ODOT contract 250230 bid tabulation
TUS-Maple & Church St Improve (MINOR RECONSTRUCTION). Let by Ohio DOT on April 24, 2025, TUS. 1 bid received; low bid $2,284,203 by Shelly & Sands Inc, -1.2% against the engineer's estimate of $2,311,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 70
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $2,284,203 | Low | -1.0% |
Engineer's estimate: $2,311,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc |
|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 3,150 | $14.00 |
| 3 | Walk removed, as per plan (202E30001) | SF | 15,123 | $1.00 |
| 4 | Steps removed (202E30200) | FT | 4 | $70.00 |
| 5 | Curb removed (202E32000) | FT | 3,593 | $4.00 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 3,348 | $4.00 |
| 7 | Manhole removed (202E58000) | EACH | 3 | $350.00 |
| 8 | Catch basin removed (202E58100) | EACH | 8 | $340.00 |
| 9 | Excavation (203E10000) | CY | 25 | $33.00 |
| 10 | Embankment (203E20000) | CY | 267 | $33.00 |
| 11 | Subgrade compaction (204E10000) | SY | 5,684 | $4.50 |
| 12 | 4" concrete walk, as per plan (608E10001) | SF | 16,971 | $7.75 |
| 13 | 6" concrete walk, as per plan (608E13001) | SF | 466 | $18.00 |
| 14 | 8" concrete walk, as per plan (608E15001) | SF | 456 | $17.00 |
| 15 | Concrete steps, type A (608E40000) | FT | 4 | $450.00 |
| 16 | Curb ramp, as per plan (608E52001) | SF | 1,295 | $60.00 |
| 17 | Special - mailbox support system, single (690E50100) | EACH | 28 | $600.00 |
| 18 | Paved gutter, misc.: paved gutter (601E40000) | FT | 149 | $199.00 |
| 19 | Soil analysis test (659E00100) | EACH | 2 | $134.00 |
| 20 | Topsoil (659E00300) | CY | 659 | $75.00 |
| 21 | Seeding and mulching, class 1 (659E00500) | SY | 3,226 | $2.00 |
| 22 | Seeding and mulching (659E10000) | SY | 2,710 | $1.00 |
| 23 | Repair seeding and mulching (659E14000) | SY | 161 | $1.00 |
| 24 | Commercial fertilizer (659E20000) | TON | 0.44 | $950.00 |
| 25 | Lime (659E31000) | ACRE | 0.67 | $170.00 |
| 26 | Water (659E35000) | MGAL | 18 | $1.00 |
| 27 | Slope erosion protection (670E00500) | SY | 2,710 | $1.50 |
| 28 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,700.00 |
| 29 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,700.00 |
| 30 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $8,050.00 |
| 31 | Erosion control (832E30000) | EACH | 20,000 | $1.00 |
| 32 | 6" conduit, type C, as per plan (611E01101) | FT | 30 | $40.00 |
| 33 | 12" conduit, type B, as per plan (611E04401) | FT | 897 | $134.00 |
| 34 | 18" conduit, type B, as per plan (611E07401) | FT | 174 | $140.00 |
| 35 | 24" conduit, type B, as per plan (611E10401) | FT | 10 | $300.00 |
| 36 | 24" conduit, type C, as per plan (611E10601) | FT | 8 | $300.00 |
| 37 | Conduit, misc.: type C for drainage discharge cont (611E97400) | FT | 100 | $35.00 |
| 38 | Conduit, misc.: type E for drainage discharge cont (611E97400) | FT | 100 | $35.00 |
| 39 | Conduit, misc.: type F for drainage discharge cont (611E97400) | FT | 100 | $35.00 |
| 40 | Catch basin, no. 3 (611E98150) | EACH | 2 | $3,800.00 |
| 41 | Catch basin, no. 3A (611E98180) | EACH | 18 | $3,200.00 |
| 42 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $2,200.00 |
| 43 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 605 | $240.00 |
| 44 | Aggregate base (304E20000) | CY | 705 | $125.00 |
| 45 | Tack coat (407E10000) | GAL | 657 | $3.50 |
| 46 | Tack coat, 702.13 (407E13900) | GAL | 417 | $3.50 |
| 47 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 237 | $250.00 |
| 48 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 392 | $225.00 |
| 49 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 23 | $750.00 |
| 50 | 6" non-reinforced concrete pavement, class QC 1P, as per plan (452E10011) | SY | 105 | $150.00 |
| 51 | 8" non-reinforced concrete pavement, class QC 1P, as per plan (452E12011) | SY | 133 | $130.00 |
| 52 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 3,709 | $30.00 |
| 53 | 6" water main polyvinyl chloride pipe and fittings, AWWA C900, DR18, as per plan (638E01131) | FT | 2,391 | $115.00 |
| 54 | 3/4" polyethylene service branch, as per plan (638E05301) | FT | 969 | $106.00 |
| 55 | 6" gate valve and valve box (638E07800) | EACH | 14 | $1,650.00 |
| 56 | 6" X 6" tapping sleeve, valve and valve box (638E09300) | EACH | 1 | $3,900.00 |
| 57 | 6" fire hydrant (638E10200) | EACH | 5 | $9,200.00 |
| 58 | Fire hydrant removed (638E10480) | EACH | 5 | $800.00 |
| 59 | Water work, misc.:connection to existing waterline (638E98000) | EACH | 6 | $4,000.00 |
| 60 | 6" conduit, type B, as per plan (611E00901) | FT | 251 | $240.00 |
| 61 | 8" conduit, type B, as per plan (611E01801) | FT | 713 | $200.00 |
| 62 | Manhole, no. 3, as per plan (611E99575) | EACH | 3 | $7,200.00 |
| 63 | Water (616E10000) | MGAL | 5 | $200.00 |
| 64 | Concrete, misc.: concrete retaining wall (511E71300) | SY | 12 | $3,000.00 |
| 65 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,714 |
| 66 | Maintaining traffic (614E11000) | LS | 1 | $65,000 |
| 67 | Field office, type B (619E16010) | MNTH | 5 | $3,600.00 |
| 68 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,000 |
| 69 | Mobilization (624E10000) | LS | 1 | $110,000 |
| 100 | Pavement planing, asphalt concrete' 3? (254E01000) | SY | 1,713 | $13.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.