NYSDOT contract D265770 bid tabulation

US 219 Crack & Seat & C540082 Rehabilitation. Let by New York State DOT on May 7, 2026, Erie, Region 05. 4 bids received; low bid $10,277,777 by D&H Excavating Inc.

Owner
New York State DOT
Letting
07 MAY 2026
Pay items
105
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D&H Excavating Inc$10,277,777Low
2McLaughlin Construction Corp/DBA Edbauer Construction$10,986,908+7.0%
3Concrete Applied Technologies Corp/DBA:Catco$11,858,693+15%
4Cold Spring Construction Company$13,858,997+35%
NYSDOT contract D265770: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D&H Excavating Inc2. McLaughlin Construction Corp/DBA Edbauer Construction3. Concrete Applied Technologies Corp/DBA:Catco4. Cold Spring Construction Company
1Clearing and Grubbing (201.06)LS1$25,000$10,000$15,000$90,000
2Unclassified Excavation and Disposal (203.02)CY16,100$30.00$40.00$36.00$36.00
3Embankment In Place (203.03)CY2,300$41.00$18.00$35.00$7.50
4 (203.24010017)1,450$62.00$51.00$40.00$55.00
5Trench and Culvert Excavation (206.0201)CY2,800$36.00$33.50$80.00$160.00
6Geotextile Stabilization (207.24)SY2,000$4.50$1.50$7.00$3.75
7 (207.96000017)18,000$0.50$0.26$2.85$4.00
8Seed and Mulch – Temporary (209.1003)SY3,300$1.75$0.50$1.00$2.50
9Stabilized Construction Access (209.22)SY300$1.00$10.00$30.00$20.00
10 (209.23010009)1,200$11.00$1.00$8.00$13.00
11 (304.00010018)455,000$0.15$0.10$0.30$0.20
12 (304.15200005)3,900$80.00$52.00$85.00$130.00
13Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT950$105.00$105.00$105.00$105.00
14Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT248$105.00$105.00$105.00$105.00
15 (404.0952)TON3,700$144.00$179.00$160.00$195.00
16 (404.0982)TON230$168.00$189.00$185.00$200.00
17 (404.1989)TON95$140.00$200.00$175.00$190.00
18 (404.3789)TON13,600$104.00$102.00$102.50$120.00
19 (406.0179)TON15,600$127.00$110.00$108.00$135.00
20 (406.0952)TON11,600$124.00$129.00$130.00$145.00
21Diluted Tack Coat (407.0102)GAL27,000$6.00$5.00$6.00$8.50
22Asphalt Pavement Joint Adhesive (418.7603)LF51,000$0.01$0.10$0.60$0.70
23Production Cold Milling of Bituminous Concrete (490.10)SY130,000$0.85$3.20$3.50$3.50
24 (502.65960005)87,000$0.90$0.56$1.20$1.35
25 (510.20000018)800$91.00$96.00$38.00$65.00
26 (553.030001)EACH1$1.00$100.00$100.00$0.01
27 (553.030002)EACH1$1.00$100.00$100.00$0.01
28 (553.030003)EACH1$1.00$100.00$100.00$0.01
29 (553.030004)EACH1$1.00$100.00$100.00$0.01
30 (553.030005)EACH1$1.00$100.00$100.00$0.01
31 (553.030006)EACH1$1.00$100.00$100.00$0.01
32 (602.2654)LF146$917.00$1,274.00$950.00$1,000.00
33 (602.3636)LF322$320.00$315.00$400.00$360.00
34 (602.3642)LF160$345.00$338.00$550.00$500.00
35 (602.3648)LF210$1.00$507.00$605.00$550.00
36 (602.36540003)188$570.00$562.00$815.00$745.00
37 (603.171912)EACH3$3,500.00$2,882.00$3,800.00$4,750.00
38Underdrain Filter, Type II (605.1001)CY1,200$140.00$25.00$80.00$200.00
39 (605.1701)LF10,500$5.25$10.00$9.00$3.00
40 (605.21010018)40$500.00$313.00$450.00$500.00
414-Cable Mid-Tension Cable Guide Rail with 5 feet Post Spacing (606.010605)LF975$111.00$110.00$108.00$100.00
424-Cable Mid-Tension Approach End Cable Terminal (606.020102)EACH1$23,000$23,030$23,000$21,500
43Anchorage Units for 4-Cable Mid-Tension Cable Guide Railing (606.0202)EACH1$14,000$13,535$13,500$12,500
44Removing and Disposing Cable Guide Railing (606.70)LF960$6.50$4.50$4.15$8.00
45Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH2$1,000.00$170.00$600.00$325.00
46Topsoil - Roadside (610.1402)CY360$60.00$25.00$125.00$125.00
47Turf Establishment - Roadside (610.1601)SY3,300$3.25$0.01$3.50$2.50
48Basic Work Zone Traffic Control (619.01)LS1$145,000$634,090$764,000$750,000
49Type III Construction Barricades (619.04)EACH200$26.00$80.00$100.00$40.00
50 (619.0901)LF65,000$0.58$0.53$0.55$0.49
51 (619.110513)EACH6$7,250.00$4,700.00$16,000$14,000
52Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611)MONTH6$12.00$448.00$10.00$750.00
53Nighttime Operations (Entire Project) (619.24)LS1$27,000$28,000$100.00$50,000
54Stone Filling (Medium) (620.04)CY125$218.00$140.00$260.00$223.00
55Bedding Material, Type 1 (620.0801)CY25$177.00$110.00$200.00$156.00
56Survey Operations (625.01)LS1$117,000$45,000$75,000$55,000
57 (627.50140008)44,000$0.01$7.15$5.40$7.00
58Cleaning Existing Pavement and/or Shoulder (633.11)SY90,000$1.30$0.10$0.40$0.25
59Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401)SY400$1.00$1.00$100.00$140.00
60Removal and Repair of Deteriorated Asphalt Pavement – Greater than 4 Square Yards and less than 20 Square Yards (633.1402)SY400$1.00$1.00$85.00$125.00
61Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403)SY400$1.00$1.00$80.00$100.00
62Removal and Repair of Loose, Broken, or Spalled PCC Pavement (633.15)SY4,500$56.00$38.00$30.00$91.00
63Concrete Cylinder Curing Equipment (637.04)EACH1$200.00$10.00$3,800.00$1.00
64Engineer’s Field Office – Type 2 (637.12)MONTH12$2,200.00$1,100.00$2,600.00$2,400.00
65Office Technology and Supplies (637.34)DOL500$1.00$1.00$1.00$1.00
66White Paint Reflectorized Pavement Stripes – 15 mils (640.10)LF56,000$0.22$0.20$0.20$0.19
67Yellow Paint Reflectorized Pavement Stripes - 15 mils (640.11)LF32,000$0.22$0.20$0.20$0.19
68Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF1,725$41.00$42.00$41.00$38.00
69Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103)SF723$41.00$43.00$42.00$40.00
70Type A Sign Posts (645.81)EACH205$220.00$224.00$219.00$210.00
71High-Capacity Type A Sign Posts with Soil Plates Only (645.8106)EACH24$1,200.00$1,359.00$1,325.00$1,250.00
72 (645.81090003)66$78.00$77.00$75.00$71.00
73 (645.830202)EACH4$4,100.00$4,212.00$4,109.00$6,650.00
74 (645.830402)EACH6$6,000.00$7,070.00$6,897.00$8,400.00
75Reference Marker Panel (646.21)EACH63$40.00$90.00$88.00$84.00
76Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH40$12.00$14.00$13.00$12.50
77Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH710$27.00$27.00$26.50$25.00
78Steel Post, 1.1 lb/ft (646.31)EACH40$73.00$77.00$75.00$71.00
79Steel Post, 2.0 lb/ft (646.32)EACH770$103.00$109.00$107.00$100.00
80Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH111$40.00$47.00$46.00$44.00
81Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size II (30-100 Square Feet) (647.62)EACH7$135.00$440.00$429.00$410.00
82 (647.83001002)667$15.00$17.00$16.50$16.00
83Milled-In Audible Roadway Delineators (MIARDs) (649.01)LF68,000$0.50$0.50$0.64$0.43
84Pavement Ride Quality Adjustment to Asphalt Level 1 (653.1010)QUALITY UNIT496$105.00$105.00$105.00$105.00
85 (662.60000108)2,500$1.00$1.00$1.00$1.00
86 (662.60000208)2,500$1.00$1.00$1.00$1.00
87Pole Excavation and Concrete Foundation (680.5001)CY5$1,000.00$5,230.00$3,600.00$7,500.00
88 (680.6714)EACH4$3,500.00$1,790.00$3,500.00$6,000.00
89Riser Assembly, 1-inch Diameter (680.700603)EACH2$1,200.00$3,190.00$1,400.00$6,000.00
90 (680.730514)LF200$5.75$11.00$10.00$9.00
91 (680.80270001)2$1.25$2,232.00$1,750.00$4,000.00
92 (680.80620215)2$1.25$3,672.00$2,500.00$4,000.00
93Flashing Beacon Sign Assembly (680.8220)EACH4$9,700.00$3,840.00$2,500.00$9,000.00
94Meter Pan (680.9402)EACH2$1,200.00$1,300.00$1,200.00$1,000.00
95Install Electrical Disconnect/Generator Transfer Switch (680.9499)EACH2$1,100.00$710.00$1,100.00$850.00
96 (680.950106)LF200$3.50$12.00$10.00$8.00
97Performance Concrete Quality Adjustment (680.99)QUALITY UNIT1$17.50$17.50$17.50$17.50
98White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF82,000$0.45$0.45$0.43$0.40
99Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF65,000$0.45$0.45$0.43$0.40
100White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF6,000$3.50$3.40$3.30$3.00
101Field Change Payment (FCP) (697.03)DOL460,000$1.00$1.00$1.00$1.00
102Asphalt Price Adjustment (698.04)DOL6,013$1.00$1.00$1.00$1.00
103Fuel Price Adjustment (698.05)DOL6,736$1.00$1.00$1.00$1.00
104Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00
105Mobilization (699.040001)LS1$366,095$422,000$456,000$533,000
NYSDOT contract D265770: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of May 7, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy