NCDOT contract C205084 bid tabulation

MILLING, RESURFACING, AND SHOULDER RECONSTRUCTION. 14 SECTIONS OF SECONDARY ROADS. Let by North Carolina DOT on April 15, 2025, Franklin. 4 bids received; low bid $1,878,129 by Barnhill Contracting Company.

Owner
North Carolina DOT
Letting
15 APR 2025
Pay items
15
Data through
20 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Barnhill Contracting Company$1,878,129Low
2S T Wooten Corporation$1,886,9050.0%
3Sunrock Industries LLC DBA Carolina Sunrock LLC$1,964,753+5.0%
4FSC II LLC DBA Fred Smith Company$1,990,302+6.0%
NCDOT contract C205084: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Barnhill Contracting Company2. S T Wooten Corporation3. Sunrock Industries LLC DBA Carolina Sunrock LLC4. FSC II LLC DBA Fred Smith Company
0001Mobilization (0000100000-N)LS1$74,055$94,000$65,139$99,500
0002Incidental stone base (1220000000-E)TON562$40.00$40.00$84.50$75.00
0003Shoulder reconstruction (1245000000-E)SMI22.42$3,260.00$3,150.00$3,855.00$2,250.00
0004Aggregate shoulder borrow (1260000000-E)TON2,071$38.75$27.75$23.50$43.00
0005Mill asp PVMT *****" DTH - (1-1/2") (1297000000-E)SY26,027$3.50$2.50$2.70$2.50
0006Incidental milling (1330000000-E)SY5,249$13.00$14.50$8.20$14.35
0007Asphalt conc surface course, type S9.5B (1519000000-E)TON13,419$59.00$64.25$62.40$60.00
0008Asphalt binder for plant mix (1575000000-E)TON893$500.00$400.00$545.00$550.00
0009Patching existing pavement (1704000000-E)TON382$150.00$130.00$171.00$115.00
0010Adjustment of manholes (2830000000-N)EACH6$800.00$800.00$800.00$800.00
0011Adjustment of meter boxes or valve boxes (2845000000-N)EACH4$750.00$750.00$750.00$750.00
0012Work zone advance/general warning signing (4413000000-E)SF1,527$6.92$7.00$6.25$6.85
0013Temporary traffic control (4457000000-N)LS1$8,000.00$66,600$45,340$63,250
0014Thermoplastic pavement marking lines (4", 90 mils) (4685000000-E)LF256,198$0.57$0.57$0.59$0.57
0015Permanent raised pavement markers (4900000000-N)EACH52$19.25$19.25$10.00$19.25
NCDOT contract C205084: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NCDOT's tabulation for this contract. NCDOT central letting bid tab workbooks, January 2013 to October 2026, each contract linked to the workbook it was read from. Bids that did not match their published total are left out.

Every contract let that day: NCDOT letting of April 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy