ODOT contract 250156 bid tabulation
FAY-SR-SR 41/VAR-22.18/VAR (TWO LANE RESURFACING). Let by Ohio DOT on March 27, 2025, FAY. 4 bids received; low bid $1,200,367 by John R Jurgensen Company, -9.9% against the engineer's estimate of $1,333,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 75
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | John R Jurgensen Company | $1,200,367 | Low | -10% |
| 2 | Fillmore Construction | $1,286,776 | +7.0% | -3.0% |
| 3 | Kokosing Construction Company Inc | $1,316,095 | +10% | -1.0% |
| 4 | Shelly Company | $1,549,723 | +29% | +16% |
Engineer's estimate: $1,333,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. John R Jurgensen Company | 2. Fillmore Construction | 3. Kokosing Construction Company Inc | 4. Shelly Company |
|---|---|---|---|---|---|---|---|
| 2 | Walk removed, as per plan (202E30001) | SF | 2,689 | $12.00 | $10.00 | $6.00 | $10.00 |
| 3 | Curb removed (202E32000) | FT | 51 | $17.00 | $50.00 | $26.00 | $50.00 |
| 4 | Guardrail removed, as per plan (202E38001) | FT | 306.75 | $2.50 | $2.50 | $2.40 | $2.40 |
| 5 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 2 | $425.00 | $425.00 | $385.00 | $385.00 |
| 6 | Anchor assembly removed, type E, as per plan (202E42011) | EACH | 1 | $175.00 | $175.00 | $165.00 | $165.00 |
| 7 | Bridge terminal assembly removed, as per plan (202E47001) | EACH | 1 | $125.00 | $125.00 | $100.00 | $100.00 |
| 8 | Embankment, as per plan (203E20001) | CY | 25 | $68.00 | $68.00 | $78.00 | $78.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 312.50 | $21.00 | $21.00 | $21.60 | $21.60 |
| 10 | Anchor assembly, MGS type E, as per plan (MASH 201 (606E26151) | EACH | 3 | $2,500.00 | $2,500.00 | $2,825.00 | $2,825.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,100.00 | $1,100.00 | $1,320.00 | $1,320.00 |
| 12 | Bridge terminal assembly, type 4, as per plan (606E35141) | EACH | 2 | $1,250.00 | $1,250.00 | $1,450.00 | $1,450.00 |
| 13 | Guardrail, misc.: alternative guardrail placement (606E98000) | FT | 25 | $7.50 | $7.50 | $12.00 | $12.00 |
| 14 | 4" concrete walk (608E10000) | SF | 810 | $9.00 | $16.00 | $8.70 | $16.00 |
| 15 | Curb ramp (608E52000) | SF | 1,782 | $20.00 | $43.00 | $20.00 | $43.00 |
| 16 | Combination curb and gutter, type 2 (609E12000) | FT | 84 | $40.00 | $110.00 | $57.00 | $110.00 |
| 17 | Curb, type 4-C (609E24510) | FT | 106 | $35.00 | $110.00 | $36.50 | $110.00 |
| 18 | Topsoil (659E00300) | CY | 41 | $140.00 | $80.00 | $30.00 | $250.00 |
| 19 | Seeding and mulching (659E10000) | SY | 395 | $10.00 | $3.00 | $9.80 | $9.80 |
| 20 | Repair seeding and mulching (659E14000) | SY | 20 | $1.00 | $3.00 | $2.00 | $2.00 |
| 21 | Inter-seeding (659E15000) | SY | 20 | $0.01 | $3.00 | $0.10 | $0.10 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.14 | $1,500.00 | $1,000.00 | $650.00 | $650.00 |
| 23 | Lime (659E31000) | ACRE | 0.15 | $200.00 | $1,000.00 | $60.00 | $60.00 |
| 24 | Water (659E35000) | MGAL | 2 | $1.00 | $10.00 | $1.00 | $1.00 |
| 25 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Catch basin adjusted to grade (611E98630) | EACH | 4 | $649.42 | $1,000.00 | $850.00 | $1,500.00 |
| 27 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 4 | $1,574.75 | $1,000.00 | $750.00 | $1,500.00 |
| 28 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01041) | SY | 995 | $52.38 | $32.00 | $57.00 | $50.00 |
| 30 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 65,866 | $1.41 | $1.00 | $2.15 | $2.10 |
| 31 | Non-tracking tack coat (407E20000) | GAL | 5,679 | $5.00 | $3.00 | $2.65 | $3.00 |
| 32 | Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000) | CY | 2,679 | $184.79 | $210.00 | $204.00 | $214.00 |
| 33 | Compacted aggregate (617E10100) | CY | 11 | $281.71 | $300.00 | $150.00 | $220.00 |
| 34 | Valve box adjusted to grade (638E10800) | EACH | 4 | $560.75 | $500.00 | $750.00 | $50.00 |
| 35 | RPM (621E00100) | EACH | 226 | $42.51 | $42.51 | $43.00 | $42.51 |
| 36 | Raised pavement marker removed (621E54000) | EACH | 226 | $10.62 | $10.00 | $1.00 | $4.00 |
| 37 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 16 | $12.00 | $12.00 | $11.80 | $11.80 |
| 38 | Edge line, 6", type 1, as per plan (642E00105) | MI | 1.87 | $1,495.00 | $1,495.00 | $2,100.00 | $1,495.00 |
| 39 | Center line, type 1, as per plan (642E00301) | MI | 1.19 | $2,244.00 | $2,244.00 | $2,280.00 | $2,244.00 |
| 40 | Edge line, 6", as per plan (644E00105) | MI | 3.42 | $3,535.00 | $3,535.00 | $3,470.00 | $3,535.00 |
| 41 | Lane line, 6", as per plan (644E00205) | MI | 0.11 | $7,709.00 | $7,709.00 | $1,470.00 | $7,709.00 |
| 42 | Center line, as per plan (644E00301) | MI | 2.12 | $5,209.00 | $5,209.00 | $5,340.00 | $5,209.00 |
| 43 | Channelizing line, 8" (644E00400) | FT | 1,417 | $1.75 | $1.75 | $2.00 | $1.75 |
| 44 | Stop line, as per plan (644E00501) | FT | 303 | $7.00 | $7.00 | $6.70 | $7.00 |
| 45 | Crosswalk line, 12", as per plan (644E00621) | FT | 1,636 | $3.50 | $3.50 | $3.30 | $3.50 |
| 46 | Transverse/diagonal line, as per plan (644E00701) | FT | 259 | $6.00 | $6.00 | $6.70 | $6.00 |
| 47 | Island marking, as per plan (644E00901) | SF | 60 | $3.00 | $3.00 | $4.00 | $3.00 |
| 48 | Railroad symbol marking, as per plan (644E01001) | EACH | 4 | $575.00 | $575.00 | $422.00 | $575.00 |
| 49 | Lane arrow, as per plan (644E01301) | EACH | 16 | $80.00 | $80.00 | $105.00 | $80.00 |
| 50 | Dotted line, 6", as per plan (644E01511) | FT | 113 | $2.50 | $2.50 | $2.65 | $2.50 |
| 51 | Edge line, 6" (646E10010) | MI | 0.18 | $16,400 | $16,400 | $14,350 | $16,400 |
| 52 | Center line (646E10200) | MI | 0.13 | $32,000 | $32,000 | $22,080 | $32,000 |
| 53 | Channelizing line, 8" (646E10300) | FT | 40 | $15.00 | $15.00 | $8.30 | $15.00 |
| 54 | Transverse/diagonal line (646E10600) | FT | 58 | $15.00 | $15.00 | $27.50 | $15.00 |
| 55 | Lane arrow (646E20300) | EACH | 1 | $405.00 | $405.00 | $445.00 | $405.00 |
| 56 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 48 | $106.40 | $100.00 | $85.00 | $80.00 |
| 57 | Work zone marking sign (614E12460) | EACH | 32 | $115.00 | $150.00 | $150.00 | $115.00 |
| 58 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 0.22 | $750.00 | $750.00 | $925.00 | $750.00 |
| 59 | Work zone center line, class III, 642 paint (614E21550) | MI | 5.43 | $2,700.00 | $2,700.00 | $2,080.00 | $2,700.00 |
| 60 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 3.42 | $1,350.00 | $1,350.00 | $1,385.00 | $1,350.00 |
| 61 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 2,834 | $0.90 | $0.90 | $1.70 | $0.90 |
| 62 | Work zone dotted line, class III, 4", 642 paint (614E24610) | FT | 113 | $1.00 | $1.00 | $2.30 | $1.00 |
| 63 | Work zone stop line, class III, 642 paint (614E26610) | FT | 174 | $3.00 | $3.00 | $5.75 | $3.00 |
| 64 | Work zone crosswalk line, class III, 12", 642 paint (614E27250) | FT | 660 | $1.50 | $1.50 | $2.85 | $1.50 |
| 65 | Work zone railroad symbol marking, class III, 642 paint (614E32210) | EACH | 2 | $245.00 | $245.00 | $405.00 | $245.00 |
| 66 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,028.66 | $28,000 | $5,500.00 | $10,000 |
| 67 | Maintaining traffic (614E11000) | LS | 1 | $18,394 | $33,500 | $50,005 | $100,000 |
| 68 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $4,536.73 | $7,500.00 | $1,000.00 | $6,500.00 |
| 69 | Mobilization (624E10000) | LS | 1 | $40,000 | $50,000 | $65,000 | $83,000 |
| 100 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01043) | CY | 521 | $321.05 | $300.00 | $320.00 | $400.00 |
| 101 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01043) | CY | 24 | $505.50 | $300.00 | $375.00 | $1,100.00 |
| 102 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 107 | $375.40 | $210.00 | $360.00 | $320.00 |
| 103 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $1,050.00 | $1,500.00 | $900.00 | $1,050.00 |
| 104 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $5,000.00 | $10,000 | $3,150.00 | $2,500.00 |
| 105 | Ground mounted support, no. 2 post (630E02100) | FT | 20 | $12.00 | $12.00 | $40.00 | $16.00 |
| 106 | Ground mounted support, no. 3 post (630E03100) | FT | 14 | $25.00 | $25.00 | $42.50 | $16.50 |
| 107 | Sign, flat sheet (630E80100) | SF | 2 | $35.00 | $35.00 | $45.00 | $19.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.