NYSDOT contract D265765 bid tabulation
HIGHWAY SIGN INSTALLATION - Various Locations. Let by New York State DOT on April 16, 2026, Broome, Chenango, Delaware, Otsego,, Region 09. 6 bids received; low bid $2,715,555 by Elderlee Inc.
- Owner
- New York State DOT
- Letting
- 16 APR 2026
- Pay items
- 29
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Elderlee Inc | $2,715,555 | Low |
| 2 | Road Safety Systems LLC | $2,772,019 | +2.0% |
| 3 | US Traffic Control Inc | $3,027,280 | +11% |
| 4 | Emi Guide Rail LLC | $3,195,299 | +18% |
| 5 | Power Line Constructors Inc | $3,256,251 | +20% |
| 6 | Economy Paving Co Inc | $4,888,888 | +80% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Elderlee Inc | 2. Road Safety Systems LLC | 3. US Traffic Control Inc | 4. Emi Guide Rail LLC | 5. Power Line Constructors Inc | 6. Economy Paving Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $10,000 | $32,050 | $5,000.00 | $8,050.00 | $35,415 | $1,000.00 |
| 2 | Mulch – Temporary (209.100101) | SY | 2,650 | $2.00 | $1.00 | $3.00 | $3.50 | $10.12 | $5.00 |
| 3 | Turf Establishment – Performance (610.1605) | SY | 2,650 | $2.00 | $6.50 | $8.00 | $3.25 | $3.67 | $5.00 |
| 4 | (617.11000024) | LS | 1 | $500.00 | $1,550.00 | $1,000.00 | $1,550.00 | $6,265.00 | $1,000.00 |
| 5 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $178,593 | $145,543 | $250,000 | $784,350 | $434,912 | $740,000 |
| 6 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $55,000 | $27,000 | $15,000 | $24,650 | $17,631 | $10,000 |
| 7 | (625.130001) | EACH | 1 | $79,350 | $14,500 | $35,000 | $30,000 | $54,198 | $35,000 |
| 8 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 18 | $3,500.00 | $2,650.00 | $1,800.00 | $2,350.00 | $2,847.00 | $3,500.00 |
| 9 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 10 | (637.41000115) | 18 | $100.00 | $195.00 | $250.00 | $210.00 | $175.00 | $100.00 | |
| 11 | (637.41000215) | 18 | $100.00 | $195.00 | $250.00 | $210.00 | $175.00 | $100.00 | |
| 12 | (645.34010004) | 1 | $4,000.00 | $850.00 | $25,000 | $310.00 | $7,619.00 | $10,000 | |
| 13 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 28,416 | $33.00 | $31.00 | $38.00 | $25.00 | $33.16 | $75.00 |
| 14 | Type A Sign Posts (645.81) | EACH | 4,835 | $185.00 | $220.00 | $220.00 | $210.00 | $232.00 | $175.00 |
| 15 | (645.81090003) | 39 | $65.00 | $60.00 | $60.00 | $74.75 | $53.34 | $25.00 | |
| 16 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 1 | $220.00 | $165.00 | $200.00 | $100.00 | $361.00 | $500.00 |
| 17 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 1,340 | $16.00 | $47.00 | $22.00 | $27.00 | $35.93 | $125.00 |
| 18 | Reference Marker, Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels Relocation (646.24) | EACH | 65 | $20.00 | $40.00 | $30.00 | $27.25 | $80.16 | $100.00 |
| 19 | Steel Post, 2.0 lb/ft (646.32) | EACH | 1,280 | $70.00 | $73.00 | $75.00 | $82.00 | $77.13 | $155.00 |
| 20 | Brackets for Barrier and Multidirectional Mounting (646.50) | EACH | 285 | $90.00 | $35.20 | $95.00 | $99.25 | $68.08 | $150.00 |
| 21 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 138 | $150.00 | $176.00 | $125.00 | $135.50 | $140.00 | $250.00 |
| 22 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 295 | $18.00 | $50.00 | $40.00 | $48.25 | $19.72 | $150.00 |
| 23 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 1,234 | $45.00 | $50.00 | $45.00 | $58.00 | $57.13 | $150.00 |
| 24 | (647.83001002) | 40 | $25.00 | $25.00 | $25.00 | $6.25 | $28.49 | $50.00 | |
| 25 | Field Change Payment (FCP) (697.03) | DOL | 149,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Fuel Price Adjustment (698.05) | DOL | 224 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 29 | Mobilization (699.040001) | LS | 1 | $104,000 | $106,616 | $88,173 | $122,500 | $120,000 | $187,564 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of April 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.