ODOT contract 250061 bid tabulation

NOB-SR 821-08.31 (MINOR RECONSTRUCTION). Let by Ohio DOT on January 30, 2025, NOB. 4 bids received; low bid $1,289,009 by Shelly & Sands Inc, -13% against the engineer's estimate of $1,480,000.

Owner
Ohio DOT
Letting
30 JAN 2025
Pay items
63
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly & Sands Inc$1,289,009Low-13%
2Alan Stone Co Inc$1,549,361+20%+5.0%
3NLS Paving, Inc$1,698,939+32%+15%
4Eclipse Co LLC$1,899,473+47%+28%
ODOT contract 250061: bids by rank

Engineer's estimate: $1,480,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly & Sands Inc2. Alan Stone Co Inc3. NLS Paving, Inc4. Eclipse Co LLC
1Clearing and grubbing (201E11000)LS1$4,500.00$5,000.00$1,500.00$6,500.00
2Pavement removed (202E23000)SY4,237$12.00$22.00$25.00$22.50
3Walk removed (202E30000)SF3,749$1.25$1.50$5.00$7.00
4Steps removed (202E30200)FT6$25.00$240.00$70.00$85.00
5Curb removed (202E32000)FT140$2.50$5.50$10.00$11.00
6Curb and gutter removed (202E32500)FT2,343$3.50$3.00$10.00$9.00
7Pipe removed, 24" and under (202E35100)FT237$32.00$15.00$35.00$27.00
8Manhole removed (202E58000)EACH1$425.00$360.00$1,000.00$535.00
9Catch basin removed (202E58100)EACH4$550.00$60.00$550.00$535.00
10Special - pipe cleanout, 24" and under (202E70110)FT126$20.00$25.00$60.00$41.00
11Excavation (203E10000)CY50$80.00$30.00$180.00$165.00
12Subgrade compaction (204E10000)SY5,121$2.00$5.00$2.50$1.00
13Excavation of subgrade (204E13000)CY1,500$17.50$40.00$50.00$57.00
14Special - geocell, subgrade (6 inch cell depth) (204E60000)SY4,590$14.50$15.00$18.50$20.00
154" concrete walk, as per plan (608E10001)SF2,176$11.50$10.00$8.50$14.00
16Concrete steps, type A (608E40000)FT30$650.00$500.00$200.00$237.00
17Curb ramp, as per plan (608E52001)SF1,795$22.00$12.00$25.00$43.00
18Water (616E10000)MGAL67$30.00$1.00$50.00$49.00
19Topsoil (659E00300)CY6$200.00$120.00$650.00$209.00
20Seeding and mulching (659E10000)SY1,322$2.80$1.50$3.00$3.00
21Repair seeding and mulching (659E14000)SY325$2.80$2.00$3.00$3.00
22Commercial fertilizer (659E20000)TON0.12$1,250.00$640.00$1,350.00$1,316.00
23Lime (659E31000)ACRE0.27$150.00$910.00$160.00$158.00
24Water (659E35000)MGAL7$1.00$1,100.00$1.00$1.00
25Erosion control (832E30000)EACH25,000$1.00$1.00$1.00$1.00
266" base pipe underdrains with geotextile fabric (605E14020)FT1,888$9.00$25.00$20.00$42.00
276" conduit, type F (611E01500)FT130$25.00$40.00$30.00$33.00
2812" conduit, type B (611E04400)FT821$77.00$120.00$95.00$144.00
2915" conduit, type B (611E05900)FT129$89.00$120.00$100.00$157.00
3018" conduit, type B (611E07400)FT275$99.00$140.00$115.00$151.00
3121" conduit, type B (611E08900)FT133$124.00$180.00$140.00$168.00
3224" conduit, type B (611E10400)FT127$129.00$150.00$150.00$174.00
33Catch basin, no. 3 (611E98150)EACH3$3,900.00$5,200.00$6,000.00$6,000.00
34Catch basin, no. 3A (611E98180)EACH17$2,900.00$3,200.00$4,750.00$5,900.00
35Catch basin, no. 2-2C (611E98504)EACH1$2,500.00$3,200.00$4,000.00$5,300.00
36Catch basin, no. 2-3 with bicycle safe grate (611E98520)EACH1$2,700.00$4,000.00$4,000.00$5,400.00
37Manhole, no. 3 (611E99574)EACH1$4,500.00$4,800.00$7,500.00$7,000.00
38Manhole adjusted to grade (611E99654)EACH2$700.00$750.00$1,500.00$808.00
39Pavement repair (253E02000)CY20$1,450.00$450.00$450.00$1,200.00
40Pavement planing, asphalt concrete (T=1.50") (254E01000)SY2,481$6.00$7.50$7.00$12.00
41Asphalt concrete base, PG64-22, (449) (301E56000)CY642$220.00$260.00$235.00$225.00
42Aggregate base (304E20000)CY858$92.00$90.00$110.00$110.00
43Non-tracking tack coat (407E20000)GAL624$3.50$5.00$3.50$4.00
44Stabilized crushed aggregate (411E10000)CY1,023$80.00$95.00$95.00$110.00
45Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100)CY263$315.00$280.00$300.00$350.00
46Asphalt concrete intermediate course, type 2, (449) (441E70300)CY243$300.00$320.00$265.00$250.00
476" non-reinforced concrete pavement, class QC MS (452E10050)SY26$230.00$75.00$100.00$68.00
488" non-reinforced concrete pavement, class QC 1P (452E12010)SY207$105.00$95.00$102.00$87.00
498" non-reinforced concrete pavement, class QC MS (452E12050)SY79$179.00$95.00$125.00$87.00
50Combination curb and gutter, type 2 (609E12000)FT2,275$28.50$65.00$36.50$72.00
51Curb, type 6 (609E26000)FT518$65.00$50.00$30.00$34.00
52Valve box adjusted to grade (638E10800)EACH2$195.00$170.00$550.00$808.00
53Removal of ground mounted sign and reerection (630E85100)EACH7$75.00$550.00$150.00$132.00
54Center line (644E00300)MI0.31$12,630$11,000$12,630$10,211
55Stop line (644E00500)FT120$10.00$9.00$9.95$8.00
56Crosswalk line, 12" (644E00620)FT280$4.50$9.00$4.50$8.00
57Crosswalk line, 24" (644E00630)FT216$9.00$20.00$8.85$17.00
58Parking lot stall marking (646E20200)FT64$12.50$3.50$12.50$3.00
59Portable changeable message sign, as per plan (614E18601)SNMT12$900.00$1,650.00$1,600.00$1,000.00
60Premium for contract performance bond and for payment bond (103E05000)LS1$6,700.00$12,000$9,993.40$27,000
61Maintaining traffic (614E11000)LS1$24,600$29,000$58,000$40,000
62Construction layout stakes and surveying (623E10000)LS1$10,000$17,000$26,000$25,000
63Mobilization (624E10000)LS1$50,000$27,000$150,000$63,000
ODOT contract 250061: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of January 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy