ODOT contract 250061 bid tabulation
NOB-SR 821-08.31 (MINOR RECONSTRUCTION). Let by Ohio DOT on January 30, 2025, NOB. 4 bids received; low bid $1,289,009 by Shelly & Sands Inc, -13% against the engineer's estimate of $1,480,000.
- Owner
- Ohio DOT
- Letting
- 30 JAN 2025
- Pay items
- 63
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $1,289,009 | Low | -13% |
| 2 | Alan Stone Co Inc | $1,549,361 | +20% | +5.0% |
| 3 | NLS Paving, Inc | $1,698,939 | +32% | +15% |
| 4 | Eclipse Co LLC | $1,899,473 | +47% | +28% |
Engineer's estimate: $1,480,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Alan Stone Co Inc | 3. NLS Paving, Inc | 4. Eclipse Co LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $4,500.00 | $5,000.00 | $1,500.00 | $6,500.00 |
| 2 | Pavement removed (202E23000) | SY | 4,237 | $12.00 | $22.00 | $25.00 | $22.50 |
| 3 | Walk removed (202E30000) | SF | 3,749 | $1.25 | $1.50 | $5.00 | $7.00 |
| 4 | Steps removed (202E30200) | FT | 6 | $25.00 | $240.00 | $70.00 | $85.00 |
| 5 | Curb removed (202E32000) | FT | 140 | $2.50 | $5.50 | $10.00 | $11.00 |
| 6 | Curb and gutter removed (202E32500) | FT | 2,343 | $3.50 | $3.00 | $10.00 | $9.00 |
| 7 | Pipe removed, 24" and under (202E35100) | FT | 237 | $32.00 | $15.00 | $35.00 | $27.00 |
| 8 | Manhole removed (202E58000) | EACH | 1 | $425.00 | $360.00 | $1,000.00 | $535.00 |
| 9 | Catch basin removed (202E58100) | EACH | 4 | $550.00 | $60.00 | $550.00 | $535.00 |
| 10 | Special - pipe cleanout, 24" and under (202E70110) | FT | 126 | $20.00 | $25.00 | $60.00 | $41.00 |
| 11 | Excavation (203E10000) | CY | 50 | $80.00 | $30.00 | $180.00 | $165.00 |
| 12 | Subgrade compaction (204E10000) | SY | 5,121 | $2.00 | $5.00 | $2.50 | $1.00 |
| 13 | Excavation of subgrade (204E13000) | CY | 1,500 | $17.50 | $40.00 | $50.00 | $57.00 |
| 14 | Special - geocell, subgrade (6 inch cell depth) (204E60000) | SY | 4,590 | $14.50 | $15.00 | $18.50 | $20.00 |
| 15 | 4" concrete walk, as per plan (608E10001) | SF | 2,176 | $11.50 | $10.00 | $8.50 | $14.00 |
| 16 | Concrete steps, type A (608E40000) | FT | 30 | $650.00 | $500.00 | $200.00 | $237.00 |
| 17 | Curb ramp, as per plan (608E52001) | SF | 1,795 | $22.00 | $12.00 | $25.00 | $43.00 |
| 18 | Water (616E10000) | MGAL | 67 | $30.00 | $1.00 | $50.00 | $49.00 |
| 19 | Topsoil (659E00300) | CY | 6 | $200.00 | $120.00 | $650.00 | $209.00 |
| 20 | Seeding and mulching (659E10000) | SY | 1,322 | $2.80 | $1.50 | $3.00 | $3.00 |
| 21 | Repair seeding and mulching (659E14000) | SY | 325 | $2.80 | $2.00 | $3.00 | $3.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.12 | $1,250.00 | $640.00 | $1,350.00 | $1,316.00 |
| 23 | Lime (659E31000) | ACRE | 0.27 | $150.00 | $910.00 | $160.00 | $158.00 |
| 24 | Water (659E35000) | MGAL | 7 | $1.00 | $1,100.00 | $1.00 | $1.00 |
| 25 | Erosion control (832E30000) | EACH | 25,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 1,888 | $9.00 | $25.00 | $20.00 | $42.00 |
| 27 | 6" conduit, type F (611E01500) | FT | 130 | $25.00 | $40.00 | $30.00 | $33.00 |
| 28 | 12" conduit, type B (611E04400) | FT | 821 | $77.00 | $120.00 | $95.00 | $144.00 |
| 29 | 15" conduit, type B (611E05900) | FT | 129 | $89.00 | $120.00 | $100.00 | $157.00 |
| 30 | 18" conduit, type B (611E07400) | FT | 275 | $99.00 | $140.00 | $115.00 | $151.00 |
| 31 | 21" conduit, type B (611E08900) | FT | 133 | $124.00 | $180.00 | $140.00 | $168.00 |
| 32 | 24" conduit, type B (611E10400) | FT | 127 | $129.00 | $150.00 | $150.00 | $174.00 |
| 33 | Catch basin, no. 3 (611E98150) | EACH | 3 | $3,900.00 | $5,200.00 | $6,000.00 | $6,000.00 |
| 34 | Catch basin, no. 3A (611E98180) | EACH | 17 | $2,900.00 | $3,200.00 | $4,750.00 | $5,900.00 |
| 35 | Catch basin, no. 2-2C (611E98504) | EACH | 1 | $2,500.00 | $3,200.00 | $4,000.00 | $5,300.00 |
| 36 | Catch basin, no. 2-3 with bicycle safe grate (611E98520) | EACH | 1 | $2,700.00 | $4,000.00 | $4,000.00 | $5,400.00 |
| 37 | Manhole, no. 3 (611E99574) | EACH | 1 | $4,500.00 | $4,800.00 | $7,500.00 | $7,000.00 |
| 38 | Manhole adjusted to grade (611E99654) | EACH | 2 | $700.00 | $750.00 | $1,500.00 | $808.00 |
| 39 | Pavement repair (253E02000) | CY | 20 | $1,450.00 | $450.00 | $450.00 | $1,200.00 |
| 40 | Pavement planing, asphalt concrete (T=1.50") (254E01000) | SY | 2,481 | $6.00 | $7.50 | $7.00 | $12.00 |
| 41 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 642 | $220.00 | $260.00 | $235.00 | $225.00 |
| 42 | Aggregate base (304E20000) | CY | 858 | $92.00 | $90.00 | $110.00 | $110.00 |
| 43 | Non-tracking tack coat (407E20000) | GAL | 624 | $3.50 | $5.00 | $3.50 | $4.00 |
| 44 | Stabilized crushed aggregate (411E10000) | CY | 1,023 | $80.00 | $95.00 | $95.00 | $110.00 |
| 45 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 263 | $315.00 | $280.00 | $300.00 | $350.00 |
| 46 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 243 | $300.00 | $320.00 | $265.00 | $250.00 |
| 47 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 26 | $230.00 | $75.00 | $100.00 | $68.00 |
| 48 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 207 | $105.00 | $95.00 | $102.00 | $87.00 |
| 49 | 8" non-reinforced concrete pavement, class QC MS (452E12050) | SY | 79 | $179.00 | $95.00 | $125.00 | $87.00 |
| 50 | Combination curb and gutter, type 2 (609E12000) | FT | 2,275 | $28.50 | $65.00 | $36.50 | $72.00 |
| 51 | Curb, type 6 (609E26000) | FT | 518 | $65.00 | $50.00 | $30.00 | $34.00 |
| 52 | Valve box adjusted to grade (638E10800) | EACH | 2 | $195.00 | $170.00 | $550.00 | $808.00 |
| 53 | Removal of ground mounted sign and reerection (630E85100) | EACH | 7 | $75.00 | $550.00 | $150.00 | $132.00 |
| 54 | Center line (644E00300) | MI | 0.31 | $12,630 | $11,000 | $12,630 | $10,211 |
| 55 | Stop line (644E00500) | FT | 120 | $10.00 | $9.00 | $9.95 | $8.00 |
| 56 | Crosswalk line, 12" (644E00620) | FT | 280 | $4.50 | $9.00 | $4.50 | $8.00 |
| 57 | Crosswalk line, 24" (644E00630) | FT | 216 | $9.00 | $20.00 | $8.85 | $17.00 |
| 58 | Parking lot stall marking (646E20200) | FT | 64 | $12.50 | $3.50 | $12.50 | $3.00 |
| 59 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $900.00 | $1,650.00 | $1,600.00 | $1,000.00 |
| 60 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,700.00 | $12,000 | $9,993.40 | $27,000 |
| 61 | Maintaining traffic (614E11000) | LS | 1 | $24,600 | $29,000 | $58,000 | $40,000 |
| 62 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $17,000 | $26,000 | $25,000 |
| 63 | Mobilization (624E10000) | LS | 1 | $50,000 | $27,000 | $150,000 | $63,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.