ODOT contract 250008 bid tabulation

D04-BH/CR FY2025 (East) (CULVERT REPLACEMENT). Let by Ohio DOT on January 16, 2025, District 4. 4 bids received; low bid $2,037,343 by Eclipse Co LLC, +26% against the engineer's estimate of $1,613,000.

Owner
Ohio DOT
Letting
16 JAN 2025
Pay items
71
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Eclipse Co LLC$2,037,343Low+26%
2Marucci & Gaffney Excavating Co$2,087,919+2.0%+29%
3Daniel R Schmoldt Enterprises Inc$3,036,787+49%+88%
4S E T Inc$3,038,000+49%+88%
ODOT contract 250008: bids by rank

Engineer's estimate: $1,613,000.

Bid tabulation

LinePay itemUnitQuantity1. Eclipse Co LLC2. Marucci & Gaffney Excavating Co3. Daniel R Schmoldt Enterprises Inc4. S E T Inc
1Clearing and grubbing, as per plan (201E11001)LS1$12,500$25,000$14,300$15,000
2Clearing and grubbing, as per plan (201E11001)LS1$12,500$5,000.00$12,650$7,000.00
3Clearing and grubbing, as per plan (201E11001)LS1$12,500$25,000$17,600$15,000
4Clearing and grubbing, as per plan (201E11001)LS1$12,500$15,000$13,750$15,000
5Special - pipe cleanout over 48" (202E70130)FT400$43.00$144.00$60.00$7.00
6Special - pipe cleanout over 48" (202E70130)FT132$130.00$22.73$60.00$22.00
7Special - pipe cleanout over 48" (202E70130)FT304$57.00$19.74$60.00$9.00
8Special - pipe cleanout over 48" (202E70130)FT224$77.00$205.00$60.00$319.00
9Removal misc.: channel cleanout, (atb-90-20.849) (202E98000)LS1$3,938.00$500.00$2,500.00$10,000
10Removal misc.: channel cleanout, (tru-305-16.860) (202E98000)LS1$3,938.00$4,000.00$3,000.00$9,000.00
11Removal misc.: channel cleanout, (tru-80-12.115) (202E98000)LS1$3,938.00$2,000.00$4,000.00$10,000
12Removal misc.: channel cleanout, (tru-82-12.260) (202E98000)LS1$3,938.00$500.00$6,000.00$25,000
13Unclassified excavation (503E21300)LS1$3,938.00$1,500.00$2,500.00$20,000
14Unclassified excavation (503E21300)LS1$3,938.00$100.00$2,500.00$16,000
15Unclassified excavation (503E21300)LS1$3,938.00$500.00$2,500.00$16,000
16Unclassified excavation (503E21300)LS1$3,938.00$500.00$2,500.00$22,000
17Special - as-built construction plans (690E91000)LS1$8,960.00$4,000.00$5,000.00$5,000.00
18Rock channel protection, type A with geotextile fabric (601E32004)CY97$219.00$270.00$220.00$404.00
19Rock channel protection, type B with geotextile fabric (601E32104)CY19$141.00$150.00$210.00$351.00
20Seeding and mulching (659E10000)SY1,200$6.00$8.00$3.00$5.00
21Erosion control (832E30000)EACH5,000$1.00$1.00$1.00$1.00
22Concrete masonry (602E20000)CY1$4,010.00$2,500.00$3,200.00$4,000.00
236" unclassified pipe underdrains (605E13300)FT60$36.00$5.00$80.00$25.00
24Aggregate drains (605E31100)FT60$20.00$8.00$18.00$18.00
2515" conduit, type C (611E06100)FT20$185.00$183.00$95.00$218.00
2618" conduit, type C (611E07600)FT20$246.00$200.00$177.28$202.00
27Liner pipe, 48", 707.35, 707.75, 707.85 (837E10000)FT304$239.00$269.00$590.00$270.00
28Liner pipe, 54", 707.35, 707.75, 707.85 (837E10000)FT132$345.00$397.00$620.00$320.00
29Liner pipe, 84", 707.35, 707.75, 707.85 (837E10000)FT224$488.00$743.00$966.00$599.00
30Backfill for liner pipe (837E21000)FT1,060$235.00$140.00$189.20$29.00
31Patching concrete structures with trowelable mortar (843E50000)SF276$114.00$75.00$130.00$80.00
32Ground mounted support, no. 2 post (630E02100)FT60$37.00$20.00$15.00$16.00
33Sign, flat sheet (630E80100)SF8$48.00$20.00$55.00$53.00
34Law enforcement officer with patrol car for assistance (614E11110)HR100$68.00$50.00$85.00$127.00
35Cofferdams and excavation bracing (503E11100)LS1$17,735$30,000$2,500.00$77,000
36Cofferdams and excavation bracing (503E11100)LS1$17,735$12,000$2,500.00$77,000
37Cofferdams and excavation bracing (503E11100)LS1$17,682$30,000$2,500.00$77,000
38Cofferdams and excavation bracing, as per plan (503E11101)LS1$30,012$125,000$2,500.00$270,000
39Clearing and grubbing, as per plan (201E11001)LS1$12,500$7,000.00$13,420$7,000.00
40Special - pipe cleanout, 24" and under (202E70110)FT32$168.00$20.00$60.00$20.00
41Special - pipe cleanout over 48" (202E70130)FT206$103.00$20.00$60.00$14.00
42Removal misc.: channel cleanout, (atb-307-16.531) (202E98000)LS1$3,938.00$2,000.00$7,200.00$7,000.00
43Cofferdams and excavation bracing (503E11100)LS1$30,752$20,000$5,000.00$80,000
44Unclassified excavation (503E21300)LS1$3,938.00$500.00$4,700.00$46,000
45Rock channel protection, type A with geotextile fabric (601E32004)CY35$155.00$200.00$220.00$473.00
46Low strength mortar backfill (613E41200)CY1$1,667.00$500.00$650.00$1,198.00
47Ground mounted support, no. 2 post (630E02100)FT15$35.50$20.00$17.50$16.00
48Sign, flat sheet (630E80100)SF2$48.00$20.00$55.00$53.00
49Removal of ground mounted sign and disposal (630E84900)EACH2$17.00$20.00$28.00$26.00
50Removal of ground mounted post support and disposal (630E86002)EACH2$23.00$20.00$28.00$26.00
51Liner pipe, 11'-10" min. X 7'-5" min. rise, 748.06 (837E10000)FT206$2,832.00$2,831.00$5,400.00$3,900.00
52Liner pipe, as per plan, 12", 707.85 (837E10001)FT32$325.00$310.00$156.80$206.00
53Backfill for liner pipe (837E21000)FT238$280.00$141.00$190.30$178.00
54Patching concrete structures with trowelable mortar (843E50000)SF15$379.00$75.00$130.00$183.00
55Clearing and grubbing, as per plan (201E11001)LS1$12,500$5,000.00$13,200$5,000.00
56Special - pipe cleanout over 48" (202E70130)FT110$192.00$20.00$60.00$26.00
57Removal misc.: channel cleanout, (mah-170-5.903) (202E98000)LS1$3,938.00$4,000.00$5,000.00$7,000.00
58Cofferdams and excavation bracing (503E11100)LS1$17,682$20,000$2,000.00$69,000
59Unclassified excavation (503E21300)LS1$3,938.00$500.00$2,800.00$24,000
60Rock channel protection, type B with geotextile fabric (601E32104)CY55$140.00$100.00$2,450.00$448.00
61Ground mounted support, no. 2 post (630E02100)FT15$37.00$20.00$17.50$16.00
62Sign, flat sheet (630E80100)SF2$16.00$100.00$55.00$53.00
63Liner pipe, 96", 707.35, 707.75, 707.85 (837E10000)FT110$629.00$697.00$1,500.00$670.00
64Backfill for liner pipe (837E21000)FT110$490.00$305.00$370.70$374.00
65Patching concrete structures with trowelable mortar (843E50000)SF15$379.00$75.00$130.00$183.00
66Premium for contract performance bond and for payment bond (103E05000)LS1$26,000$13,000$74,068$23,000
67Maintaining traffic (614E11000)LS1$68,192$64,800$20,230$200,000
68Field office, type B (619E16010)MNTH6$684.00$1,000.00$1,500.00$1,268.00
69Construction layout stakes and surveying (623E10000)LS1$12,115$24,000$16,234$15,000
70Mobilization (624E10000)LS1$52,500$100,000$144,000$234,000
100Liner pipe 54", 707.85 (837E10000)FT400$286.00$343.33$620.00$320.00
ODOT contract 250008: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy