ODOT contract 250161 bid tabulation
LAK-IR 90-02.93 Slope (SLIDE REPAIR). Let by Ohio DOT on March 27, 2025, LAK. 2 bids received; low bid $4,963,840 by Great Lakes Crushing LTD, +54% against the engineer's estimate of $3,230,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 64
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Great Lakes Crushing LTD | $4,963,840 | Low | +54% |
| 2 | Great Lakes Construction Co | $4,710,752 | -5.0% | +46% |
Engineer's estimate: $3,230,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Great Lakes Crushing LTD | 2. Great Lakes Construction Co |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $25,000 |
| 2 | Headwall removed, as per plan (202E20011) | EACH | 2 | $500.00 | $3,000.00 |
| 3 | Pavement removed (202E23000) | SY | 51 | $25.00 | $70.00 |
| 4 | Pipe removed (202E34900) | FT | 50 | $100.00 | $55.00 |
| 5 | Guardrail removed (202E38000) | FT | 100 | $10.00 | $5.40 |
| 6 | Excavation (203E10000) | CY | 1,116 | $60.00 | $32.00 |
| 7 | Embankment (203E20000) | CY | 100 | $100.00 | $30.00 |
| 8 | Roadway, misc.:contractor access (203E98500) | LS | 1 | $446,000 | $335,000 |
| 9 | Reshaping under guardrail, as per plan (209E15001) | STA | 1 | $10,000 | $650.00 |
| 10 | Guardrail, type MGS (606E15050) | FT | 100 | $75.00 | $53.20 |
| 11 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 195 | $200.00 | $150.00 |
| 12 | Rock channel protection, type B with aggregate filter (601E32110) | CY | 228 | $250.00 | $150.00 |
| 13 | Paved gutter, type 1-4 (601E38000) | FT | 96 | $75.00 | $125.00 |
| 14 | Soil analysis test (659E00100) | EACH | 2 | $500.00 | $300.00 |
| 15 | Topsoil (659E00300) | CY | 522 | $35.00 | $40.00 |
| 16 | Seeding and mulching (659E10000) | SY | 4,698 | $10.00 | $0.95 |
| 17 | Repair seeding and mulching (659E14000) | SY | 235 | $10.00 | $2.00 |
| 18 | Inter-seeding (659E15000) | SY | 235 | $10.00 | $0.25 |
| 19 | Commercial fertilizer (659E20000) | TON | 0.63 | $10,000 | $1,500.00 |
| 20 | Lime (659E31000) | ACRE | 0.98 | $10,000 | $50.00 |
| 21 | Water (659E35000) | MGAL | 25.37 | $10.00 | $1.00 |
| 22 | Storm water pollution prevention plan (832E15000) | LS | 1 | $15,000 | $3,500.00 |
| 23 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $7,500.00 | $21,500 |
| 24 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $35,000 | $18,000 |
| 25 | Erosion control (832E30000) | EACH | 35,000 | $1.00 | $1.00 |
| 26 | Concrete masonry (602E20000) | CY | 0.76 | $1,500.00 | $5,700.00 |
| 27 | Concrete masonry, as per plan (602E20001) | CY | 8.64 | $2,500.00 | $3,900.00 |
| 28 | 36" conduit, type A, as per plan (611E16201) | FT | 50 | $500.00 | $500.00 |
| 29 | Conduit, misc.: pacp inspection (611E97300) | LS | 1 | $5,000.00 | $5,500.00 |
| 30 | Pavement planing, asphalt concrete (1.0" depth) (254E01000) | SY | 62 | $200.00 | $150.00 |
| 31 | Pavement planing, asphalt concrete (1.5" depth) (254E01000) | SY | 834 | $35.00 | $8.00 |
| 32 | Non-tracking tack coat (407E20000) | GAL | 75 | $25.00 | $2.00 |
| 33 | Asphalt concrete intermediate course, type 1, (449), (under guardrail), as per plan (441E70801) | CY | 4 | $2,000.00 | $1,000.00 |
| 34 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 35 | $1,500.00 | $430.00 |
| 35 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 0.57 | $25,000 | $10,500 |
| 36 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $125.00 | $100.00 |
| 37 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 1 | $4,500.00 | $2,500.00 |
| 38 | Replacement sign (614E12500) | EACH | 5 | $200.00 | $180.00 |
| 39 | Work zone raised pavement marker, as per plan (614E12801) | EACH | 825 | $10.00 | $52.69 |
| 40 | Barrier reflector, type 1 (one-way or BI-direction (614E13310) | EACH | 18 | $20.00 | $15.00 |
| 41 | Object marker, one way (614E13350) | EACH | 18 | $30.00 | $24.00 |
| 42 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,500.00 | $950.00 |
| 43 | Water (616E10000) | MGAL | 22 | $10.00 | $50.00 |
| 44 | Portable barrier, unanchored (622E41100) | FT | 850 | $50.00 | $60.00 |
| 45 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $525,000 | $536,000 |
| 46 | Unclassified excavation (503E21100) | CY | 2,345 | $25.00 | $70.00 |
| 47 | Steel piles, misc.:W24X 207, furnished (507E00400) | FT | 94.19 | $100.00 | $220.00 |
| 48 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 1,456 | $5.00 | $3.40 |
| 49 | Prefabricated geocomposite drain (518E20000) | SY | 386 | $50.00 | $20.00 |
| 50 | 4" perforated corrugated plastic pipe (518E39800) | FT | 156 | $50.00 | $40.00 |
| 51 | Pneumatically placed concrete shotcrete (520E10000) | SF | 3,476 | $30.00 | $38.60 |
| 52 | Drilled shafts, misc.:plug pile 36" diameter, unre (524E95000) | FT | 2,146 | $175.00 | $235.00 |
| 53 | Special - retaining wall, soil nail (530E51100) | EACH | 240 | $2,500.00 | $1,715.00 |
| 54 | Special - retaining wall, soil nail verification test (530E51110) | EACH | 3 | $6,000.00 | $2,000.00 |
| 55 | Special - retaining wall, soil nail proof test (530E51120) | EACH | 6 | $1,200.00 | $400.00 |
| 56 | Steel piles, misc.: W24X146, furnished (alternate [alternate group AA1] (507E00400) | FT | 4,003 | $200.00 | $147.00 |
| 57 | Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705) | FT | 1,440 | $350.00 | $233.00 |
| 58 | Drilled shafts, 42" diameter, above bedrock, as per plan (524E94803) | FT | 2,681.27 | $175.00 | $233.00 |
| 61 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $75,000 | $75,000 |
| 62 | CPM progress schedule (108E10000) | LS | 1 | $15,000 | $550.00 |
| 63 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $75,000 | $150,000 |
| 64 | Field office, type B, as per plan (619E16011) | MNTH | 12 | $3,500.00 | $4,750.00 |
| 65 | Construction layout stakes and surveying (623E10000) | LS | 1 | $50,000 | $20,000 |
| 66 | Mobilization (624E10000) | LS | 1 | $100,000 | $232,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.