ODOT contract 250531 bid tabulation
MUS-US 22/SR 83-26.63/00.00 (TWO LANE RESURFACING). Let by Ohio DOT on November 13, 2025, MUS. 3 bids received; low bid $5,775,000 by NLS Paving, Inc, +3.8% against the engineer's estimate of $5,566,000.
- Owner
- Ohio DOT
- Letting
- 13 NOV 2025
- Pay items
- 66
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | NLS Paving, Inc | $5,775,000 | Low | +4.0% |
| 2 | Shelly Company | $5,840,108 | +1.0% | +5.0% |
| 3 | Shelly & Sands Inc | $6,234,227 | +8.0% | +12% |
Engineer's estimate: $5,566,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. NLS Paving, Inc | 2. Shelly Company | 3. Shelly & Sands Inc |
|---|---|---|---|---|---|---|
| 1 | Pavement removed, as per plan (202E23001) | SY | 146 | $100.00 | $30.00 | $95.00 |
| 2 | Wearing course removed (202E23500) | SY | 9,254 | $7.50 | $7.50 | $11.00 |
| 3 | Walk removed (202E30000) | SF | 512 | $18.00 | $12.00 | $6.00 |
| 4 | Curb removed (202E32000) | FT | 72 | $30.00 | $17.00 | $18.00 |
| 5 | Excavation (203E10000) | CY | 1 | $700.00 | $150.00 | $400.00 |
| 6 | Preparing subgrade for shoulder paving, as per plan (209E72051) | MI | 30.12 | $1,650.00 | $1,500.00 | $2,600.00 |
| 7 | 4" concrete walk (608E10000) | SF | 50 | $35.00 | $20.00 | $60.00 |
| 8 | 6" concrete walk (608E13000) | SF | 55 | $40.00 | $20.00 | $55.00 |
| 9 | Curb ramp (608E52000) | SF | 566 | $45.00 | $20.00 | $35.00 |
| 10 | Detectable warning (608E53020) | SF | 24 | $45.00 | $50.00 | $55.00 |
| 11 | Curb, type 6 (609E26000) | FT | 64 | $55.00 | $40.00 | $75.00 |
| 12 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 20 | $2,150.00 | $1,100.00 | $1,200.00 |
| 13 | Catch basin reconstructed to grade, as per plan (611E98635) | EACH | 1 | $3,200.00 | $1,500.00 | $1,700.00 |
| 14 | Manhole adjusted to grade (611E99654) | EACH | 18 | $1,600.00 | $1,100.00 | $1,200.00 |
| 15 | Valve box adjusted to grade (638E10800) | EACH | 5 | $750.00 | $430.00 | $800.00 |
| 16 | Full depth rigid pavement removal and flexible replacement, as per plan (252E01001) | SY | 320 | $215.00 | $244.00 | $350.00 |
| 17 | Full depth pavement sawing (252E01500) | FT | 1,586 | $5.00 | $5.65 | $1.75 |
| 18 | Pavement repair (253E02000) | CY | 2,650 | $345.00 | $315.50 | $365.00 |
| 19 | Pavement repair (253E02000) | CY | 150 | $525.00 | $855.00 | $685.00 |
| 20 | Pavement planing, asphalt concrete, 1.50" (254E01000) | SY | 256,219 | $1.85 | $2.30 | $3.00 |
| 21 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 28 | $525.00 | $325.00 | $750.00 |
| 22 | Aggregate base (304E20000) | CY | 24 | $350.00 | $190.00 | $290.00 |
| 23 | Non-tracking tack coat (407E20000) | GAL | 21,033 | $3.25 | $4.10 | $3.30 |
| 24 | Prime coat, as per plan (408E10001) | GAL | 14,316 | $4.50 | $4.50 | $4.75 |
| 25 | Sawing and sealing asphalt concrete pavement joints (409E30000) | FT | 52 | $29.00 | $28.79 | $32.50 |
| 26 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 10,680 | $230.00 | $233.00 | $230.00 |
| 27 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 326 | $500.00 | $385.00 | $485.00 |
| 28 | 2" deep joint sealer, as per plan (516E31011) | FT | 378 | $29.00 | $28.79 | $32.50 |
| 29 | Compacted aggregate, as per plan (617E10101) | CY | 1,964 | $78.50 | $90.00 | $115.00 |
| 30 | RPM (621E00100) | EACH | 1,466 | $36.00 | $36.00 | $34.00 |
| 31 | Raised pavement marker removed (621E54000) | EACH | 1,466 | $8.00 | $4.25 | $17.00 |
| 32 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 37.50 | $38.00 | $35.00 | $38.00 |
| 33 | Sign, flat sheet (630E80100) | SF | 27 | $52.00 | $35.00 | $52.00 |
| 34 | Edge line, 6" (644E00104) | MI | 30.80 | $3,500.00 | $3,580.00 | $3,500.00 |
| 35 | Lane line, 6" (644E00204) | MI | 0.86 | $2,500.00 | $2,465.00 | $2,500.00 |
| 36 | Center line (644E00300) | MI | 15.86 | $4,500.00 | $4,795.00 | $4,500.00 |
| 37 | Channelizing line, 8" (644E00400) | FT | 1,030 | $2.00 | $2.80 | $2.00 |
| 38 | Stop line (644E00500) | FT | 1,133 | $5.00 | $11.10 | $5.00 |
| 39 | Crosswalk line, 12" (644E00620) | FT | 2,004 | $4.00 | $4.80 | $4.00 |
| 40 | Transverse/diagonal line (644E00700) | FT | 465 | $5.00 | $8.85 | $5.00 |
| 41 | School symbol marking, 96" (644E01110) | EACH | 4 | $500.00 | $880.00 | $500.00 |
| 42 | Parking lot stall marking (644E01200) | FT | 3,475 | $2.00 | $2.45 | $2.00 |
| 43 | Lane arrow (644E01300) | EACH | 19 | $120.00 | $105.00 | $120.00 |
| 44 | Word on pavement, 96" (644E01410) | EACH | 6 | $150.00 | $155.00 | $150.00 |
| 45 | Dotted line, 6" (644E01510) | FT | 240 | $2.00 | $2.75 | $2.00 |
| 46 | Yield line (644E20800) | FT | 80 | $15.00 | $12.50 | $15.00 |
| 47 | Edge line, 6" (646E10010) | MI | 0.32 | $20,000 | $14,250 | $20,000 |
| 48 | Center line (646E10200) | MI | 0.16 | $20,000 | $20,650 | $20,000 |
| 49 | Handicap symbol marking, type B125 (647E20212) | EACH | 2 | $500.00 | $225.00 | $500.00 |
| 50 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 300 | $95.00 | $75.00 | $91.00 |
| 51 | Work zone marking sign (614E12460) | EACH | 86 | $90.00 | $88.02 | $88.00 |
| 52 | Asphalt concrete for maintaining traffic (614E13000) | CY | 17 | $350.00 | $190.00 | $215.00 |
| 53 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $1,500.00 | $1,500.00 | $1,500.00 |
| 54 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 0.86 | $1,495.00 | $1,500.00 | $1,500.00 |
| 55 | Work zone center line, class III, 642 paint (614E21550) | MI | 15.87 | $855.00 | $860.00 | $845.00 |
| 56 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 1,030 | $1.92 | $2.00 | $1.75 |
| 57 | Work zone stop line, class III, 642 paint (614E26610) | FT | 186 | $8.50 | $9.00 | $8.00 |
| 58 | Portions of structure removed (202E11300) | CY | 0.50 | $6,660.00 | $6,660.00 | $18,800 |
| 59 | Class QC2 concrete, misc.: accelerating admixture (511E53012) | CY | 0.50 | $9,360.00 | $9,360.00 | $25,200 |
| 60 | Polymer modified asphalt expansion joint system (846E00110) | CF | 18 | $591.00 | $591.00 | $700.00 |
| 61 | Polymer modified asphalt expansion joint system (846E00110) | CF | 14 | $605.00 | $605.29 | $725.00 |
| 62 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $28,942 | $15,000 | $24,999 |
| 63 | Maintaining traffic (614E11000) | LS | 1 | $350,000 | $453,000 | $396,927 |
| 64 | Field office, type C (619E16020) | MNTH | 18 | $2,500.00 | $3,000.00 | $3,500.00 |
| 65 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10,000 | $5,000.00 | $8,500.00 |
| 66 | Mobilization (624E10000) | LS | 1 | $200,000 | $115,000 | $65,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way