ODOT contract 250225 bid tabulation

SAN-SR-SR 53-10.45 Resurf & UrbPav (FOUR LANE RESURFACING). Let by Ohio DOT on April 24, 2025, SAN. 3 bids received; low bid $1,849,844 by Kokosing Construction Company Inc, -4.7% against the engineer's estimate of $1,941,000.

Owner
Ohio DOT
Letting
24 APR 2025
Pay items
41
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Kokosing Construction Company Inc$1,849,844Low-5.0%
2Gerken Paving Inc$1,879,279+2.0%-3.0%
3M & B Asphalt Co Inc$1,993,253+8.0%+3.0%
ODOT contract 250225: bids by rank

Engineer's estimate: $1,941,000.

Bid tabulation

LinePay itemUnitQuantity1. Kokosing Construction Company Inc2. Gerken Paving Inc3. M & B Asphalt Co Inc
1Pavement removed (202E23000)SY6$150.00$100.00$90.00
2Walk removed (202E30000)SF48$10.00$15.00$20.00
3Linear grading (209E60500)MI4.88$2,500.00$1,600.00$1,600.00
4Seeding and mulching (659E10000)SY6$10.00$50.00$200.00
5Erosion control (832E30000)EACH1,000$1.00$1.00$1.00
6Catch basin adjusted to grade (611E98630)EACH1$600.00$1,500.00$1,800.00
7Manhole adjusted to grade (611E99654)EACH1$700.00$1,500.00$1,800.00
8Partial depth pavement repair (441) (251E01010)CY230$410.00$300.00$260.00
9Pavement planing, asphalt concrete, 1 3/4" (254E01000)SY110,903$1.20$1.70$1.75
10Non-tracking tack coat (407E20000)GAL9,427$2.50$2.25$2.65
11Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000)CY5,391$228.00$214.00$225.00
12Compacted aggregate (617E10100)CY435$30.00$92.00$67.00
13Void reducing asphalt membrane (vram) (872E10000)FT38,007$1.85$3.00$2.20
14Valve box adjusted to grade (638E10800)EACH2$500.00$800.00$350.00
15RPM (621E00100)EACH309$45.00$45.00$50.00
16Raised pavement marker removed (621E54000)EACH309$4.00$6.00$3.00
17Edge line, 6", type 1 (642E00104)MI4.65$650.00$650.00$650.00
18Lane line, 6", type 1 (642E00204)MI4.03$500.00$500.00$500.00
19Center line, type 1 (642E00300)MI4.69$800.00$800.00$800.00
20Channelizing line, 12" (644E00404)FT4,497$2.00$2.00$2.00
21Stop line (644E00500)FT375$5.50$5.50$5.50
22Transverse/diagonal line (644E00700)FT909$5.50$5.50$5.50
23Chevron marking (644E00720)FT136$5.50$5.50$5.50
24Lane arrow (644E01300)EACH54$90.00$90.00$90.00
25Dotted line, 6" (644E01510)FT3,562$1.00$1.00$1.00
27Stop line radar detection, as per plan (809E69101)EACH4$9,400.00$9,050.00$9,050.00
28Law enforcement officer with patrol car for assistance (614E11110)HR80$100.00$90.00$88.00
29Work zone marking sign (614E12460)EACH50$50.00$120.00$100.00
30Replacement sign (614E12500)EACH5$150.00$145.00$100.00
31Replacement drum (614E12600)EACH5$50.00$105.00$75.00
32Work zone lane line, class I, 6" (614E20010)MI10$500.00$500.00$500.00
33Work zone center line, class I, 642 paint (614E21100)MI9$800.00$800.00$800.00
34Work zone edge line, class I, 6", 642 paint (614E22110)MI10$600.00$650.00$650.00
35Work zone channelizing line, class I, 8", 642 paint (614E23200)FT8,994$0.75$0.75$0.75
36Work zone dotted line, class I, 6", 642 paint (614E24202)FT7,124$0.50$0.50$0.50
37Work zone stop line, class I, 642 paint (614E26200)FT702$1.50$1.50$1.50
38Work zone arrow, class I, 642 paint (614E30200)EACH108$35.00$35.00$35.00
39Premium for contract performance bond and for payment bond (103E05000)LS1$7,500.00$9,000.00$11,000
40Maintaining traffic (614E11000)LS1$36,994$72,000$175,000
41Construction layout stakes and surveying (623E10000)LS1$2,000.00$2,525.00$3,500.00
42Mobilization (624E10000)LS1$91,350$60,000$50,000
ODOT contract 250225: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy