ODOT contract 250008 bid tabulation
D04-BH/CR FY2025 (East) (CULVERT REPLACEMENT). Let by Ohio DOT on January 16, 2025, District 4. 4 bids received; low bid $2,037,343 by Eclipse Co LLC, +26% against the engineer's estimate of $1,613,000.
- Owner
- Ohio DOT
- Letting
- 16 JAN 2025
- Pay items
- 71
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eclipse Co LLC | $2,037,343 | Low | +26% |
| 2 | Marucci & Gaffney Excavating Co | $2,087,919 | +2.0% | +29% |
| 3 | Daniel R Schmoldt Enterprises Inc | $3,036,787 | +49% | +88% |
| 4 | S E T Inc | $3,038,000 | +49% | +88% |
Engineer's estimate: $1,613,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eclipse Co LLC | 2. Marucci & Gaffney Excavating Co | 3. Daniel R Schmoldt Enterprises Inc | 4. S E T Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $12,500 | $25,000 | $14,300 | $15,000 |
| 2 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $12,500 | $5,000.00 | $12,650 | $7,000.00 |
| 3 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $12,500 | $25,000 | $17,600 | $15,000 |
| 4 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $12,500 | $15,000 | $13,750 | $15,000 |
| 5 | Special - pipe cleanout over 48" (202E70130) | FT | 400 | $43.00 | $144.00 | $60.00 | $7.00 |
| 6 | Special - pipe cleanout over 48" (202E70130) | FT | 132 | $130.00 | $22.73 | $60.00 | $22.00 |
| 7 | Special - pipe cleanout over 48" (202E70130) | FT | 304 | $57.00 | $19.74 | $60.00 | $9.00 |
| 8 | Special - pipe cleanout over 48" (202E70130) | FT | 224 | $77.00 | $205.00 | $60.00 | $319.00 |
| 9 | Removal misc.: channel cleanout, (atb-90-20.849) (202E98000) | LS | 1 | $3,938.00 | $500.00 | $2,500.00 | $10,000 |
| 10 | Removal misc.: channel cleanout, (tru-305-16.860) (202E98000) | LS | 1 | $3,938.00 | $4,000.00 | $3,000.00 | $9,000.00 |
| 11 | Removal misc.: channel cleanout, (tru-80-12.115) (202E98000) | LS | 1 | $3,938.00 | $2,000.00 | $4,000.00 | $10,000 |
| 12 | Removal misc.: channel cleanout, (tru-82-12.260) (202E98000) | LS | 1 | $3,938.00 | $500.00 | $6,000.00 | $25,000 |
| 13 | Unclassified excavation (503E21300) | LS | 1 | $3,938.00 | $1,500.00 | $2,500.00 | $20,000 |
| 14 | Unclassified excavation (503E21300) | LS | 1 | $3,938.00 | $100.00 | $2,500.00 | $16,000 |
| 15 | Unclassified excavation (503E21300) | LS | 1 | $3,938.00 | $500.00 | $2,500.00 | $16,000 |
| 16 | Unclassified excavation (503E21300) | LS | 1 | $3,938.00 | $500.00 | $2,500.00 | $22,000 |
| 17 | Special - as-built construction plans (690E91000) | LS | 1 | $8,960.00 | $4,000.00 | $5,000.00 | $5,000.00 |
| 18 | Rock channel protection, type A with geotextile fabric (601E32004) | CY | 97 | $219.00 | $270.00 | $220.00 | $404.00 |
| 19 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 19 | $141.00 | $150.00 | $210.00 | $351.00 |
| 20 | Seeding and mulching (659E10000) | SY | 1,200 | $6.00 | $8.00 | $3.00 | $5.00 |
| 21 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Concrete masonry (602E20000) | CY | 1 | $4,010.00 | $2,500.00 | $3,200.00 | $4,000.00 |
| 23 | 6" unclassified pipe underdrains (605E13300) | FT | 60 | $36.00 | $5.00 | $80.00 | $25.00 |
| 24 | Aggregate drains (605E31100) | FT | 60 | $20.00 | $8.00 | $18.00 | $18.00 |
| 25 | 15" conduit, type C (611E06100) | FT | 20 | $185.00 | $183.00 | $95.00 | $218.00 |
| 26 | 18" conduit, type C (611E07600) | FT | 20 | $246.00 | $200.00 | $177.28 | $202.00 |
| 27 | Liner pipe, 48", 707.35, 707.75, 707.85 (837E10000) | FT | 304 | $239.00 | $269.00 | $590.00 | $270.00 |
| 28 | Liner pipe, 54", 707.35, 707.75, 707.85 (837E10000) | FT | 132 | $345.00 | $397.00 | $620.00 | $320.00 |
| 29 | Liner pipe, 84", 707.35, 707.75, 707.85 (837E10000) | FT | 224 | $488.00 | $743.00 | $966.00 | $599.00 |
| 30 | Backfill for liner pipe (837E21000) | FT | 1,060 | $235.00 | $140.00 | $189.20 | $29.00 |
| 31 | Patching concrete structures with trowelable mortar (843E50000) | SF | 276 | $114.00 | $75.00 | $130.00 | $80.00 |
| 32 | Ground mounted support, no. 2 post (630E02100) | FT | 60 | $37.00 | $20.00 | $15.00 | $16.00 |
| 33 | Sign, flat sheet (630E80100) | SF | 8 | $48.00 | $20.00 | $55.00 | $53.00 |
| 34 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $68.00 | $50.00 | $85.00 | $127.00 |
| 35 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $17,735 | $30,000 | $2,500.00 | $77,000 |
| 36 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $17,735 | $12,000 | $2,500.00 | $77,000 |
| 37 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $17,682 | $30,000 | $2,500.00 | $77,000 |
| 38 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $30,012 | $125,000 | $2,500.00 | $270,000 |
| 39 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $12,500 | $7,000.00 | $13,420 | $7,000.00 |
| 40 | Special - pipe cleanout, 24" and under (202E70110) | FT | 32 | $168.00 | $20.00 | $60.00 | $20.00 |
| 41 | Special - pipe cleanout over 48" (202E70130) | FT | 206 | $103.00 | $20.00 | $60.00 | $14.00 |
| 42 | Removal misc.: channel cleanout, (atb-307-16.531) (202E98000) | LS | 1 | $3,938.00 | $2,000.00 | $7,200.00 | $7,000.00 |
| 43 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $30,752 | $20,000 | $5,000.00 | $80,000 |
| 44 | Unclassified excavation (503E21300) | LS | 1 | $3,938.00 | $500.00 | $4,700.00 | $46,000 |
| 45 | Rock channel protection, type A with geotextile fabric (601E32004) | CY | 35 | $155.00 | $200.00 | $220.00 | $473.00 |
| 46 | Low strength mortar backfill (613E41200) | CY | 1 | $1,667.00 | $500.00 | $650.00 | $1,198.00 |
| 47 | Ground mounted support, no. 2 post (630E02100) | FT | 15 | $35.50 | $20.00 | $17.50 | $16.00 |
| 48 | Sign, flat sheet (630E80100) | SF | 2 | $48.00 | $20.00 | $55.00 | $53.00 |
| 49 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $17.00 | $20.00 | $28.00 | $26.00 |
| 50 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $23.00 | $20.00 | $28.00 | $26.00 |
| 51 | Liner pipe, 11'-10" min. X 7'-5" min. rise, 748.06 (837E10000) | FT | 206 | $2,832.00 | $2,831.00 | $5,400.00 | $3,900.00 |
| 52 | Liner pipe, as per plan, 12", 707.85 (837E10001) | FT | 32 | $325.00 | $310.00 | $156.80 | $206.00 |
| 53 | Backfill for liner pipe (837E21000) | FT | 238 | $280.00 | $141.00 | $190.30 | $178.00 |
| 54 | Patching concrete structures with trowelable mortar (843E50000) | SF | 15 | $379.00 | $75.00 | $130.00 | $183.00 |
| 55 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $12,500 | $5,000.00 | $13,200 | $5,000.00 |
| 56 | Special - pipe cleanout over 48" (202E70130) | FT | 110 | $192.00 | $20.00 | $60.00 | $26.00 |
| 57 | Removal misc.: channel cleanout, (mah-170-5.903) (202E98000) | LS | 1 | $3,938.00 | $4,000.00 | $5,000.00 | $7,000.00 |
| 58 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $17,682 | $20,000 | $2,000.00 | $69,000 |
| 59 | Unclassified excavation (503E21300) | LS | 1 | $3,938.00 | $500.00 | $2,800.00 | $24,000 |
| 60 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 55 | $140.00 | $100.00 | $2,450.00 | $448.00 |
| 61 | Ground mounted support, no. 2 post (630E02100) | FT | 15 | $37.00 | $20.00 | $17.50 | $16.00 |
| 62 | Sign, flat sheet (630E80100) | SF | 2 | $16.00 | $100.00 | $55.00 | $53.00 |
| 63 | Liner pipe, 96", 707.35, 707.75, 707.85 (837E10000) | FT | 110 | $629.00 | $697.00 | $1,500.00 | $670.00 |
| 64 | Backfill for liner pipe (837E21000) | FT | 110 | $490.00 | $305.00 | $370.70 | $374.00 |
| 65 | Patching concrete structures with trowelable mortar (843E50000) | SF | 15 | $379.00 | $75.00 | $130.00 | $183.00 |
| 66 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $26,000 | $13,000 | $74,068 | $23,000 |
| 67 | Maintaining traffic (614E11000) | LS | 1 | $68,192 | $64,800 | $20,230 | $200,000 |
| 68 | Field office, type B (619E16010) | MNTH | 6 | $684.00 | $1,000.00 | $1,500.00 | $1,268.00 |
| 69 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,115 | $24,000 | $16,234 | $15,000 |
| 70 | Mobilization (624E10000) | LS | 1 | $52,500 | $100,000 | $144,000 | $234,000 |
| 100 | Liner pipe 54", 707.85 (837E10000) | FT | 400 | $286.00 | $343.33 | $620.00 | $320.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 16, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way