ODOT contract 250149 bid tabulation
WAY-SR 95-00.17 (CULVERT REPLACEMENT). Let by Ohio DOT on February 27, 2025, WAY. 6 bids received; low bid $244,682 by Ed Wilson Services LLC, -6.3% against the engineer's estimate of $261,000.
- Owner
- Ohio DOT
- Letting
- 27 FEB 2025
- Pay items
- 53
- Data through
- 12 NOV 2026
5 of the 6 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ed Wilson Services LLC | $244,682 | Low | -6.0% |
| 3 | Adena Corporation | $269,744 | +10% | +3.0% |
| 4 | BCC Ohio Inc | $270,799 | +11% | +4.0% |
| 5 | Stanley Miller Construction Company | $447,403 | +83% | +71% |
| 6 | Eclipse Co LLC | $468,412 | +91% | +79% |
Engineer's estimate: $261,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ed Wilson Services LLC | 2. Adena Corporation | 3. BCC Ohio Inc | 4. Stanley Miller Construction Company | 5. Eclipse Co LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,000.00 | $9,563.77 | $1,872.00 | $7,000.00 | $10,000 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $1,000.00 | $2,020.22 | $3,813.75 | $1,500.00 | $8,361.00 |
| 3 | Pavement removed (202E23000) | SY | 80 | $50.00 | $33.34 | $14.79 | $30.00 | $42.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 13 | $50.00 | $7.47 | $21.06 | $60.00 | $37.00 |
| 5 | Pipe removed, over 24" diameter (202E35200) | FT | 4 | $100.00 | $3,378.56 | $1,614.38 | $500.00 | $4,943.00 |
| 6 | Excavation (203E10000) | CY | 242 | $25.00 | $20.05 | $21.37 | $70.00 | $62.00 |
| 7 | Embankment (203E20000) | CY | 161 | $25.00 | $19.31 | $17.55 | $55.00 | $44.00 |
| 8 | Subgrade compaction (204E10000) | SY | 89 | $3.00 | $8.73 | $2.34 | $5.00 | $5.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 225 | $35.00 | $26.78 | $22.58 | $28.50 | $20.00 |
| 10 | Guardrail, type MGS, long-span (606E17360) | FT | 75 | $50.00 | $41.11 | $34.65 | $26.50 | $22.00 |
| 11 | Anchor assembly, type E (606E26100) | EACH | 4 | $3,500.00 | $3,301.93 | $2,782.50 | $4,500.00 | $2,540.00 |
| 12 | Monument assembly, type C (623E38500) | EACH | 2 | $2,000.00 | $1,992.37 | $2,133.00 | $4,500.00 | $2,851.00 |
| 13 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,500.00 | $934.50 | $2,625.00 | $2,500.00 | $3,298.00 |
| 14 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,500.00 | $934.50 | $2,625.00 | $2,500.00 | $3,298.00 |
| 15 | Rock channel protection, type B with filter (601E32100) | CY | 38 | $175.00 | $158.17 | $227.29 | $250.00 | $198.00 |
| 16 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $100.00 | $137.25 | $150.00 | $175.00 |
| 17 | Topsoil (659E00300) | CY | 114 | $50.00 | $52.20 | $72.54 | $50.00 | $112.00 |
| 18 | Seeding and mulching (659E10000) | SY | 1,030 | $2.50 | $3.05 | $3.41 | $8.00 | $4.00 |
| 19 | Repair seeding and mulching (659E14000) | SY | 52 | $1.00 | $1.00 | $3.15 | $2.00 | $1.10 |
| 20 | Inter-seeding (659E15000) | SY | 52 | $1.00 | $1.00 | $3.15 | $1.00 | $0.10 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.14 | $800.00 | $1,112.50 | $2,250.00 | $800.00 | $700.00 |
| 22 | Lime (659E31000) | ACRE | 0.21 | $150.00 | $296.67 | $490.00 | $150.00 | $40.00 |
| 23 | Water (659E35000) | MGAL | 5.70 | $1.00 | $1.00 | $10.50 | $1.00 | $1.00 |
| 24 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | 7' X 4' conduit, type A, 706.05 (611E94726) | FT | 15 | $1,800.00 | $2,370.18 | $2,077.50 | $2,750.00 | $3,873.00 |
| 26 | 7' X 4' conduit, type A, 706.05, as per plan (611E94727) | FT | 13 | $1,800.00 | $1,750.48 | $2,663.74 | $2,200.00 | $3,697.00 |
| 27 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 19 | $500.00 | $560.70 | $472.50 | $647.00 | $800.00 |
| 28 | Aggregate base (304E20000) | CY | 62 | $90.00 | $122.39 | $150.60 | $175.00 | $113.00 |
| 29 | Tack coat (407E10000) | GAL | 13 | $4.00 | $24.92 | $21.00 | $24.00 | $2.00 |
| 30 | Prime coat, as per plan (408E10001) | GAL | 84 | $7.00 | $22.42 | $18.90 | $50.00 | $12.00 |
| 31 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001) | CY | 7 | $900.00 | $1,246.01 | $1,050.00 | $705.00 | $2,210.00 |
| 32 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 8 | $15.00 | $13.70 | $13.20 | $50.00 | $13.00 |
| 33 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 24 | $17.00 | $108.41 | $91.36 | $70.00 | $87.00 |
| 34 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $220.00 | $303.95 | $256.14 | $105.00 | $244.00 |
| 35 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $110.00 | $26.73 | $22.53 | $60.00 | $21.00 |
| 36 | Edge line, 6", type 1 (642E00104) | MI | 0.01 | $68,000 | $98,005 | $82,588 | $100,000 | $78,655 |
| 37 | Center line, type 1 (642E00300) | MI | 0.01 | $90,000 | $130,296 | $110,114 | $130,000 | $104,870 |
| 38 | Detour signing (614E12420) | LS | 1 | $4,000.00 | $7,264.55 | $6,121.75 | $12,000 | $5,830.00 |
| 39 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $5,000.00 | $10,700 | $11,754 | $30,000 | $27,284 |
| 40 | Unclassified excavation (503E21300) | LS | 1 | $10,000 | $16,770 | $6,796.35 | $42,000 | $10,238 |
| 41 | Epoxy coated steel reinforcement (509E10000) | LB | 2,972 | $2.00 | $2.30 | $1.92 | $3.00 | $5.00 |
| 42 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 6 | $1,500.00 | $1,892.69 | $2,038.31 | $1,250.00 | $3,945.00 |
| 43 | Class QC1 concrete, footing (511E46510) | CY | 20 | $500.00 | $653.65 | $1,148.51 | $850.00 | $1,152.00 |
| 44 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $1,500.00 | $1,275.91 | $2,079.08 | $2,000.00 | $4,077.00 |
| 45 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 24 | $30.00 | $94.64 | $44.55 | $160.00 | $106.00 |
| 46 | Type 2 waterproofing (512E33000) | SY | 19 | $35.00 | $33.57 | $42.91 | $295.00 | $34.00 |
| 47 | Type 3 waterproofing (512E33010) | SY | 33 | $35.00 | $41.98 | $84.15 | $365.00 | $58.00 |
| 48 | 1" preformed expansion joint filler (516E13600) | SF | 26 | $15.00 | $3.83 | $13.15 | $57.00 | $9.00 |
| 49 | Porous backfill with geotextile fabric (518E21230) | LS | 1 | $125.00 | $1,634.76 | $2,508.00 | $8,000.00 | $2,139.00 |
| 50 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $3,115.03 | $3,343.08 | $10,000 | $9,500.00 |
| 51 | Maintaining traffic (614E11000) | LS | 1 | $8,000.00 | $2,801.64 | $1,801.80 | $12,000 | $22,438 |
| 52 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,500.00 | $4,884.37 | $3,795.00 | $12,000 | $7,097.00 |
| 53 | Mobilization (624E10000) | LS | 1 | $25,000 | $5,081.92 | $8,148.00 | $45,000 | $32,065 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.