.27)EACH9$250.00$250.00$526.00
19Survey Operations (625.01)LS1$2,000.00$300.00$24,268
20Engineer’s Field Office – Type 2 (637.12)MONTH9$2,800.00$4,000.00$3,238.40
21Office Technology and Supplies (637.34)DOL500$1.00$1.00$1.00
22 (637.41000115)9$390.00$200.00$220.00
23Reference Marker Panel (646.21)EACH35$35.00$32.00$60.90
24Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH265$22.75$16.00$25.60
25Steel Post, 2.0 lb/ft (646.32)EACH255$73.00$58.00$83.60
26 (647.83001002)190$8.50$7.00$17.20
27Field Change Payment (FCP) (697.03)DOL91,000$1.00$1.00$1.00
28Asphalt Price Adjustment (698.04)DOL100$1.00$1.00$1.00
29Fuel Price Adjustment (698.05)DOL100$1.00$1.00$1.00
30Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
31Mobilization (699.040001)LS1$84,000$85,000$103,080
NYSDOT contract D265703: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of February 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way