ODOT contract 250214 bid tabulation
CAR-Magnolia Sidewalks (SIDEWALK). Let by Ohio DOT on April 24, 2025, CAR. 4 bids received; low bid $519,849 by Stanley Miller Construction Company, -5.7% against the engineer's estimate of $551,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 46
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Stanley Miller Construction Company | $519,849 | Low | -6.0% |
| 2 | LMS Construction Inc | $586,999 | +13% | +7.0% |
| 3 | Shelly & Sands Inc | $590,255 | +14% | +7.0% |
| 4 | Shelly Company | $610,791 | +17% | +11% |
Engineer's estimate: $551,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stanley Miller Construction Company | 2. LMS Construction Inc | 3. Shelly & Sands Inc | 4. Shelly Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,722.00 | $2,500.00 | $540.00 | $4,500.00 |
| 2 | Pavement removed (202E23000) | SY | 258 | $26.00 | $23.00 | $34.00 | $35.00 |
| 3 | Walk removed, as per plan (202E30001) | SF | 14,692 | $1.20 | $2.00 | $2.00 | $4.50 |
| 4 | Curb removed (202E32000) | FT | 1,081 | $4.70 | $15.00 | $7.00 | $16.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 20 | $80.00 | $5.00 | $80.00 | $40.00 |
| 6 | Manhole removed (202E58000) | EACH | 1 | $2,000.00 | $600.00 | $1,300.00 | $1,000.00 |
| 7 | Excavation (203E10000) | CY | 8 | $90.00 | $300.00 | $95.00 | $65.00 |
| 8 | Embankment (203E20000) | CY | 16 | $100.00 | $150.00 | $40.00 | $120.00 |
| 9 | Subgrade compaction (204E10000) | SY | 2,644 | $1.00 | $5.00 | $2.20 | $5.60 |
| 10 | 4" concrete walk, as per plan (608E10001) | SF | 17,630 | $8.35 | $8.25 | $6.50 | $6.65 |
| 11 | 6" concrete walk, as per plan (608E13001) | SF | 1,237 | $10.50 | $17.00 | $21.00 | $10.35 |
| 12 | Curb ramp, as per plan (608E52001) | SF | 1,036 | $34.00 | $38.00 | $50.00 | $22.00 |
| 13 | Walkway, misc.: monolithic curb and sidewalk (608E98000) | SF | 1,174 | $18.36 | $20.00 | $20.00 | $10.50 |
| 14 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $50.00 | $130.00 | $400.00 |
| 15 | Topsoil (659E00300) | CY | 32 | $50.00 | $10.00 | $158.00 | $250.00 |
| 16 | Seeding and mulching, class 1 (659E00500) | SY | 286 | $7.00 | $10.00 | $19.00 | $4.00 |
| 17 | Repair seeding and mulching (659E14000) | SY | 14 | $1.00 | $5.00 | $1.00 | $10.00 |
| 18 | Commercial fertilizer (659E20000) | TON | 0.01 | $800.00 | $20,000 | $1,050.00 | $2,000.00 |
| 19 | Lime (659E31000) | ACRE | 0.06 | $150.00 | $5,000.00 | $168.00 | $100.00 |
| 20 | Water (659E35000) | MGAL | 5 | $1.00 | $10.00 | $1.10 | $10.00 |
| 21 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | 24" conduit, type C (611E10600) | FT | 30 | $75.00 | $101.00 | $170.00 | $198.00 |
| 23 | Manhole, no. 3 (611E99574) | EACH | 1 | $6,000.00 | $10,000 | $5,100.00 | $4,250.00 |
| 24 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 32 | $650.00 | $650.00 | $875.00 | $550.00 |
| 25 | Aggregate base (304E20000) | CY | 69 | $160.00 | $200.00 | $175.00 | $240.00 |
| 26 | Tack coat (407E10000) | GAL | 18 | $25.00 | $10.00 | $3.50 | $3.00 |
| 27 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 7 | $1,200.00 | $1,300.00 | $1,300.00 | $1,000.00 |
| 28 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 9 | $950.00 | $1,350.00 | $1,000.00 | $800.00 |
| 29 | 4" non-reinforced concrete pavement, class QC 1P (452E09010) | SY | 112 | $90.50 | $180.00 | $60.00 | $70.00 |
| 30 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 131 | $99.00 | $190.00 | $200.00 | $114.00 |
| 31 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 27 | $160.00 | $267.00 | $160.00 | $160.00 |
| 32 | Curb, type 4-C (609E24510) | FT | 734 | $34.00 | $45.00 | $42.00 | $40.00 |
| 33 | Special - brick paver restoration and reinstallat (690E98200) | SF | 1,012 | $21.00 | $31.00 | $45.00 | $50.00 |
| 34 | 6" fire hydrant (638E10200) | EACH | 1 | $14,800 | $9,000.00 | $5,919.83 | $9,375.00 |
| 35 | Fire hydrant removed (638E10480) | EACH | 1 | $2,800.00 | $1,200.00 | $996.92 | $1,385.00 |
| 36 | Valve box adjusted to grade (638E10800) | EACH | 3 | $500.00 | $600.00 | $5,900.00 | $100.00 |
| 37 | Signing, misc.: solar powered rectangular rapid FL (630E97700) | EACH | 2 | $8,000.00 | $7,500.00 | $7,600.00 | $11,200 |
| 38 | Crosswalk line, 24", as per plan (644E00631) | FT | 50 | $40.00 | $25.00 | $20.00 | $18.30 |
| 39 | Removal of pavement marking (644E30000) | FT | 20 | $50.00 | $10.00 | $22.00 | $20.00 |
| 40 | Water (616E10000) | MGAL | 5 | $1.00 | $10.00 | $87.00 | $10.00 |
| 41 | Concrete, misc.: retaining wall (511E71100) | CY | 1 | $3,000.00 | $3,800.00 | $2,500.00 | $2,000.00 |
| 42 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $25,000 | $3,295.00 | $8,000.00 |
| 43 | Maintaining traffic (614E11000) | LS | 1 | $17,500 | $6,000.00 | $35,000 | $60,000 |
| 44 | Field office, type B (619E16010) | MNTH | 4 | $1,500.00 | $1,500.00 | $4,500.00 | $2,000.00 |
| 45 | Construction layout stakes and surveying (623E10000) | LS | 1 | $25,000 | $1,000.00 | $4,700.00 | $6,000.00 |
| 46 | Mobilization (624E10000) | LS | 1 | $22,500 | $20,000 | $15,000 | $30,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.