ODOT contract 250261 bid tabulation
SUM-Barberton Sidewalks (SIDEWALK). Let by Ohio DOT on May 8, 2025, SUM. 3 bids received; low bid $750,534 by Fabrizi Trucking & Paving Co Inc, +1.6% against the engineer's estimate of $739,000.
- Owner
- Ohio DOT
- Letting
- 08 MAY 2025
- Pay items
- 75
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fabrizi Trucking & Paving Co Inc | $750,534 | Low | +2.0% |
| 2 | Shelly & Sands Inc | $773,518 | +3.0% | +5.0% |
| 3 | Stanley Miller Construction Company | $971,741 | +29% | +31% |
Engineer's estimate: $739,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fabrizi Trucking & Paving Co Inc | 2. Shelly & Sands Inc | 3. Stanley Miller Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $4,267.00 | $2,000.00 | $5,000.00 |
| 2 | Pavement removed (202E23000) | SY | 1,130 | $18.25 | $18.00 | $17.00 |
| 3 | Walk removed (202E30000) | SF | 2,990 | $1.75 | $1.25 | $5.00 |
| 4 | Curb removed (202E32000) | FT | 218 | $8.00 | $11.00 | $5.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 205 | $5.00 | $11.00 | $40.00 |
| 6 | Catch basin removed (202E58100) | EACH | 4 | $375.00 | $200.00 | $1,500.00 |
| 7 | Removal misc.: inspection well (202E98100) | EACH | 1 | $1,360.00 | $300.00 | $5,000.00 |
| 8 | Removal misc.: conduit (202E98200) | FT | 5 | $5.00 | $40.00 | $400.00 |
| 9 | Excavation (203E10000) | CY | 75 | $68.00 | $55.00 | $130.00 |
| 10 | Embankment (203E20000) | CY | 160 | $90.00 | $68.00 | $120.00 |
| 11 | Embankment, as per plan (203E20001) | CY | 50 | $82.00 | $15.00 | $130.00 |
| 12 | Roadway, misc.:pre-construction video (203E98500) | LS | 1 | $878.00 | $1,500.00 | $5,000.00 |
| 13 | Subgrade compaction (204E10000) | SY | 1,116 | $4.00 | $8.00 | $2.00 |
| 14 | 4" concrete walk, as per plan (608E10001) | SF | 10,055 | $11.75 | $9.00 | $10.50 |
| 15 | Curb ramp, as per plan (608E52001) | SF | 801 | $24.00 | $28.00 | $40.00 |
| 16 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $190.00 | $280.00 | $1,000.00 |
| 17 | Special - survey control verification (690E98400) | LS | 1 | $1,287.00 | $2,000.00 | $6,000.00 |
| 18 | Soil analysis test (659E00100) | EACH | 2 | $52.00 | $160.00 | $150.00 |
| 19 | Topsoil (659E00300) | CY | 85 | $410.00 | $130.00 | $60.00 |
| 20 | Seeding and mulching (659E10000) | SY | 760 | $2.25 | $5.30 | $9.00 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.10 | $1,475.00 | $1,300.00 | $800.00 |
| 22 | Lime (659E31000) | ACRE | 0.16 | $850.00 | $160.00 | $150.00 |
| 23 | Water (659E35000) | MGAL | 6.16 | $20.00 | $1.00 | $1.00 |
| 24 | Erosion control (832E30000) | EACH | 5,200 | $1.00 | $1.00 | $1.00 |
| 25 | 6" base pipe underdrains with geotextile fabric, as per plan (605E14021) | FT | 865 | $16.50 | $27.00 | $10.00 |
| 26 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 80 | $18.00 | $32.00 | $50.00 |
| 27 | 12" conduit, type B (611E04400) | FT | 529 | $135.00 | $117.00 | $75.00 |
| 28 | 15" conduit, type B (611E05900) | FT | 165 | $155.00 | $108.00 | $75.00 |
| 29 | Conduit, misc.: type C for drainage discharge cont (611E97400) | FT | 5 | $165.00 | $30.00 | $150.00 |
| 30 | Conduit, misc.: type E for drainage discharge cont (611E97400) | FT | 5 | $185.00 | $30.00 | $150.00 |
| 31 | Conduit, misc.: type F for drainage discharge cont (611E97400) | FT | 5 | $185.00 | $30.00 | $150.00 |
| 32 | Catch basin, no. 3 (611E98150) | EACH | 1 | $6,045.00 | $4,700.00 | $5,000.00 |
| 33 | Catch basin, no. 3A (611E98180) | EACH | 6 | $4,945.00 | $3,600.00 | $5,000.00 |
| 34 | Catch basin, no. 6 (611E98370) | EACH | 1 | $4,691.00 | $4,500.00 | $4,500.00 |
| 35 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $4,718.00 | $3,200.00 | $5,000.00 |
| 36 | Manhole, no. 3 (611E99574) | EACH | 1 | $7,704.00 | $4,500.00 | $6,000.00 |
| 37 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 4 | $1,105.00 | $3,000.00 | $1,000.00 |
| 38 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 1 | $975.00 | $2,500.00 | $1,000.00 |
| 39 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $1,794.00 | $3,500.00 | $2,000.00 |
| 40 | Inspection well (611E99720) | EACH | 1 | $895.00 | $1,000.00 | $5,000.00 |
| 41 | Special - miscellaneous metal (611E99820) | LB | 400 | $2.75 | $2.00 | $20.00 |
| 42 | Drainage structure, misc.: trench drain (611E99900) | EACH | 2 | $4,688.00 | $2,500.00 | $5,000.00 |
| 43 | Pavement planing, asphalt concrete (T=1.25") (254E01000) | SY | 4,416 | $4.75 | $5.00 | $4.70 |
| 44 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 65 | $212.00 | $275.00 | $211.75 |
| 45 | Aggregate base (304E20000) | CY | 151 | $85.00 | $180.00 | $200.00 |
| 46 | Non-tracking tack coat (407E20000) | GAL | 421 | $4.00 | $3.00 | $3.65 |
| 47 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 169 | $382.00 | $240.00 | $384.00 |
| 48 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 18 | $217.00 | $330.00 | $217.65 |
| 49 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 2 | $585.00 | $768.00 | $588.00 |
| 50 | Asphalt concrete intermediate course, type 2, (449), (driveways) (441E70700) | CY | 1 | $585.00 | $1,400.00 | $588.00 |
| 51 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 661 | $96.00 | $103.00 | $110.00 |
| 52 | 8" non-reinforced concrete pavement, class QC MS (452E12050) | SY | 40 | $105.00 | $121.00 | $150.00 |
| 53 | Curb, type 6, as per plan (609E26001) | FT | 1,291 | $33.00 | $31.00 | $42.00 |
| 54 | Longitudinal joint adhesive (875E10000) | LB | 276 | $5.90 | $0.90 | $5.90 |
| 55 | 1" polyethylene service branch (638E05400) | FT | 150 | $62.00 | $52.00 | $30.00 |
| 56 | Valve box adjusted to grade (638E10800) | EACH | 5 | $115.00 | $190.00 | $500.00 |
| 57 | Service box adjusted to grade (638E10900) | EACH | 1 | $115.00 | $375.00 | $2,000.00 |
| 58 | Ground mounted support, no. 3 post (630E03100) | FT | 14.10 | $13.00 | $12.00 | $50.00 |
| 59 | Street name sign support, no. 3 post (630E08520) | FT | 12.60 | $19.00 | $17.00 | $50.00 |
| 60 | Sign, flat sheet (630E80100) | SF | 6.30 | $26.00 | $23.00 | $65.00 |
| 61 | Sign, flat sheet, as per plan (630E80101) | SF | 20.20 | $35.00 | $32.00 | $65.00 |
| 62 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $23.50 | $21.00 | $35.00 |
| 63 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $23.50 | $21.00 | $35.00 |
| 64 | Edge line, 4" (644E00100) | MI | 0.26 | $4,507.00 | $4,100.00 | $10,000 |
| 65 | Center line (644E00300) | MI | 0.26 | $6,380.00 | $5,800.00 | $20,000 |
| 66 | Work zone marking sign (614E12460) | EACH | 10 | $82.00 | $75.00 | $250.00 |
| 67 | Work zone center line, class I (614E21000) | MI | 0.26 | $2,927.00 | $2,600.00 | $10,000 |
| 68 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.26 | $2,927.00 | $2,600.00 | $10,000 |
| 69 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,305.00 | $5,000.00 | $20,000 |
| 70 | Maintaining traffic (614E11000) | LS | 1 | $34,225 | $87,000 | $43,530 |
| 71 | Field office, type B (619E16010) | MNTH | 6 | $2,065.00 | $3,500.00 | $1,800.00 |
| 72 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,565.00 | $12,000 | $30,000 |
| 73 | Mobilization (624E10000) | LS | 1 | $10,476 | $35,000 | $59,000 |
| 74 | Special - as-built construction plans (690E91000) | LS | 1 | $2,341.00 | $2,000.00 | $70,000 |
| 100 | Special - fill and plug existing conduit (202E70000) | FT | 51 | $52.00 | $36.00 | $500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.