ODOT contract 250132 bid tabulation
RIC-/HUR-SR 39/SR 61-11.15/11.97 (CULVERT REPLACEMENT). Let by Ohio DOT on February 27, 2025, RIC. 3 bids received; low bid $339,000 by Adena Corporation, +5.6% against the engineer's estimate of $321,000.
- Owner
- Ohio DOT
- Letting
- 27 FEB 2025
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Adena Corporation | $339,000 | Low | +6.0% |
| 2 | Stanley Miller Construction Company | $415,003 | +22% | +29% |
| 3 | Madex Construction Co | $436,325 | +29% | +36% |
Engineer's estimate: $321,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Adena Corporation | 2. Stanley Miller Construction Company | 3. Madex Construction Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $9,685.40 | $10,000 | $2,382.43 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $333.30 | $2,500.00 | $1,890.00 |
| 3 | Pipe removed, over 24" diameter (202E35200) | FT | 20 | $40.62 | $300.00 | $85.09 |
| 4 | Guardrail removed for reuse, as per plan (202E38201) | FT | 137.50 | $5.90 | $12.00 | $11.66 |
| 5 | Special - pipe cleanout, 27" to 48" (202E70120) | FT | 274 | $29.09 | $24.00 | $4.50 |
| 6 | Fence removed (202E75000) | FT | 104 | $0.97 | $20.00 | $15.57 |
| 7 | Excavation (203E10000) | CY | 49 | $20.72 | $120.00 | $77.17 |
| 8 | Embankment (203E20000) | CY | 49 | $20.72 | $120.00 | $85.34 |
| 9 | Monument assembly, type C (623E38500) | EACH | 2 | $2,959.39 | $5,000.00 | $2,158.62 |
| 10 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,309.70 | $4,000.00 | $5,242.11 |
| 11 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,309.70 | $4,000.00 | $3,452.11 |
| 12 | Riprap, type D (601E11000) | SY | 20 | $484.46 | $850.00 | $922.41 |
| 13 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 27 | $94.89 | $375.00 | $168.36 |
| 14 | Rock channel protection, type A with filter (601E32000) | CY | 51 | $191.10 | $250.00 | $196.61 |
| 15 | Rock channel protection, type B with filter (601E32100) | CY | 25 | $196.23 | $250.00 | $247.55 |
| 16 | Soil analysis test (659E00100) | EACH | 4 | $100.00 | $150.00 | $289.47 |
| 17 | Topsoil (659E00300) | CY | 127 | $51.62 | $55.00 | $89.41 |
| 18 | Seeding and mulching (659E10000) | SY | 1,143 | $6.31 | $6.50 | $4.56 |
| 19 | Repair seeding and mulching (659E14000) | SY | 57 | $1.00 | $2.00 | $2.47 |
| 20 | Inter-seeding (659E15000) | SY | 57 | $1.00 | $1.00 | $2.47 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.15 | $1,302.00 | $800.00 | $1,086.73 |
| 22 | Lime (659E31000) | ACRE | 0.24 | $135.63 | $150.00 | $175.46 |
| 23 | Water (659E35000) | MGAL | 6.32 | $1.00 | $1.00 | $38.21 |
| 24 | Erosion control (832E30000) | EACH | 6,000 | $1.00 | $1.00 | $1.00 |
| 25 | 36" conduit, type A (611E16200) | FT | 20 | $386.94 | $850.00 | $380.12 |
| 26 | Conduit, misc.: video log (611E97400) | FT | 274 | $6.23 | $20.00 | $5.79 |
| 27 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $14,617 | $10,000 | |
| 28 | Conduit renewal using spray applied structural liner, round conduit (833E10000) | FT | 172 | $484.03 | $411.00 | |
| 29 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $6,266.75 | ||
| 30 | Cured-in-place pipe liner (48" diameter) (899E10000) | FT | 172 | $797.37 | ||
| 31 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $14,617 | $10,000 | |
| 32 | Concrete masonry (602E20000) | CY | 1.52 | $3,210.40 | $2,000.00 | |
| 33 | Conduit renewal using spray applied structural liner, round conduit (833E10000) | FT | 102 | $685.75 | $576.00 | |
| 34 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $6,031.46 | ||
| 35 | Concrete masonry (602E20000) | CY | 1.52 | $3,641.01 | ||
| 36 | Cured-in-place pipe liner (36" diameter) (899E10000) | FT | 102 | $770.00 | ||
| 37 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,207.90 | $10,000 | $23,821 |
| 38 | Maintaining traffic (614E11000) | LS | 1 | $33,357 | $35,000 | $20,452 |
| 39 | Field office, type B (619E16010) | MNTH | 3 | $500.00 | $500.00 | $964.71 |
| 40 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,559.60 | $15,000 | $9,631.58 |
| 41 | Mobilization (624E10000) | LS | 1 | $18,581 | $50,000 | $39,860 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.